CAR-SR 212-05.84
CAR County · est $0.2M
Bid dateThursday, March 26—
CAR County · est $0.2M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 42 more items below.
| Item | Quantity | R1Tucson INC | R2Bog Construction INC | R3Stanley Miller Construction Company | R4Lockhart Concrete CO | R5Ohio-west Virginia Excavating CO | R6Eclipse CO LLC | R7Amaazz Construction Ohio LLC | R8R C Construction Company And Son INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 614E12740 WORK ZONE LIGHTING SYSTEM | 2 EACH | $18,600 | $18,500 | $3,889 | $10,000 | $1,650 | $3,700 | $38,425 | $5,000 | 21% |
| 611E96600 CONDUIT, BORED OR JACKED 36" CONDUIT, TYPE A | 82 FT | $445 | $666 | $619 | $450 | $565 |
| Item | Quantity | R1Tucson INC | R2Bog Construction INC | R3Stanley Miller Construction Company | R4Lockhart Concrete CO | R5Ohio-west Virginia Excavating CO | R6Eclipse CO LLC | R7Amaazz Construction Ohio LLC | R8R C Construction Company And Son INC |
|---|---|---|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 1 EACH | $850 | $500 | $1,612 | $500 | $1,625 | $1,200 | $764 | $5,000 |
| 202E23000 PAVEMENT REMOVED | 56 SY | $15.00 | $25.00 | $26.00 | $20.00 | $18.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $890 |
| $778 |
| $1,800 |
| 21% |
| 203E20000 EMBANKMENT | 452 CY | $25.00 | $25.00 | $32.25 | $30.00 | $48.50 | $31.50 | $37.40 | $65.00 | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $6,500 | $23,444 | $29,000 | $35,000 | $28,000 | $9,744 | $25,000 | 6% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 13 CY | $540 | $600 | $481 | $531 | $610 | $1,049 | $659 | $650 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $7,000 | $7,500 | $19,293 | $29,000 | $25,000 | $17,079 | $19,781 | $12,500 | 4% |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT | 48 FT | $145 | $45.00 | $144 | $100 | $95.00 | $73.00 | $85.80 | $350 | 4% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 7 CY | $913 | $800 | $973 | $1,131 | $2,200 | $2,965 | $1,903 | $650 | 4% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $618 | $150 | $60.00 | $220 | $386 | $275 | $628 | $25.00 | 4% |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $2,000 | $500 | $556 | $500 | $500 | $500 | $2,408 | $100 | 3% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 34 SY | $175 | $130 | $92.00 | $80.00 | $385 | $150 | $247 | $175 | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 175 FT | $27.00 | $26.00 | $27.34 | $22.00 | $27.00 | $25.50 | $35.10 | $40.00 | 3% |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 2 EACH | $2,300 | $2,100 | $2,917 | $2,350 | $2,450 | $2,400 | $2,470 | $2,500 | 3% |
| 202E11201 PORTIONS OF STRUCTURE REMOVED, AS PER PLAN | 1 LS | $4,000 | $7,500 | $2,322 | $2,900 | $1,625 | $1,500 | $9,464 | $5,000 | 2% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 11 CY | $362 | $500 | $373 | $320 | $244 | $340 | $368 | $400 | 2% |
| 622E41000 PORTABLE BARRIER, 32" | 140 FT | $28.00 | $20.00 | $67.00 | $32.00 | $64.00 | $54.00 | $38.40 | $30.00 | 2% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 1,792 LB | $2.00 | $2.00 | $1.75 | $1.00 | $2.00 | $5.50 | $1.90 | $3.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $8,000 | $3,200 | $20,000 | $10,000 | $8,200 | $3,005 | $16,000 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,000 | $2,500 | $2,167 | $4,000 | $5,000 | $3,500 | $7,451 | $2,500 | 2% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (3 CY | $982 | $1,200 | $1,010 | $475 | $509 | $940 | $998 | $2,000 | 2% |
| $22.50 |
| $28.60 |
| $20.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 12 FT | $15.00 | $50.00 | $22.00 | $30.00 | $49.00 | $51.50 | $41.80 | $200 |
| 203E10000 EXCAVATION | 51 CY | $25.00 | $50.00 | $36.00 | $30.00 | $38.00 | $26.00 | $31.40 | $20.00 |
| 204E10000 SUBGRADE COMPACTION | 64 SY | $3.50 | $3.00 | $1.00 | $2.00 | $4.00 | $7.50 | $4.10 | $2.00 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 70 FT | $4.00 | $10.00 | $5.60 | $5.00 | $11.01 | $11.50 | $11.00 | $40.00 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 1 EACH | $1,400 | $1,500 | $1,417 | $1,100 | $1,390 | $1,325 | $1,647 | $1,750 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,150 | $1,200 | $1,167 | $1,000 | $1,150 | $1,100 | $1,098 | $1,850 |
| 601E32210 ROCK CHANNEL PROTECTION, TYPE C WITH AGGREGATE FIL | 9 CY | $125 | $100 | $203 | $125 | $218 | $126 | $197 | $100 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $100 | $50.00 | $100 | $200 | $55.00 | $106 | $65.90 | $20.00 |
| 659E00300 TOPSOIL | 78 CY | $35.00 | $30.00 | $46.30 | $30.00 | $55.00 | $57.00 | $101 | $20.00 |
| 659E10000 SEEDING AND MULCHING | 701 SY | $3.50 | $7.00 | $3.65 | $1.00 | $4.00 | $5.00 | $8.10 | $3.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 35 SY | $1.00 | $1.00 | $1.00 | $1.00 | $7.00 | $5.00 | $15.40 | $0.20 |
| 659E20000 COMMERCIAL FERTILIZER | 0.09 TON | $700 | $1,000 | $660 | $800 | $900 | $637 | $548 | $1,200 |
| 659E31000 LIME | 0.14 ACRE | $500 | $200 | $575 | $600 | $1,600 | $79.00 | $108 | $800 |
| 659E35000 WATER | 3.8 MGAL | $1.00 | $1.00 | $1.00 | $50.00 | $495 | $1.00 | $13.20 | $1.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.8 CY | $1,850 | $1,500 | $4,623 | $1,000 | $2,100 | $1,286 | $1,069 | $4,500 |
| 605E31100 AGGREGATE DRAINS | 20 FT | $25.00 | $20.00 | $26.00 | $20.00 | $39.00 | $49.00 | $21.40 | $10.00 |
| 304E20000 AGGREGATE BASE | 27 CY | $80.00 | $165 | $175 | $50.00 | $110 | $81.00 | $117 | $100 |
| 407E10000 TACK COAT | 2 GAL | $4.00 | $10.00 | $4.00 | $10.00 | $312 | $4.00 | $4.00 | $20.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 23 GAL | $108 | $10.00 | $111 | $20.00 | $31.00 | $100 | $109 | $25.00 |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 2 CY | $1,380 | $1,500 | $1,420 | $500 | $715 | $1,300 | $1,403 | $2,000 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 4 EACH | $8.00 | $20.00 | $25.00 | $10.00 | $8.00 | $8.00 | $9.30 | $20.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 13.6 FT | $27.00 | $35.00 | $22.50 | $21.00 | $27.50 | $26.50 | $16.50 | $75.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 2 EACH | $140 | $150 | $77.00 | $69.00 | $130 | $160 | $65.90 | $200 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 1 EACH | $140 | $100 | $125 | $123 | $11.00 | $108 | $22.00 | $50.00 |
| 646E10010 EDGE LINE, 6" | 0.03 MILE | $24,000 | $100,000 | $24,658 | $19,000 | $24,200 | $120,087 | $24,360 | $45,000 |
| 646E10200 CENTER LINE | 0.01 MILE | $40,000 | $100,000 | $40,869 | $22,000 | $40,000 | $120,235 | $40,380 | $45,000 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $70.00 | $60.00 | $75.00 | $50.00 | $115 | $68.50 | $87.80 | $25.00 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL | 4 EACH | $50.00 | $20.00 | $11.00 | $10.00 | $50.00 | $10.00 | $50.50 | $25.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 4 EACH | $52.00 | $20.00 | $23.00 | $21.00 | $53.00 | $22.00 | $53.20 | $25.00 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.18 MILE | $14,800 | $15,000 | $11,889 | $11,000 | $17,300 | $11,271 | $15,013 | $12,500 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.09 MILE | $13,600 | $15,000 | $9,889 | $10,000 | $15,600 | $9,375 | $13,888 | $12,500 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 51 FT | $13.00 | $25.00 | $7.00 | $6.00 | $13.00 | $6.50 | $13.20 | $50.00 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $1,800 | $3,000 | $2,322 | $29,000 | $5,000 | $8,500 | $5,950 | $7,500 |
| 616E10000 WATER | 10 MGAL | $1.00 | $1.00 | $1.00 | $50.00 | $470 | $13.50 | $43.90 | $1.00 |
| 503E21100 UNCLASSIFIED EXCAVATION | 69 CY | $25.00 | $35.00 | $47.00 | $50.00 | $35.00 | $55.50 | $124 | $25.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 27 SY | $41.00 | $30.00 | $43.00 | $20.00 | $21.00 | $35.00 | $27.40 | $50.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 10 SF | $27.00 | $10.00 | $1.55 | $5.00 | $28.00 | $23.00 | $19.40 | $20.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 11 CY | $135 | $110 | $220 | $50.00 | $148 | $140 | $272 | $85.00 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,500 | $6,000 | $11,245 | $20,000 | $5,000 | $15,071 | $3,294 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 614E12740 WORK ZONE LIGHTING SYSTEM | 2 EACH | $18,600 | $37k | 17% |
| 611E96600 CONDUIT, BORED OR JACKED 36" CONDUIT, TYPE A | 82 FT | $445 | $36k | 17% |
| 203E20000 EMBANKMENT | 452 CY | $25 | $11k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $10k | 5% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 13 CY | $540 | $7k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $7,000 | $7k | 3% |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT | 48 FT | $145 | $7k | 3% |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 7 CY | $913 | $6k | 3% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $618 | $6k | 3% |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $2,000 | $6k | 3% |