LAK-SR 174-00.00
LAK County · est $1.9M
Bid dateThursday, January 29—
Awarded toKARVO COMPANIES INC$1.73M
LAK County · est $1.9M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10201 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (2918 CY | $168 | $490k | 28% |
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 2,066 CY | $198 | $409k | 24% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (3 | 58,898 SY | $3.25 | $191k | 11% |
| 624E10000 MOBILIZATION | 1 LS | $115,000 | $115k | 7% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $100,000 | $100k | 6% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN | 300 CY | $300 | $90k | 5% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 374 CY | $100 | $37k | 2% |
| 255E16001 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 110 SY | $300 | $33k | 2% |
| 441E70101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), AS Section 4 - PAVEMENT - Totals Awd $1,347,926.10 2 $1,414,081.00 3 $1,564,326.70 4 $1,394,068.00 5 $1,369,388.16 6 $1,511,220.50 7 $1,680,208.00 8 $1,608,087.00 | 45 CY | $675 | $30k | 2% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 400 SY | $75 | $30k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 26 more items below.
| Item | Quantity | R1Karvo Companies INC | R2Ronyak Paving INC | R3Geauga Highway CO | R4Shelly Company | R5Kokosing Construction Company INC | R6Specialized Construction INC | R7Barbicas Construction Company INC | R8Phillips Paving LLC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 441E10201 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (2918 CY | $168 | $187 | $187 | $170 | $177 | $210 | $200 | $185 | 30% |
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 2,066 CY | $198 | $200 | $210 | $215 | $208 | $220 | $270 | $225 | 25% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (3 | 58,898 SY | $3.25 | $2.50 | $4.65 | $2.50 | $2.47 | $3.15 | $5.00 | $5.00 | 12% |
| 624E10000 MOBILIZATION | 1 LS | $115,000 | $80,000 | $10,000 | $40,000 | $89,800 | $90,000 | $65,000 | $121,260 | 7% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $100,000 | $88,000 | $26,619 | $190,000 | $140,978 | $25,000 | $100,000 | $197,000 | 6% |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN | 300 CY | $300 | $485 | $500 | $400 | $450 | $340 | $250 | $400 | 5% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 374 CY | $100 | $100 | $120 | $100 | $80.00 | $100 | $100 | $125 | 2% |
| 255E16001 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 110 SY | $300 | $260 | $150 | $425 | $155 | $290 | $150 | $300 | 2% |
| 441E70101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), AS Section 4 - PAVEMENT - Totals Awd $1,347,926.10 2 $1,414,081.00 3 $1,564,326.70 4 $1,394,068.00 5 $1,369,388.16 6 $1,511,220.50 7 $1,680,208.00 8 $1,608,087.00 | 45 CY | $675 | $450 | $320 | $450 | $440 | $395 | $750 | $400 | 2% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 400 SY | $75.00 | $80.00 | $65.50 | $90.00 | $98.00 | $55.00 | $30.00 | $100 | 2% |
| 614E11111 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 160 HOUR | $125 | $125 | $50.00 | $120 | $100 | $100 | $80.00 | $100 | 1% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC Section 8 - MAINTENANCE OF TRAFFIC - Totals Awd $58,704.59 2 $48,112.80 3 $33,180.59 4 $60,797.00 5 $51,440.59 6 $53,836.00 7 $54,482.00 8 $58,880.59 | 100 CY | $200 | $60.00 | $50.00 | $120 | $125 | $130 | $200 | $200 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $14,891 | $12,469 | $11,568 | $10,000 | $7,180 | $13,000 | $20,000 | $40,000 | 1% |
| 638E10800 VALVE BOX ADJUSTED TO GRADE Section 5 - WATER WORK - Totals Awd $14,000.00 2 $8,400.00 3 $10,500.00 4 $9,800.00 5 $9,100.00 6 $15,400.00 7 $7,000.00 8 $14,000.00 | 14 EACH | $1,000 | $600 | $750 | $700 | $650 | $1,100 | $500 | $1,000 | 1% |
| 209E72051 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 7.61 MILE | $1,725 | $750 | $4,500 | $1,500 | $3,100 | $6,400 | $1,000 | $500 | 1% |
| 407E13900 TACK COAT, 702.13 | 5,303 GAL | $2.30 | $2.00 | $3.00 | $2.00 | $3.00 | $3.40 | $4.00 | $2.00 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 3,539 GAL | $2.30 | $4.00 | $3.00 | $3.00 | $2.90 | $3.40 | $4.00 | $2.00 | 0% |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 6 EACH | $1,300 | $1,000 | $1,150 | $1,200 | $3,300 | $1,400 | $1,000 | $1,800 | 0% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 9 SNMT | $850 | $1,225 | $950 | $1,000 | $1,100 | $1,100 | $850 | $1,250 | 0% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $7,500.00 2 $7,500.00 3 $7,500.00 4 $7,500.00 5 $7,500.00 6 $7,500.00 7 $7,500.00 8 $7,500.00 | 7,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 0% |
| Item | Quantity | R1Karvo Companies INC | R2Ronyak Paving INC | R3Geauga Highway CO | R4Shelly Company | R5Kokosing Construction Company INC | R6Specialized Construction INC | R7Barbicas Construction Company INC | R8Phillips Paving LLC |
|---|---|---|---|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $3,500 | $2,000 | $1,500 | $2,500 | $2,700 | $7,500 | $5,000 | $100 |
| 202E32001 CURB REMOVED, AS PER PLAN | 100 FT | $50.00 | $30.00 | $6.00 | $10.00 | $9.00 | $20.00 | $10.00 | $20.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 170 CY | $10.00 | $35.00 | $80.00 | $30.00 | $70.00 | $220 | $40.00 | $25.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 178 CY | $40.00 | $45.00 | $90.00 | $60.00 | $94.00 | $45.00 | $60.00 | $100 |
| 204E50000 GEOTEXTILE FABRIC | 410 SY | $1.00 | $2.00 | $3.50 | $2.00 | $6.50 | $25.00 | $2.00 | $1.00 |
| 204E51000 GEOGRID | 410 SY | $2.00 | $2.00 | $5.00 | $5.00 | $7.25 | $25.00 | $3.00 | $2.00 |
| 623E39500 MONUMENT ASSEMBLY ADJUSTED TO GRADE Section 1 - ROADWAY - Totals Awd $34,177.25 2 $28,357.50 3 $70,950.00 4 $35,565.00 5 $65,160.50 6 $126,314.00 7 $37,140.00 8 $31,185.00 | 2 EACH | $1,250 | $1,025 | $750 | $1,000 | $1,850 | $1,100 | $2,000 | $1,000 |
| 611E98635 CATCH BASIN RECONSTRUCTED TO GRADE, AS PER PLAN | 2 EACH | $1,750 | $2,585 | $1,800 | $1,500 | $3,850 | $1,650 | $1,800 | $3,400 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL Section 3 - DRAINAGE - Totals Awd $17,300.00 2 $21,170.00 3 $15,500.00 4 $18,200.00 5 $35,500.00 6 $16,700.00 7 $13,000.00 8 $27,600.00 | 2,000 LB | $3.00 | $5.00 | $2.50 | $4.00 | $4.00 | $2.50 | $1.70 | $5.00 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 150 FT | $5.00 | $5.00 | $3.50 | $5.00 | $4.00 | $3.00 | $3.00 | $8.00 |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 24 CY | $25.00 | $50.00 | $120 | $60.00 | $99.00 | $75.00 | $65.00 | $100 |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 75 FT | $65.00 | $45.00 | $75.00 | $90.00 | $48.00 | $80.00 | $80.00 | $125 |
| 609E14000 CURB, TYPE 2-A | 100 FT | $40.00 | $45.00 | $75.00 | $30.00 | $4.50 | $30.00 | $50.00 | $100 |
| 609E24511 CURB, TYPE 4-C, AS PER PLAN | 25 FT | $75.00 | $65.00 | $75.00 | $120 | $21.00 | $80.00 | $50.00 | $100 |
| 875E10000 LONGITUDINAL JOINT ADHESIVE | 4,004 LB | $1.00 | $2.00 | $3.50 | $2.50 | $0.75 | $1.00 | $5.00 | $2.00 |
| 642E00100 EDGE LINE, 4", TYPE 1 | 7.39 MILE | $790 | $790 | $790 | $750 | $790 | $1,100 | $750 | $790 |
| 642E00300 CENTER LINE, TYPE 1 | 3.68 MILE | $860 | $860 | $860 | $1,350 | $860 | $1,800 | $1,350 | $860 |
| 642E00500 STOP LINE, TYPE 1 Section 6 - TRAFFIC CONTROL - Totals Awd $9,826.90 2 $9,826.90 3 $9,826.90 4 $10,922.50 5 $9,826.90 6 $15,319.50 7 $10,922.50 8 $9,826.90 | 103 FT | $8.00 | $8.00 | $8.00 | $4.00 | $8.00 | $5.50 | $4.00 | $8.00 |
| 632E26501 DETECTOR LOOP, AS PER PLAN Section 7 - TRAFFIC SIGNALS - Totals Awd $3,000.00 2 $3,600.00 3 $6,800.00 4 $2,900.00 5 $2,900.00 6 $3,600.00 7 $3,000.00 8 $2,900.00 | 2 EACH | $1,500 | $1,800 | $3,400 | $1,450 | $1,450 | $1,800 | $1,500 | $1,450 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 3.68 MILE | $937 | $940 | $937 | $750 | $937 | $1,500 | $750 | $937 |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 7.39 MILE | $937 | $940 | $937 | $1,350 | $937 | $900 | $1,350 | $937 |
| 616E10000 WATER | 50 MGAL | $1.00 | $1.00 | $10.00 | $10.00 | $13.00 | $10.00 | $7.50 | $10.00 |
| 616E20000 CALCIUM CHLORIDE | 14 TON | $1.00 | $1.00 | $10.00 | $500 | $100 | $125 | $40.00 | $10.00 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 103 FT | $6.00 | $6.00 | $6.00 | $3.50 | $6.00 | $5.00 | $3.50 | $6.00 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $2,500 | $5,850 | $2,500 | $5,000 | $5,600 | $10,000 | $200 | $5,000 |
| 690E98400 SPECIAL - PRECONSTRUCTION VIDEO Section 9 - INCIDENTALS - Totals Awd $234,890.91 2 $188,818.80 3 $52,486.84 4 $247,500.00 5 $245,358.00 6 $139,880.00 7 $186,700.00 8 $365,260.00 | 1 LS | $2,500 | $2,500 | $1,800 | $2,500 | $1,800 | $1,880 | $1,500 | $2,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →