ATB-US 20/SR 84-06.35/14.23
ATB County · est $1.9M
Bid dateThursday, November 8—
ATB County · est $1.9M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 6.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 33 more items below.
| Item | Quantity | R1Ronyak Paving INC | R2Koski Construction CO | R3Chagrin Valley Paving INC | % of bid |
|---|---|---|---|---|---|
| 424E12001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B, AS P | 6,318 CY | $180 | $182 | $200 | 64% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A (T=1 1 | 105,994 SY | $0.90 | $1.30 | $1.15 | 5% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A (T=1/2 | 92,849 SY | $0.90 | $1.10 | $0.90 | 5% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 2,000 SY | $35.00 | $37.00 | $50.00 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $51,000 | $99,000 |
| Item | Quantity | R1Ronyak Paving INC | R2Koski Construction CO | R3Chagrin Valley Paving INC |
|---|---|---|---|---|
| 209E60200 LINEAR GRADING | 405 STA | $10.00 | $10.00 | $20.00 |
| 659E20000 COMMERCIAL FERTILIZER | 3.04 TON | $400 | $800 | $250 |
| 659E31000 LIME | 4.65 ACRE | $10.00 | $100 | $50.00 |
| 659E35000 WATER | 121.5 MGAL | $1.00 | $0.50 | $3.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 |
| 611E98630 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $195,000 |
| 3% |
| 624E10000 MOBILIZATION | 1 LS | $48,405 | $40,000 | $103,500 | 3% |
| 644E00300 CENTER LINE | 9.58 MILE | $4,790 | $4,600 | $4,500 | 3% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 709 CY | $60.00 | $35.00 | $75.00 | 2% |
| 407E20000 NON-TRACKING TACK COAT | 17,518 GAL | $2.15 | $3.00 | $2.00 | 2% |
| 621E00100 RPM | 1,190 EACH | $24.36 | $21.75 | $21.25 | 2% |
| 644E00104 EDGE LINE, 6" | 11.04 MILE | $2,492 | $3,250 | $3,125 | 2% |
| 408E10000 PRIME COAT | 5,107 GAL | $3.50 | $3.50 | $2.00 | 1% |
| 623E39501 MONUMENT BOX ADJUSTED TO GRADE, AS PER PLAN | 27 EACH | $600 | $725 | $600 | 1% |
| 209E72001 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 583 STA | $25.00 | $6.00 | $20.00 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 15.1 MILE | $965 | $825 | $800 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $13,600 | $14,000 | $15,000 | 1% |
| 659E10000 SEEDING AND MULCHING | 22,600 SY | $0.50 | $0.50 | $1.25 | 1% |
| 644E00204 LANE LINE, 6" | 8.12 MILE | $1,375 | $1,550 | $1,500 | 1% |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 9.58 MILE | $1,100 | $825 | $800 | 1% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 10 EACH | $900 | $1,500 | $1,000 | 1% |
| 5 EACH |
| $650 |
| $2,000 |
| $1,250 |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 5 EACH | $625 | $1,350 | $750 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 952 EACH | $4.00 | $7.25 | $1.00 |
| 644E00400 CHANNELIZING LINE, 8" | 690 FT | $2.50 | $2.50 | $2.25 |
| 644E00500 STOP LINE | 148 FT | $8.00 | $6.50 | $6.15 |
| 644E00600 CROSSWALK LINE | 337 FT | $4.00 | $3.00 | $3.00 |
| 644E01000 RAILROAD SYMBOL MARKING | 1 EACH | $600 | $750 | $600 |
| 644E01100 SCHOOL SYMBOL MARKING, 72" | 2 EACH | $600 | $350 | $300 |
| 644E01300 LANE ARROW | 18 EACH | $104 | $110 | $100 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 50 HOUR | $60.00 | $70.00 | $75.00 |
| 614E12460 WORK ZONE MARKING SIGN | 35 EACH | $80.00 | $110 | $80.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 20 CY | $150 | $200 | $250 |
| 614E20010 WORK ZONE LANE LINE, CLASS I, 6" | 8.12 MILE | $595 | $625 | $600 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 8.12 MILE | $575 | $775 | $750 |
| 614E23000 WORK ZONE CHANNELIZING LINE, CLASS I, 8" | 690 FT | $0.60 | $1.00 | $0.75 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 690 FT | $0.58 | $1.00 | $0.75 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 148 FT | $3.10 | $3.00 | $3.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 148 FT | $3.00 | $3.00 | $3.00 |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $930 | $4,500 | $500 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 103 SY | $48.45 | $50.00 | $100 |
| 512E74000 REMOVAL OF EXISTING COATINGS FROM CONCRETE SURFACE | 53 SY | $72.71 | $60.00 | $100 |
| 530E00800 SPECIAL - STRUCTURES CONCRETE SPALL REMOVAL | 50 SY | $127 | $100 | $100 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 15 FT | $15.00 | $15.00 | $15.00 |
| 630E80100 SIGN, FLAT SHEET, 730.20 | 2 SF | $20.00 | $25.00 | $20.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $25.00 | $25.00 | $25.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $20.00 | $25.00 | $20.00 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $1,250 | $2,750 | $1,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,500 | $6,500 | $2,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 424E12001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B, AS P | 6,318 CY | $180 | $1.14M | 61% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A (T=1 1 | 105,994 SY | $0.9 | $95k | 5% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A (T=1/2 | 92,849 SY | $0.9 | $84k | 4% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 2,000 SY | $35 | $70k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $51,000 | $51k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $48,405 | $48k | 3% |
| 644E00300 CENTER LINE | 9.58 MILE | $4,790 | $46k | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 709 CY | $60 | $43k | 2% |
| 407E20000 NON-TRACKING TACK COAT | 17,518 GAL | $2.15 | $38k | 2% |
| 621E00100 RPM | 1,190 EACH | $24.36 | $29k | 2% |