D10-Culverts FY2020B
D10 County · est $0.3M
Bid dateThursday, April 23—
D10 County · est $0.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 6.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 30 more items below.
| Item | Quantity | R1Parker Corporation | R2Alan Stone CO INC | R3Axis Civil Construction LLC | R4Amaazz Construction Ohio LLC | R5Ohio-west Virginia Excavating CO | % of bid |
|---|---|---|---|---|---|---|---|
| 611E23601 60" CONDUIT, TYPE A, AS PER PLAN, 706.02 | 52 FT | $478 | $400 | $350 | $247 | $610 | 13% |
| 602E20001 CONCRETE MASONRY, AS PER PLAN | 24.8 CY | $750 | $790 | $1,100 | $1,920 | $1,325 | 10% |
| 613E41300 LOW STRENGTH MORTAR BACKFILL (TYPE 2) | 154 CY | $120 | $140 | $210 | $180 | $235 | 10% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN: 60" CO |
| Item | Quantity | R1Parker Corporation | R2Alan Stone CO INC | R3Axis Civil Construction LLC | R4Amaazz Construction Ohio LLC | R5Ohio-west Virginia Excavating CO |
|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 3 EACH | $1,000 | $220 | $400 | $340 | $1,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 48 FT | $10.00 | $19.00 | $22.00 | $26.00 | $35.00 |
| 202E35200 PIPE REMOVED, OVER 24" | 32 FT | $100 | $28.00 | $150 | $116 | $155 |
| 202E75000 FENCE REMOVED | 25 FT | $10.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 102 FT |
| $150 |
| $110 |
| $100 |
| $152 |
| $165 |
| 8% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 198 FT | $70.00 | $23.00 | $100 | $75.00 | $74.00 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $12,900 | $21,500 | $11,882 | $20,500 | 5% |
| 203E20000 EMBANKMENT | 465 CY | $20.00 | $35.00 | $40.00 | $34.00 | $55.00 | 5% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,000 | $1,800 | $5,000 | $9,500 | $8,000 | 4% |
| 611E13600 30" CONDUIT, TYPE C | 80 FT | $100 | $130 | $72.00 | $112 | $110 | 4% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $8,000 | $15,000 | $25,000 | $30,000 | $43,000 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,000 | $15,500 | $5,000 | $3,400 | $8,000 | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 20 CY | $350 | $510 | $300 | $359 | $285 | 4% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN: 6'-1" | 44 FT | $150 | $210 | $120 | $204 | $235 | 3% |
| 611E97400 CONDUIT, MISC.: 33" CONDUIT, TYPE A, 707.01 | 62 FT | $100 | $360 | $250 | $127 | $139 | 3% |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $6,000 | $3,800 | $3,500 | $3,940 | $5,390 | 3% |
| 611E06100 15" CONDUIT, TYPE C | 64 FT | $75.00 | $110 | $65.00 | $83.00 | $58.00 | 3% |
| 511E47010 CLASS QC1 CONCRETE, CULVERT | 4 CY | $1,000 | $370 | $350 | $1,415 | $950 | 2% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 10 CY | $350 | $1,200 | $400 | $525 | $465 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $4,500 | $3,500 | $2,255 | $7,200 | 2% |
| $3.00 |
| $6.00 |
| $22.00 |
| $6.00 |
| 203E10000 EXCAVATION | 168 CY | $20.00 | $11.00 | $40.00 | $14.00 | $35.00 |
| 204E10000 SUBGRADE COMPACTION | 128 SY | $0.50 | $3.00 | $3.00 | $3.25 | $10.00 |
| 606E16501 GUARDRAIL REBUILT, TYPE 5, AS PER PLAN | 25 FT | $25.00 | $79.00 | $26.00 | $110 | $65.00 |
| 607E15000 FENCE, TYPE 47 | 25 FT | $25.00 | $79.00 | $25.00 | $105 | $39.00 |
| 601E26000 DUMPED ROCK FILL, TYPE B | 14 CY | $150 | $310 | $120 | $132 | $185 |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 18 CY | $150 | $190 | $135 | $157 | $137 |
| 659E10000 SEEDING AND MULCHING | 1,364 SY | $1.00 | $5.00 | $2.00 | $4.50 | $3.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.13 TON | $3,850 | $560 | $500 | $1,135 | $665 |
| 659E31000 LIME | 0.28 ACRE | $1,790 | $720 | $200 | $1,135 | $80.00 |
| 659E35000 WATER | 4 MGAL | $0.25 | $2.00 | $1.00 | $4.55 | $1.00 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $100 | $17,300 | $15,000 | $11,150 | $4,000 |
| 602E20000 CONCRETE MASONRY | 0.9 CY | $2,250 | $1,500 | $3,000 | $2,115 | $2,000 |
| 611E00201 4" CONDUIT, TYPE C, AS PER PLAN | 40 FT | $5.00 | $19.00 | $8.00 | $11.25 | $46.00 |
| 611E98540 CATCH BASIN, NO. 2-4 | 1 EACH | $3,000 | $1,700 | $2,500 | $2,950 | $4,000 |
| 611E98634 CATCH BASIN RECONSTRUCTED TO GRADE | 1 EACH | $2,000 | $1,100 | $1,500 | $465 | $2,000 |
| 304E20000 AGGREGATE BASE | 43 CY | $75.00 | $120 | $120 | $108 | $150 |
| 407E10000 TACK COAT | 14 GAL | $2.00 | $5.00 | $5.00 | $4.00 | $5.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 2 EACH | $10.00 | $29.00 | $8.00 | $32.00 | $82.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.04 MILE | $20,000 | $20,300 | $19,250 | $21,000 | $21,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.02 MILE | $25,000 | $40,800 | $38,800 | $41,000 | $42,000 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 10 CY | $20.00 | $110 | $80.00 | $250 | $150 |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL) | 2 EACH | $100 | $2,600 | $2,000 | $2,600 | $2,700 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 5 CY | $40.00 | $1,200 | $120 | $230 | $575 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 BIDIRECTIONAL | 3 EACH | $2.00 | $100 | $8.00 | $100 | $100 |
| 614E13360 OBJECT MARKER, TWO WAY | 3 EACH | $2.00 | $100 | $15.00 | $100 | $100 |
| 622E41000 PORTABLE BARRIER, 32" | 120 FT | $2.00 | $18.00 | $25.00 | $28.00 | $48.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E23601 60" CONDUIT, TYPE A, AS PER PLAN, 706.02 | 52 FT | $478 | $25k | 11% |
| 602E20001 CONCRETE MASONRY, AS PER PLAN | 24.8 CY | $750 | $19k | 8% |
| 613E41300 LOW STRENGTH MORTAR BACKFILL (TYPE 2) | 154 CY | $120 | $18k | 8% |
| 611E96551 FIELD PAVING OF EXISTING PIPE, AS PER PLAN: 60" CO | 102 FT | $150 | $15k | 7% |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 198 FT | $70 | $14k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 5% |
| 203E20000 EMBANKMENT | 465 CY | $20 | $9k | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,000 | $8k | 4% |
| 611E13600 30" CONDUIT, TYPE C | 80 FT | $100 | $8k | 4% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $8,000 | $8k | 4% |