HAM-CR 196-01.89 Delhi Ave
HAM County · est $1.2M
Bid dateThursday, March 26—
Awarded toSUNESIS CONSTRUCTION CO$1.53M
HAM County · est $1.2M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 256 CY | $530 | $136k | 9% |
| 624E10000 MOBILIZATION Section 12 - INCIDENTALS - Totals Awd $149,877.48 2 $272,350.60 3 $164,025.04 4 $122,500.00 | 1 LS | $106,168 | $106k | 7% |
| AA2 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | — | $8,303 | $66k | 4% |
| 611E07400 18" CONDUIT, TYPE B | 229 FT | $257.72 | $59k | 4% |
| 870E10001 PREFABRICATED MODULAR RETAINING WALL, AS PER PLAN | 538 SF | $101.21 | $54k | 4% |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 1 EACH | $54,348 | $54k | 4% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 6 EACH | $8,031 | $48k | 3% |
| 633E65521 CABINET, TYPE 332, AS PER PLAN | 2 EACH | $22,529 | $45k | 3% |
| 632E79111 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 3 EACH | $14,770 | $44k | 3% |
| 608E12000 5" CONCRETE WALK | 3,166 SF | $13.38 | $42k | 3% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 100 more items below.
| Item | Quantity | R1Sunesis Construction CO | R2Prus Construction Company | R3John R Jurgensen Company | R4Barrett Paving Materials INC | % of bid |
|---|---|---|---|---|---|---|
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 256 CY | $530 | $274 | $530 | $525 | 13% |
| 624E10000 MOBILIZATION Section 12 - INCIDENTALS - Totals Awd $149,877.48 2 $272,350.60 3 $164,025.04 4 $122,500.00 | 1 LS | $106,168 | $40,000 | $75,000 | $40,000 | 11% |
| AA2 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | — | $8,303 | $9,075 | $8,250 | $11,100 | 7% |
| 611E07400 18" CONDUIT, TYPE B | 229 FT | $258 | $201 | $166 | $195 | 6% |
| 870E10001 PREFABRICATED MODULAR RETAINING WALL, AS PER PLAN | 538 SF | $101 | $85.69 | $113 | $105 | 5% |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL | 1 EACH | $54,348 | $59,400 | $54,000 | $68,000 | 5% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 6 EACH | $8,031 | $8,778 | $7,980 | $14,500 | 5% |
| 633E65521 CABINET, TYPE 332, AS PER PLAN | 2 EACH | $22,529 | $24,624 | $22,385 | $19,300 | 4% |
| 632E79111 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 3 EACH | $14,770 | $16,143 | $14,675 | $17,500 | 4% |
| 608E12000 5" CONCRETE WALK | 3,166 SF | $13.38 | $12.56 | $15.81 | $14.50 | 4% |
| 632E78349 COMBINATION SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 1 | 1 EACH | $41,858 | $45,749 | $41,590 | $36,400 | 4% |
| 632E71389 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 10 POLE, WITH | 1 EACH | $39,322 | $42,977 | $39,070 | $40,000 | 4% |
| 870E12500 CONCRETE COPING | 140 FT | $262 | $249 | $105 | $160 | 4% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B Section 10 - MAINTENANCE OF TRAFFIC - Totals Awd $119,130.73 2 $99,596.06 3 $107,768.60 4 $187,100.00 | 220 SY | $165 | $111 | $165 | $225 | 4% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 44 CY | $820 | $493 | $820 | $800 | 4% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 4" | 465 FT | $77.50 | $84.70 | $77.00 | $68.00 | 4% |
| 441E70200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (43 CY | $830 | $663 | $830 | $700 | 4% |
| 304E20000 AGGREGATE BASE | 200 CY | $162 | $115 | $185 | $200 | 3% |
| 203E10000 EXCAVATION | 370 CY | $77.07 | $45.87 | $90.08 | $85.00 | 3% |
| 609E26000 CURB, TYPE 6 Section 4 - PAVEMENT - Totals Awd $268,346.51 2 $165,668.78 3 $276,820.92 4 $270,515.00 | 553 FT | $50.67 | $36.96 | $57.64 | $55.00 | 3% |
| Item | Quantity | R1Sunesis Construction CO | R2Prus Construction Company | R3John R Jurgensen Company | R4Barrett Paving Materials INC |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $11,534 | $3,157 | $14,975 | $10,000 |
| 202E23000 PAVEMENT REMOVED | 654 SY | $30.68 | $26.62 | $46.49 | $30.00 |
| 202E30000 WALK REMOVED | 1,661 SF | $2.50 | $4.20 | $7.39 | $5.00 |
| 202E32000 CURB REMOVED | 290 FT | $17.70 | $20.11 | $21.82 | $22.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 291 FT | $27.32 | $79.52 | $81.80 | $35.00 |
| 202E58000 MANHOLE REMOVED | 1 EACH | $1,261 | $1,775 | $3,521 | $1,000 |
| 202E75000 FENCE REMOVED | 11 FT | $24.47 | $30.84 | $40.00 | $6.00 |
| 203E20000 EMBANKMENT | 123 CY | $40.20 | $39.22 | $56.91 | $80.00 |
| 203E35000 GRANULAR EMBANKMENT | 15 CY | $176 | $238 | $234 | $175 |
| 204E10000 SUBGRADE COMPACTION | 1,099 SY | $5.62 | $4.47 | $4.35 | $7.50 |
| 204E45000 PROOF ROLLING | 2 HOUR | $391 | $154 | $309 | $2,500 |
| 204E50000 GEOTEXTILE FABRIC | 1,092 SY | $2.23 | $4.47 | $4.62 | $2.50 |
| 517E76300 RAILING, MISC.: DECORATIVE RAILING | 140 FT | $96.00 | $110 | $96.00 | $96.00 |
| 608E52000 CURB RAMP Section 1 - ROADWAY - Totals Awd $163,771.78 2 $165,102.44 3 $222,095.76 4 $185,830.50 | 690 SF | $17.55 | $22.93 | $18.22 | $16.00 |
| 659E00300 TOPSOIL | 15 CY | $194 | $106 | $172 | $175 |
| 659E10000 SEEDING AND MULCHING | 140 SY | $10.11 | $2.19 | $35.00 | $10.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.02 TON | $1,000 | $1,650 | $1,500 | $2,000 |
| 659E31000 LIME | 0.03 ACRE | $1,000 | $550 | $200 | $500 |
| 659E35000 WATER | 0.8 MGAL | $1.39 | $1.10 | $3.00 | $1.00 |
| 659E40000 MOWING | 0.3 MSF | $100 | $110 | $1,800 | $500 |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $9,410.41 2 $6,984.93 3 $13,053.75 4 $9,230.80 | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E11110 6" SHALLOW PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 642 FT | $24.67 | $30.18 | $52.60 | $40.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 68 FT | $26.87 | $57.51 | $78.14 | $50.00 |
| 611E04400 12" CONDUIT, TYPE B | 49 FT | $305 | $170 | $237 | $185 |
| 611E98180 CATCH BASIN, NO. 3A | 2 EACH | $4,397 | $5,096 | $3,995 | $5,000 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 1 EACH | $924 | $1,384 | $1,533 | $3,000 |
| 611E99574 MANHOLE, NO. 3 Section 3 - DRAINAGE - Totals Awd $111,175.33 2 $104,500.00 3 $109,261.43 4 $110,800.00 | 2 EACH | $4,904 | $7,659 | $5,562 | $7,500 |
| 407E20000 NON-TRACKING TACK COAT | 100 GAL | $5.00 | $17.49 | $5.00 | $4.00 |
| 690E98000 SPECIAL -ADJUST EXISTING CHAMBER TO GRADE | 1 EACH | $1,291 | $707 | $3,492 | $1,500 |
| 690E98000 SPECIAL - FURNISHING AND INSTALLING 6? PLUG IN EXI | 1 EACH | $9,038 | $2,439 | $6,246 | $7,000 |
| 690E98000 SPECIAL -REMOVING EXISTING MANHOLE CURB AND COVER | 1 EACH | $2,425 | $1,081 | $3,521 | $3,000 |
| 690E98000 SPECIAL -REMOVING EXISTING VALUVE BOX | 1 EACH | $1,783 | $560 | $1,435 | $350 |
| 690E98000 SPECIAL -REMOVING FIRE HYDRANT Section 5 - WATER WORK - Totals Awd $16,194.60 2 $5,666.59 3 $16,825.27 4 $13,350.00 | 1 EACH | $1,657 | $880 | $2,130 | $1,500 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 3 EACH | $1,114 | $924 | $1,533 | $1,500 |
| 611E99700 SPECIAL - GAS VALVE BOX ADJUSTED TO GRADE Section 6 - OTHER UTILITIES - Totals Awd $3,790.54 2 $6,003.14 3 $10,733.83 4 $7,700.00 | 4 EACH | $112 | $808 | $1,533 | $800 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 51.5 FT | $15.50 | $18.70 | $17.00 | $17.00 |
| 630E08600 SIGN POST REFLECTOR | 1 EACH | $50.00 | $55.00 | $50.00 | $50.00 |
| 630E79100 SIGN HANGER ASSEMBLY, MAST ARM | 18 EACH | $449 | $237 | $215 | $215 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 4 EACH | $55.00 | $116 | $105 | $105 |
| 630E80100 SIGN, FLAT SHEET | 171.3 SF | $16.00 | $25.30 | $23.00 | $23.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 10 EACH | $15.00 | $16.50 | $15.00 | $15.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 8 EACH | $20.00 | $27.50 | $25.00 | $25.00 |
| 644E00300 CENTER LINE | 0.05 MILE | $18,000 | $19,800 | $18,000 | $18,000 |
| 644E00400 CHANNELIZING LINE, 8" | 192 FT | $3.00 | $3.30 | $3.00 | $3.00 |
| 644E00500 STOP LINE | 71 FT | $12.00 | $13.20 | $12.00 | $12.00 |
| 644E00620 CROSSWALK LINE, 12" | 413 FT | $7.00 | $7.70 | $7.00 | $7.00 |
| 644E01300 LANE ARROW | 3 EACH | $210 | $231 | $210 | $210 |
| 644E30000 REMOVAL OF PAVEMENT MARKING Section 7 - TRAFFIC CONTROL - Totals Awd $20,683.85 2 $19,785.84 3 $17,986.40 4 $17,986.40 | 160 FT | $16.45 | $18.10 | $16.45 | $16.45 |
| 625E00450 CONNECTION, FUSED PULL APART | 4 EACH | $121 | $132 | $120 | $130 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 8 EACH | $121 | $132 | $120 | $130 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 4 EACH | $121 | $132 | $120 | $130 |
| 625E18401 BRACKET ARM, 20', AS PER PLAN | 1 EACH | $1,761 | $1,925 | $1,750 | $2,200 |
| 625E18511 BRACKET ARM, 30', AS PER PLAN | 4 EACH | $3,180 | $3,476 | $3,160 | $3,600 |
| 625E23304 NO. 8 AWG 600 VOLT DISTRIBUTION CABLE | 1,008 FT | $2.16 | $2.37 | $2.15 | $5.00 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 753 FT | $2.01 | $2.20 | $2.00 | $3.00 |
| 625E25408 CONDUIT, 2", 725.051 | 66 FT | $6.29 | $6.88 | $6.25 | $14.00 |
| 625E25604 CONDUIT, 4", 725.051 | 95 FT | $11.98 | $13.09 | $11.90 | $22.00 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 5 EACH | $478 | $523 | $475 | $650 |
| 625E29002 TRENCH, 24" DEEP | 147 FT | $16.35 | $17.88 | $16.25 | $18.00 |
| 625E30706 PULL BOX, 725.08, 24" | 10 EACH | $1,313 | $1,436 | $1,305 | $1,650 |
| 625E32000 GROUND ROD | 15 EACH | $493 | $539 | $490 | $300 |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 14 EACH | $1,364 | $1,491 | $1,355 | $1,600 |
| 632E05007 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 4 EACH | $1,490 | $1,628 | $1,480 | $1,700 |
| 632E05086 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 2 EACH | $2,144 | $2,343 | $2,130 | $2,375 |
| 632E20731 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, | 12 EACH | $674 | $737 | $670 | $850 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 20 EACH | $85.55 | $93.50 | $85.00 | $50.00 |
| 632E25010 COVERING OF PEDESTRIAN SIGNAL HEAD | 12 EACH | $85.55 | $93.50 | $85.00 | $40.00 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 1,814 FT | $2.47 | $2.70 | $2.45 | $3.50 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 2,182 FT | $2.62 | $2.86 | $2.60 | $4.00 |
