CAR-SR 9/VAR-13.76/VAR
CAR County · est $2.1M
Bid dateThursday, February 13—
CAR County · est $2.1M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 6.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 32 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Superior Paving & Materials INC | R3Karvo Companies INC | R4Central-allied Enterprises INC | R5Shelly Company | % of bid |
|---|---|---|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 2,867 CY | $138 | $146 | $163 | $157 | $160 | 21% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (2563 CY | $130 | $140 | $149 | $153 | $145 | 17% |
| 424E12001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B, AS P | 1,591 CY | $170 | $170 | $187 | $190 | $180 | 14% |
| Item | Quantity | R1Shelly & Sands INC | R2Superior Paving & Materials INC | R3Karvo Companies INC | R4Central-allied Enterprises INC | R5Shelly Company |
|---|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 345 SF | $15.00 | $13.00 | $20.20 | $3.50 | $12.89 |
| 202E32000 CURB REMOVED | 40 FT | $85.00 | $50.00 | $31.00 | $5.00 | $50.00 |
| 209E60500 LINEAR GRADING | 8 MILE | $750 | $750 | $1,650 | $250 | $975 |
| 209E72051 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 6 MILE | $750 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $130,000 |
| $116,000 |
| $142,000 |
| $175,000 |
| $220,000 |
| 7% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 2 1/4" | 35,420 SY | $3.25 | $2.20 | $1.42 | $0.50 | $2.50 | 6% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 957 CY | $115 | $146 | $162 | $172 | $150 | 6% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 395 CY | $235 | $220 | $300 | $325 | $400 | 5% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A, 1" | 57,280 SY | $1.25 | $1.29 | $0.80 | $1.45 | $1.50 | 4% |
| 407E20000 NON-TRACKING TACK COAT | 19,213 GAL | $2.95 | $3.50 | $2.50 | $3.00 | $2.85 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $55,018 | $56,500 | $80,000 | $85,000 | $100,000 | 3% |
| 202E23500 WEARING COURSE REMOVED | 3,852 SY | $11.00 | $3.00 | $2.80 | $5.00 | $8.50 | 2% |
| 646E10200 CENTER LINE | 10.48 MILE | $3,650 | $3,560 | $3,612 | $3,612 | $3,560 | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 718 CY | $50.00 | $55.00 | $46.00 | $65.00 | $50.00 | 2% |
| 441E50401 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448) | — | $275 | $320 | $300 | $460 | $350 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 2" | 14,546 SY | $1.85 | $1.90 | $1.30 | $1.95 | $1.50 | 1% |
| 646E10010 EDGE LINE, 6" | 9.38 MILE | $2,800 | $2,752 | $3,070 | $3,070 | $2,752 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 23.8 MILE | $1,035 | $950 | $950 | $635 | $950 | 1% |
| 253E02000 PAVEMENT REPAIR | 90 CY | $270 | $210 | $300 | $390 | $341 | 1% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1 1/2" | 10,842 SY | $2.10 | $1.50 | $1.05 | $1.55 | $1.50 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 5,635 GAL | $3.75 | $4.00 | $3.45 | $3.00 | $3.75 | 1% |
| $650 |
| $1,300 |
| $500 |
| $500 |
| 607E98000 FENCE, MISC.: TEMPORARY ORANGE PLASTIC CONSTRUCTIO | 565 FT | $1.50 | $5.00 | $4.00 | $0.45 | $5.00 |
| 608E52000 CURB RAMP | 198 SF | $35.00 | $34.00 | $29.80 | $40.00 | $34.00 |
| 608E53021 DETECTABLE WARNING, AS PER PLAN | 214 SF | $70.00 | $85.00 | $27.30 | $80.00 | $85.00 |
| 659E98000 SEEDING, MISC.: CURB RAMP GRADING RESTORATION | 9 SY | $215 | $300 | $80.00 | $40.00 | $300 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 180 FT | $5.00 | $6.50 | $12.00 | $20.00 | $5.00 |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 2 | 8,000 SY | $2.45 | $1.80 | $1.50 | $1.50 | $2.00 |
| 609E26000 CURB, TYPE 6 | 4 FT | $80.00 | $60.00 | $25.75 | $15.00 | $60.00 |
| 617E20000 SHOULDER PREPARATION | 6,752 SY | $0.50 | $0.49 | $0.25 | $0.30 | $0.25 |
| 621E00100 RPM | 498 EACH | $26.50 | $31.00 | $31.00 | $28.00 | $26.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 500 EACH | $3.45 | $7.00 | $1.00 | $7.00 | $4.50 |
| 632E26500 DETECTOR LOOP | 13 EACH | $1,250 | $1,200 | $1,200 | $1,400 | $1,200 |
| 632E65200 LOOP DETECTOR LEAD-IN CABLE | 130 FT | $1.05 | $1.00 | $1.00 | $1.00 | $1.00 |
| 646E10300 CHANNELIZING LINE, 8" | 867 FT | $1.65 | $1.55 | $1.60 | $1.60 | $1.55 |
| 646E10400 STOP LINE | 601 FT | $10.50 | $10.15 | $9.00 | $9.00 | $10.15 |
| 646E10500 CROSSWALK LINE | 3,299 FT | $5.00 | $4.80 | $4.30 | $4.30 | $4.80 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 323 FT | $8.50 | $8.00 | $8.00 | $8.00 | $8.00 |
| 646E10800 ISLAND MARKING | 100 SF | $5.25 | $5.00 | $5.00 | $5.00 | $5.00 |
| 646E20000 RAILROAD SYMBOL MARKING | 2 EACH | $575 | $545 | $650 | $650 | $545 |
| 646E20100 SCHOOL SYMBOL MARKING, 72" | 4 EACH | $615 | $580 | $650 | $650 | $580 |
| 646E20300 LANE ARROW | 48 EACH | $120 | $113 | $150 | $150 | $113 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 200 HOUR | $75.00 | $70.00 | $65.00 | $75.00 | $65.00 |
| 614E12460 WORK ZONE MARKING SIGN | 45 EACH | $95.00 | $88.00 | $88.00 | $55.00 | $88.00 |
| 614E21500 WORK ZONE CENTER LINE, CLASS II, 642 PAINT | 23.8 MILE | $100 | $450 | $450 | $1,100 | $450 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 2,153 FT | $0.70 | $0.50 | $0.50 | $0.15 | $0.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 1,584 FT | $5.25 | $2.25 | $2.25 | $0.20 | $2.25 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $750 | $3,450 | $5,000 | $10,000 | $10,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $11,500 | $26,000 | $55,000 | $12,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 2,867 CY | $138 | $396k | 19% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (2563 CY | $130 | $333k | 16% |
| 424E12001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B, AS P | 1,591 CY | $170 | $270k | 13% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $130,000 | $130k | 6% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 2 1/4" | 35,420 SY | $3.25 | $115k | 5% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 957 CY | $115 | $110k | 5% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 395 CY | $235 | $93k | 4% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A, 1" | 57,280 SY | $1.25 | $72k | 3% |
| 407E20000 NON-TRACKING TACK COAT | 19,213 GAL | $2.95 | $57k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $55,018 | $55k | 3% |