PER-CR 18-00.90
PER County · est $0.4M
Bid dateThursday, May 17—
PER County · est $0.4M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 42 more items below.
| Item | Quantity | R1Mc Connell Contracting INC | R2Buds INC | R3Righter Company INC | R4Shelly & Sands INC | R5Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|---|
| 515E10071 PRESTRESSED CONCRETE NON-COMPOSITE BOX BEAM BRIDGE | 7 EACH | $13,000 | $13,600 | $15,200 | $13,244 | $16,500 | 29% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 88 CY | $410 | $394 | $650 | $660 | $850 | 12% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $30,000 | $22,000 | $15,000 | $19,000 | $25,000 | 10% |
| 517E70000 |
| Item | Quantity | R1Mc Connell Contracting INC | R2Buds INC | R3Righter Company INC | R4Shelly & Sands INC | R5Complete General Construction Company |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,000 | $2,000 | $4,000 | $670 | $2,000 |
| 202E23010 PAVEMENT REMOVED, ASPHALT | 54 SY | $5.00 | $25.00 | $20.00 | $21.00 | $30.00 |
| 202E38000 GUARDRAIL REMOVED | 100 FT | $2.50 | $2.00 | $5.00 | $3.00 | $2.60 |
| 203E10000 EXCAVATION | 167 CY | $18.00 | $12.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 133 FT |
| $130 |
| $118 |
| $122 |
| $133 |
| $135 |
| 6% |
| 507E00200 STEEL PILES HP12X53, FURNISHED | 525 FT | $30.00 | $26.00 | $40.00 | $25.00 | $28.00 | 5% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $15,000 | $16,000 | $15,000 | $28,900 | $13,000 | 5% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 11,229 LB | $1.10 | $1.20 | $1.50 | $1.42 | $1.50 | 4% |
| 601E32210 ROCK CHANNEL PROTECTION, TYPE C WITH AGGREGATE FIL | 165 CY | $70.00 | $78.00 | $102 | $67.00 | $140 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $4,000 | $10,000 | $10,000 | $20,000 | 3% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 24 CF | $410 | $350 | $408 | $432 | $408 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 30 CY | $295 | $255 | $294 | $295 | $294 | 3% |
| 504E11101 STEEL SHEET PILING LEFT IN PLACE, AS PER PLAN | 425 SF | $20.00 | $60.00 | $30.00 | $35.00 | $35.00 | 3% |
| 512E33010 TYPE 3 WATERPROOFING | 196 SY | $35.00 | $25.00 | $29.50 | $27.00 | $29.50 | 2% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (27 CY | $250 | $255 | $249 | $270 | $250 | 2% |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 3 EACH | $2,200 | $2,000 | $2,000 | $2,100 | $1,930 | 2% |
| 203E20000 EMBANKMENT | 331 CY | $18.00 | $18.00 | $20.00 | $16.00 | $25.00 | 2% |
| 659E10000 SEEDING AND MULCHING | 1,789 SY | $3.00 | $1.80 | $2.92 | $2.00 | $2.10 | 2% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $4,000 | $7,000 | $5,000 | $5,000 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,000 | $2,000 | $3,750 | $3,968 | $5,000 | 2% |
| $50.00 |
| $16.00 |
| $20.00 |
| 204E10000 SUBGRADE COMPACTION | 63 SY | $5.00 | $3.50 | $5.00 | $10.00 | $15.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 262.5 FT | $18.00 | $16.50 | $16.50 | $17.00 | $16.40 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 4 EACH | $1,100 | $1,050 | $1,050 | $1,100 | $1,085 |
| 606E35003 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1, AS PER PLAN | 1 EACH | $3,600 | $2,700 | $2,700 | $2,800 | $3,135 |
| 659E14000 REPAIR SEEDING AND MULCHING | 89 SY | $1.00 | $0.25 | $1.00 | $1.00 | $0.40 |
| 659E20000 COMMERCIAL FERTILIZER | 0.42 TON | $625 | $600 | $625 | $725 | $500 |
| 659E31000 LIME | 0.37 ACRE | $100 | $400 | $85.00 | $163 | $100 |
| 659E35000 WATER | 10 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 660E20000 SODDING REINFORCED | 81 SY | $27.00 | $16.00 | $27.00 | $24.00 | $20.50 |
| 605E31100 AGGREGATE DRAINS | 115 FT | $8.00 | $15.00 | $15.00 | $22.00 | $15.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1 1/2" THICK | 250 SY | $18.00 | $24.00 | $30.00 | $35.00 | $15.50 |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 8 CY | $370 | $550 | $366 | $583 | $366 |
| 304E20000 AGGREGATE BASE | 10 CY | $110 | $120 | $166 | $132 | $95.00 |
| 407E10000 TACK COAT | 72 GAL | $3.00 | $2.00 | $3.08 | $3.00 | $3.08 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 54 CY | $75.00 | $98.00 | $85.00 | $68.00 | $92.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTOINAL | 8 EACH | $10.00 | $7.50 | $7.50 | $8.00 | $6.75 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 46 FT | $20.00 | $12.00 | $12.00 | $13.00 | $15.50 |
| 630E80100 SIGN, FLAT SHEET | 12 SF | $20.00 | $17.50 | $17.50 | $19.00 | $26.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $25.00 | $10.00 | $15.00 | $16.00 | $10.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $25.00 | $10.00 | $15.00 | $16.00 | $10.00 |
| 642E00100 EDGE LINE, 4", TYPE 1 | 0.18 MILE | $4,500 | $4,500 | $870 | $4,780 | $4,500 |
| 642E00300 CENTER LINE, TYPE 1 | 0.09 MILE | $9,000 | $4,500 | $1,485 | $9,524 | $9,000 |
| 614E12420 DETOUR SIGNING | 1 LS | $4,500 | $2,800 | $4,450 | $4,800 | $8,200 |
| 616E10000 WATER | 1 MGAL | $1.00 | $1.00 | $10.00 | $81.00 | $60.00 |
| 202E23500 WEARING COURSE REMOVED | 125 SY | $5.00 | $20.50 | $15.00 | $5.00 | $20.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $2,500 | $4,500 | $3,000 | $23,564 | $20,000 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $3,000 | $5,000 | $25,000 | $24,400 | $20,000 |
| 507E00250 STEEL PILES HP12X53, DRIVEN | 455 FT | $5.00 | $2.25 | $10.00 | $18.00 | $28.50 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 117 SY | $10.00 | $27.00 | $10.50 | $11.00 | $10.50 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 133 SF | $3.00 | $12.00 | $5.00 | $5.00 | $10.00 |
| 516E41100 1/8" PREFORMED BEARING PAD (9" X 12") | 14 EACH | $15.00 | $12.00 | $70.00 | $16.00 | $65.00 |
| 516E43201 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 28 EACH | $125 | $125 | $150 | $155 | $239 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 64 CY | $55.00 | $92.00 | $90.00 | $80.00 | $95.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 147 FT | $10.00 | $14.50 | $10.00 | $16.00 | $14.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 98 FT | $10.00 | $10.00 | $10.00 | $10.00 | $9.00 |
| 518E40011 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 60 FT | $10.00 | $15.00 | $15.00 | $13.00 | $10.00 |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $500 | $200 | $2,000 | $4,159 | $1,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,500 | $2,500 | $3,550 | $8,424 | $1,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E10071 PRESTRESSED CONCRETE NON-COMPOSITE BOX BEAM BRIDGE | 7 EACH | $13,000 | $91k | 24% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 88 CY | $410 | $36k | 10% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $30,000 | $30k | 8% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 133 FT | $130 | $17k | 5% |
| 507E00200 STEEL PILES HP12X53, FURNISHED | 525 FT | $30 | $16k | 4% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $15,000 | $15k | 4% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 11,229 LB | $1.1 | $12k | 3% |
| 601E32210 ROCK CHANNEL PROTECTION, TYPE C WITH AGGREGATE FIL | 165 CY | $70 | $12k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 3% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 24 CF | $410 | $10k | 3% |