| 632E64021 PEDESTAL FOUNDATION, AS PER PLAN | 7 EACH | $2,999 | $3,278 | $2,980 | $1,500 |
| 632E65300 LOOP DETECTOR LEAD-IN CABLE, 2 CONDUCTOR, NO. 14 A | 1,754 FT | $2.16 | $2.37 | $2.15 | $3.00 |
| 632E66104 POWER CABLE, 3 CONDUCTOR, NO. 10 AWG | 47 FT | $6.14 | $6.71 | $6.10 | $7.00 |
| 632E69800 SERVICE CABLE, 3 CONDUCTOR, NO. 6 AWG | 224 FT | $7.25 | $7.92 | $7.20 | $9.00 |
| 632E70001 POWER SERVICE, AS PER PLAN | 2 EACH | $6,391 | $6,985 | $6,350 | $2,700 |
| 632E72141 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13, AS PER P | 1 EACH | $22,097 | $24,151 | $21,955 | $22,900 |
| 632E89921 PEDESTAL, 10.7' TALL, TRANSFORMER BASE, AS PER PLA | 7 EACH | $2,305 | $2,519 | $2,290 | $2,400 |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 2 EACH | $5,349 | $5,847 | $5,315 | $4,500 |
| 632E90400 SIGNALIZATION, MISC.: VACUUM EXCAVATION OF FOUNDAT | 4 EACH | $2,466 | $2,695 | $2,450 | $4,200 |
| 633E67101 CABINET FOUNDATION, AS PER PLAN | 2 EACH | $1,983 | $2,167 | $1,970 | $3,200 |
| 633E67200 CONTROLLER WORK PAD Section 8 - TRAFFIC SIGNALS - Totals Awd $457,075.21 2 $499,581.30 3 $454,143.05 4 $499,823.00 | 2 EACH | $1,359 | $1,485 | $1,350 | $850 |
| AA2 632E20750 ACCESSIBLE PEDESTRIAN PUSHBUTTON, (POLARA) (ALTERN | 12 EACH | $800 | $875 | $795 | $1,500 |
| AA2 633E45000 GPS (GLOBAL POSITIONING SYSTEM) CLOCK ASSEMBLY | — | $1,157 | $1,265 | $1,150 | $1,850 |
| AA2 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 2 EACH | $7,433 | $8,124 | $7,385 | $6,000 |
| AA2 809E69123 ATC CONTROLLER, AS PER PLAN, (INTELIGHT) (ALTERNAT Section 9 - TRAFFIC SIGNALS ALTERNATES - Totals Awd $104,811.58 2 $114,554.00 3 $104,140.00 4 $138,100.00 | 2 EACH | $5,802 | $6,342 | $5,765 | $7,800 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 16 HOUR | $110 | $158 | $170 | $100 |
| 614E18002 MAINTAINING TRAFFIC, MISC.:TEMPORARY SIGNAL VEHICL | 1 LS | $10,000 | $11,000 | $10,000 | $48,000 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $16,723 | $2,211 | $4,751 | $20,000 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 75 SY | $50.00 | $66.61 | $50.00 | $50.00 |
| 516E31000 JOINT SEALER | 25 FT | $40.00 | $23.59 | $40.00 | $40.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 20 CY | $245 | $147 | $237 | $240 |
| 870E11000 WALL EXCAVATION | 33 CY | $88.64 | $97.46 | $112 | $115 |
| 870E11100 NATURAL SOIL | 7 CY | $114 | $118 | $246 | $150 |
| 870E12000 6" DRAINAGE PIPE, PERFORATED | 140 FT | $4.28 | $11.00 | $20.49 | $16.00 |
| 870E12100 6" DRAINAGE PIPE, NON-PERFORATED | 12 FT | $43.59 | $63.08 | $120 | $50.00 |
| 870E14000 ON-SITE ASSISTANCE | 2 DAY | $0.02 | $305 | $400 | $1,000 |
| 870E15000 PMRW INSPECTION AND COMPACTION TESTING Section 11 - RETAINING WALLS - Totals Awd $107,690.38 2 $97,662.02 3 $97,760.56 4 $100,625.00 | 1 LS | $2,100 | $1,273 | $2,308 | $2,500 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $9,229 | $18,300 | $7,342 | $4,500 |
| 108E10000 CPM PROGRESS SCHEDULE | 1 LS | $4,580 | $5,185 | $5,916 | $3,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $18,500 | $198,306 | $66,444 | $60,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $11,400 | $10,560 | $9,324 | $15,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →