CLE-IR 275 Rest Areas TP
CLE County · est $7.4M
Bid dateFriday, April 17—
Awarded toGREAT LAKES CONSTRUCTION CO$7.51M
CLE County · est $7.4M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 452E14020 10" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 24,686 SY | $81 | $2.00M | 27% |
| 304E20000 AGGREGATE BASE | 5,495 CY | $85.33 | $469k | 6% |
| 624E10000 MOBILIZATION Section 11 - INCIDENTALS - Totals Awd $591,150.00 2 $333,683.79 3 $509,500.00 | 1 LS | $370,000 | $370k | 5% |
| 203E10000 EXCAVATION | 10,585 CY | $30.5 | $323k | 4% |
| 442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 841 CY | $347 | $292k | 4% |
| 625E29000 TRENCH | 15,362 FT | $16.35 | $251k | 3% |
| 839E29000 TRENCH DRAIN, TYPE A WITH STANDARD GRATE Section 3 - DRAINAGE - Totals Awd $781,117.75 2 $802,835.55 3 $889,364.75 | 846 FT | $235 | $199k | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 735 CY | $265 | $195k | 3% |
| 442E10001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 502 CY | $375 | $188k | 3% |
| 202E23000 PAVEMENT REMOVED | 17,570 SY | $10.25 | $180k | 2% |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 117 more items below.
| Item | Quantity | R1Great Lakes Construction CO | R2Sunesis Construction CO | R3Prus Construction Company | % of bid |
|---|---|---|---|---|---|
| 452E14020 10" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 24,686 SY | $81.00 | $87.70 | $85.75 | 35% |
| 304E20000 AGGREGATE BASE | 5,495 CY | $85.33 | $113 | $82.78 | 8% |
| 624E10000 MOBILIZATION Section 11 - INCIDENTALS - Totals Awd $591,150.00 2 $333,683.79 3 $509,500.00 | 1 LS | $370,000 | $162,815 | $200,000 | 7% |
| 203E10000 EXCAVATION | 10,585 CY | $30.50 | $30.88 | $22.15 | 6% |
| 442E10100 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 841 CY | $347 | $315 | $347 | 5% |
| 625E29000 TRENCH | 15,362 FT | $16.35 | $13.25 | $11.55 | 4% |
| 839E29000 TRENCH DRAIN, TYPE A WITH STANDARD GRATE Section 3 - DRAINAGE - Totals Awd $781,117.75 2 $802,835.55 3 $889,364.75 | 846 FT | $235 | $177 | $295 | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 735 CY | $265 | $268 | $295 | 3% |
| 442E10001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 502 CY | $375 | $355 | $391 | 3% |
| 202E23000 PAVEMENT REMOVED | 17,570 SY | $10.25 | $8.33 | $9.00 | 3% |
| 625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C | 9,899 FT | $16.65 | $17.20 | $19.25 | 3% |
| 605E14020 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 10,503 FT | $14.25 | $20.75 | $18.75 | 3% |
| 204E30020 GRANULAR MATERIAL, TYPE C | 2,348 CY | $55.00 | $87.74 | $74.50 | 2% |
| 611E99010 INLET, NO. 2-A-20 | 8 EACH | $14,500 | $19,703 | $16,000 | 2% |
| 625E25400 CONDUIT, 2", 725.04 | 6,080 FT | $19.00 | $15.95 | $19.25 | 2% |
| 659E00300 TOPSOIL | 4,194 CY | $27.00 | $17.90 | $11.00 | 2% |
| 832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $290,239.83 2 $286,229.54 3 $255,893.31 | 113,069 EACH | $1.00 | $1.00 | $1.00 | 2% |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 57 EACH | $1,980 | $1,943 | $1,650 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $91,000 | $34,022 | $234,000 | 2% |
| 204E13000 EXCAVATION OF SUBGRADE | 2,498 CY | $36.19 | $37.36 | $35.01 | 2% |
| Item | Quantity | R1Great Lakes Construction CO | R2Sunesis Construction CO | R3Prus Construction Company |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $80,000 | $70,000 | $65,000 |
| 202E30000 WALK REMOVED | 3,269 SF | $1.25 | $1.38 | $2.50 |
| 202E30600 CONCRETE MEDIAN REMOVED | 36 SY | $32.00 | $40.52 | $42.00 |
| 202E32000 CURB REMOVED | 4,761 FT | $5.00 | $3.98 | $5.50 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 1,473 FT | $32.00 | $15.11 | $38.00 |
| 202E38000 GUARDRAIL REMOVED | 1,700 FT | $2.00 | $5.00 | $2.45 |
| 202E58100 CATCH BASIN REMOVED | 15 EACH | $650 | $519 | $735 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 12" DIAM | 87 FT | $25.00 | $15.91 | $32.00 |
| 202E70110 SPECIAL - PIPE CLEANOUT, 24" AND UNDER | 178 FT | $38.00 | $15.00 | $27.35 |
| 202E98100 REMOVAL MISC.: POST | 9 EACH | $120 | $77.30 | $145 |
| 203E20000 EMBANKMENT | 3,159 CY | $7.00 | $14.51 | $23.25 |
| 204E10000 SUBGRADE COMPACTION | 38,188 SY | $1.00 | $1.69 | $1.35 |
| 204E45000 PROOF ROLLING | 19 HOUR | $300 | $264 | $150 |
| 204E50000 GEOTEXTILE FABRIC, TYPE D, 712.09 | 5,634 SY | $2.25 | $1.71 | $2.35 |
| 606E15050 GUARDRAIL, TYPE MGS | 1,775 FT | $20.80 | $22.00 | $23.75 |
| 606E26050 ANCHOR ASSEMBLY, MGS TYPE B | 2 EACH | $2,620 | $2,400 | $2,915 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 5 EACH | $1,380 | $1,225 | $1,515 |
| 607E98000 FENCE, MISC.: WOODEN SLAT FENCE | 96 FT | $198 | $95.00 | $220 |
| 690E50600 SPECIAL - BOLLARD | 10 EACH | $825 | $400 | $910 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER Section 1 - ROADWAY - Totals Awd $1,081,768.75 2 $1,138,540.88 3 $1,158,589.75 | 1 LS | $25,000 | $39,627 | $95,750 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 15 SY | $112 | $182 | $333 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 12 SY | $105 | $196 | $408 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 15 CY | $170 | $150 | $435 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $200 | $85.00 | $95.00 |
| 659E00540 SEEDING AND MULCHING, CLASS 3C | 34,861 SY | $0.64 | $1.74 | $1.30 |
| 659E14000 REPAIR SEEDING AND MULCHING | 1,744 SY | $0.50 | $1.10 | $1.25 |
| 659E15000 INTER-SEEDING | 1,744 SY | $0.01 | $0.80 | $0.90 |
| 659E20000 COMMERCIAL FERTILIZER | 4.87 TON | $1,000 | $700 | $775 |
| 659E31000 LIME | 7.21 ACRE | $200 | $10.00 | $11.00 |
| 659E35000 WATER | 194 MGAL | $1.00 | $1.00 | $1.10 |
| 670E00500 SLOPE EROSION PROTECTION | 2,906 SY | $1.95 | $1.45 | $1.65 |
| 670E00720 DITCH EROSION PROTECTION MAT, TYPE B | 87 SY | $1.95 | $1.45 | $1.65 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $3,500 | $1,500 | $3,635 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $9,000 | $7,200 | $7,500 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $10,000 | $9,888 | $10,875 |
| 503E21104 UNCLASSIFIED EXCAVATION, INCLUDING ROCK | 50 CY | $150 | $119 | $71.00 |
| 602E20000 CONCRETE MASONRY | 0.8 CY | $2,850 | $3,322 | $3,710 |
| 605E13500 6" ROCK CUT UNDERDRAINS | 3,350 FT | $22.50 | $28.93 | $41.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 1,155 FT | $25.00 | $21.73 | $35.00 |
| 611E01500 6" CONDUIT, TYPE F | 116 FT | $40.00 | $29.03 | $49.25 |
| 611E04400 12" CONDUIT, TYPE B | 450 FT | $160 | $118 | $81.75 |
| 611E04400 12" CONDUIT, TYPE B, 706.02 | 10 FT | $310 | $337 | $415 |
| 611E05900 15" CONDUIT, TYPE B | 210 FT | $170 | $136 | $120 |
| 611E07400 18" CONDUIT, TYPE B | 232 FT | $200 | $128 | $125 |
| 611E08200 18" CONDUIT, TYPE F, 707.05 TYPE C, 707.21, OR 707 | 74 FT | $305 | $192 | $135 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $5,000 | $2,532 | $3,775 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 4 EACH | $650 | $727 | $675 |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $5,900 | $4,750 | $6,175 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 2 EACH | $650 | $582 | $1,000 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 8 EACH | $425 | $444 | $635 |
| 253E02000 PAVEMENT REPAIR | 68 CY | $850 | $1,100 | $1,210 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 4" | 7,723 SY | $10.00 | $9.00 | $10.00 |
| 407E20000 NON-TRACKING TACK COAT | 1,877 GAL | $4.00 | $5.00 | $5.00 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 537 CY | $90.58 | $134 | $89.86 |
| 452E12010 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 150 SY | $160 | $91.00 | $175 |
| 609E28000 CURB, TYPE 7 | 3,112 FT | $29.00 | $32.36 | $30.00 |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) Section 4 - PAVEMENT - Totals Awd $1,455,773.52 2 $1,610,990.98 3 $1,510,977.00 | 4,804 FT | $1.38 | $1.64 | $3.00 |
| 625E00450 CONNECTION, FUSED PULL APART | 114 EACH | $120 | $196 | $171 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 57 EACH | $120 | $190 | $171 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 15 EACH | $118 | $173 | $182 |
| 625E10503 LIGHT POLE (INSTALLATION ONLY), AS PER PLAN, AT20B | 57 EACH | $475 | $920 | $660 |
| 625E10503 LIGHT POLE (INSTALLATION ONLY), AS PER PLAN, TOWER | 10 EACH | $575 | $2,760 | $2,200 |
| 625E15000 LIGHT TOWER FOUNDATION, 36" X 15' DEEP | 2 EACH | $7,350 | $9,937 | $11,000 |
| 625E15700 LIGHT TOWER FOUNDATION, MISC.: 36" X 10' DEEP | 8 EACH | $6,250 | $5,852 | $8,250 |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 509 FT | $4.30 | $5.40 | $5.50 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 11,970 FT | $2.20 | $2.05 | $1.65 |
| 625E25402 CONDUIT, 2", 725.05 | 93 FT | $6.35 | $6.45 | $14.30 |
| 625E25900 CONDUIT, JACKED OR DRILLED, 2", 725.04 | 299 FT | $54.00 | $66.15 | $33.00 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 57 EACH | $480 | $140 | $330 |
| 625E26263 LUMINAIRE, HIGH MAST, SOLID STATE (LED), AS PER PL | 20 EACH | $1,205 | $1,306 | $1,210 |
| 625E30700 PULL BOX, 725.08, 18" | 24 EACH | $1,080 | $1,125 | $1,540 |
| 625E32000 GROUND ROD | 77 EACH | $430 | $273 | $440 |
| 625E34001 POWER SERVICE, AS PER PLAN | 1 EACH | $13,320 | $7,797 | $17,600 |
| 625E34450 CONTROL CENTER CABINET, COMPLETE | 2 EACH | $6,390 | $6,256 | $11,000 |
| 625E36010 UNDERGROUND WARNING MARKING TAPE | 15,362 FT | $1.70 | $3.45 | $1.65 |
| 625E76000 ARC FLASH CALCULATIONS AND LABEL, CC-NB CIRCUIT C | 2 EACH | $280 | $2,300 | $4,400 |
| 632E69100 POWER CABLE, 1 CONDUCTOR, NO. 4 AWG Section 5 - LIGHTING - Totals Awd $995,529.65 2 $1,028,226.45 3 $1,001,134.75 | 6,429 FT | $3.55 | $8.80 | $3.30 |
| 620E00500 DELINEATOR, POST GROUND MOUNTED | 59 EACH | $75.00 | $77.34 | $82.50 |
| 621E00100 RPM | 275 EACH | $39.30 | $65.00 | $42.90 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BI-DIRECTIONAL) | 28 EACH | $12.50 | $13.00 | $16.50 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 525.5 FT | $16.00 | $16.50 | $17.60 |
| 630E06400 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, S4X7.7 | 72.2 FT | $35.00 | $36.09 | $38.50 |
| 630E07000 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W8X18 | 201.8 FT | $60.00 | $61.87 | $66.00 |
| 630E07500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X22 | 105.3 FT | $70.00 | $72.19 | $77.00 |
| 630E08600 SIGN POST REFLECTOR, (RED) | 14 EACH | $45.00 | $46.41 | $49.50 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 16 EACH | $720 | $742 | $792 |
| 630E80100 SIGN, FLAT SHEET | 205.4 SF | $20.00 | $20.62 | $22.00 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 628 SF | $26.00 | $26.81 | $28.60 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 16 EACH | $980 | $1,212 | $1,293 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 7 EACH | $15.00 | $15.47 | $16.50 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 7 EACH | $20.00 | $20.62 | $22.00 |
| 644E00720 CHEVRON MARKING | 188 FT | $7.00 | $7.00 | $7.70 |
| 807E14010 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, EDG | 0.91 MILE | $4,100 | $4,100 | $4,510 |
| 807E14310 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, CHA | 3,104 FT | $2.20 | $2.20 | $2.42 |
| 807E14410 WET REFLECTIVE THERMOPLASTIC PAVEMENT MARKING, DOT | 3,180 FT | $0.85 | $0.85 | $0.94 |
| 850E10010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $1,500 | $1,500 | $1,650 |
| 850E10110 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $1.00 | $1.00 | $1.10 |
| 850E10130 GROOVING FOR 12" RECESSED PAVEMENT MARKING Section 6 - TRAFFIC CONTROL - Totals Awd $119,392.30 2 $132,291.41 3 $134,847.98 | — | $1.75 | $1.75 | $1.95 |
| 625E29010 TRENCH, 30" DEEP | 2,515 FT | $16.95 | $17.85 | $19.25 |
| 625E36010 UNDERGROUND WARNING MARKING TAPE | 2,515 FT | $1.70 | $3.45 | $1.65 |
| 809E01900 ITS PULL BOX WITH PAD AND STANDARD LID ASSEMBLY, 3 | 2 EACH | $4,070 | $4,560 | $4,950 |
| 809E02000 32" ITS PULL BOX WITH PAD AND STANDARD LID ASSEMBL | 2 EACH | $4,040 | $4,620 | $4,950 |
| 809E20020 MICRO-DUCT PATHWAY, 4 CELL 14/10 | 2,515 FT | $6.00 | $14.80 | $17.60 |
| 809E22000 MICRO-DUCT PATHWAY, JACKED OR DRILLED, 4 CELL 14/1 | 541 FT | $40.50 | $55.50 | $22.00 |
| 809E70000 MAINTAINING ITS DURING CONSTRUCTION Section 7 - TRAFFIC SURVEILLANCE - Totals Awd $106,125.25 2 $154,127.00 3 $134,579.50 | 1 LS | $6,000 | $14,950 | $6,050 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 150 HOUR | $100 | $75.00 | $132 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 25 CY | $350 | $473 | $275 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $759 | $759 | $835 |
| 616E10000 WATER Section 8 - MAINTENANCE OF TRAFFIC - Totals Awd $34,353.80 2 $32,658.70 3 $37,445.00 | 30 MGAL | $50.00 | $15.98 | $25.00 |
| 645E00118 EDGE LINE, 6", TYPE A4 | 1.13 MILE | $23,000 | $23,000 | $25,300 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 314 FT | $4.00 | $4.00 | $4.40 |
| 646E20200 PARKING LOT STALL MARKING | 4,470 FT | $1.75 | $1.75 | $1.95 |
| 646E20320 WRONG WAY ARROW | 4 EACH | $200 | $200 | $220 |
| 850E20010 GROOVING FOR 6" RECESSED PAVEMENT MARKING | — | $2,500 | $2,500 | $2,750 |
| 850E20130 GROOVING FOR 12" RECESSED PAVEMENT MARKING Section 10 - ITEMS OF WORK (OPTION B: RIGID) - Totals Awd $2,038,573.50 2 $2,203,969.70 3 $2,159,844.50 | — | $1.00 | $1.00 | $1.10 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $55,000 | $35,246 | $51,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $75,150 | $101,600 | $24,000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →