Ohio DOT · bid history
| Result | Project | County | Let | Their bid | Winning bid |
|---|---|---|---|---|---|
| Rank 8of 10 | ROS-SF5-00.00 ODNRDrainage | ROS | Dec 2020 | $187k | $133k |
| Rank 6of 9 | TUS-SR 516-00.00Pavement | TUS | Dec 2020 | $790k | $725k |
| Wonof 3 | COS-SR 93/93D-03.52/00.00Pavement | COS | Dec 2020 | $1.74M | $1.74M |
| Rank 5of 5 | TUS-SR 212-09.09, TUS-SR 800-22.74Pavement | TUS | Nov 2020 | $10.0M | $7.19M |
| Rank 2of 4 | COS-US 36-26.49Pavement | COS | Nov 2020 | $5.34M | $5.25M |
| Rank 4of 4 | MED-SR 3-15.05Pavement | MED | Oct 2020 | $9.46M | $7.90M |
| Rank 3of 4 | TUS-US 36-17.49, TUS-US 250-21.35Pavement | TUS | Sep 2020 | $2.51M | $2.49M |
| Rank 5of 10 | NOB-SR 146-13.17Drainage | NOB | Sep 2020 | $352k | $279k |
| Wonof 3 | JAC-SR 32-00.00Pavement | JAC | Aug 2020 | $2.12M | $2.12M |
| Rank 4of 4 | ROS-SR 28-00.00Pavement | ROS | Aug 2020 | $1.20M | $943k |
| Rank 4of 8 | MRG-SR 60-13.31Earthwork | MRG | Jun 2020 | $1.51M | $1.32M |
| Rank 4of 7 | BEL-SR 147-10.40, BEL-SR 149-22.91Drainage | BEL | May 2020 | $248k | $208k |
| Rank 2of 2 | LAW-SR 217-13.59Pavement | LAW | May 2020 | $272k | $240k |
| Wonof 4 | GUE-Salt Fork Resurfacing FY20Pavement | GUE | May 2020 | $2.20M | $2.20M |
| Rank 2of 5 | MEG-Middleport Trail Phase 2Safety | MEG | May 2020 | $177k | $172k |
| Rank 2of 5 | MEG-SR 7-18.70Earthwork | MEG | Apr 2020 | $153k | $125k |
| Rank 4of 5 | D10-Culverts FY2020BDrainage | D10 | Apr 2020 | $313k | $222k |
| Wonof 3 | PIK-SR 32-15.77 Safety (PART 1 AND PART 2)Safety | PIK | Apr 2020 | $2.48M | $2.48M |
| Wonof 3 | D05-CUL FY2020Drainage | D05 | Apr 2020 | $976k | $976k |
| Rank 6of 8 | BRO-SR 505-05.50Drainage | BRO | Apr 2020 | $231k | $150k |
| Rank 4of 7 | GAL-SR 141-08.85Earthwork | GAL | Apr 2020 | $345k | $310k |
| Rank 2of 3 | HAS-SR 258-00.00Pavement | HAS | Apr 2020 | $2.27M | $2.24M |
| Rank 2of 2 | LAW-US 52-20.45 SafetySignals | LAW | Apr 2020 | $949k | $793k |
| Rank 2of 3 | MRG-SR 60-10.44Maintenance | MRG | Mar 2020 | $316k | $242k |
| Rank 7of 8 | CAR-SR 212-05.84Drainage | CAR | Mar 2020 | $350k | $217k |
| Rank 6of 8 | D10-Culverts FY2020ADrainage | D10 | Mar 2020 | $241k | $145k |
| Rank 4of 6 | TUS-SR 39-10.24Pavement | TUS | Mar 2020 | $1.04M | $885k |
| Rank 5of 5 | SCI-SR 140-02.16 SafetySafety | SCI | Mar 2020 | $251k | $101k |
| Wonof 3 | PIC-SR 316/SR 752-13.05/00.000 (PART 1 AND PART 2)Pavement | PIC | Mar 2020 | $2.75M | $2.75M |
| Wonof 8 | ROS-US 23-02.50 OH17-01Earthwork | ROS | Mar 2020 | $676k | $676k |
| Rank 2of 5 | MUS-SR 666-04.49Drainage | MUS | Mar 2020 | $254k | $233k |
| Wonof 2 | SCI-US 52-31.24Pavement | SCI | Feb 2020 | $1.74M | $1.74M |
| Rank 4of 4 | FRA-SR 104-00.00Pavement | FRA | Feb 2020 | $2.19M | $1.89M |
| Rank 5of 8 | GAL-US 35 14.800Earthwork | GAL | Feb 2020 | $582k | $469k |
| Rank 2of 8 | ATH-SR 124-01.60Earthwork | ATH | Feb 2020 | $1.71M | $1.61M |
| Wonof 6 | LIC-SR 37/SR 661-16.59/00.00Pavement | LIC | Feb 2020 | $8.78M | $8.78M |
| Rank 9of 9 | NOB-SR 340 4.100Earthwork | NOB | Feb 2020 | $536k | $319k |
Source: public.bid_results, ODOT bid tabs. Bidder strings are normalized to upper-case but not yet entity-resolved, so related firms (e.g. "Shelly Company" vs "Shelly & Sands") are shown separately.