HAM-Dana Ave Storm Pipe
HAM County · est $0.1M
Bid dateThursday, August 13—
HAM County · est $0.1M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 1 more items below.
| Item | Quantity | R1Barrett Paving Materials INC | R2John R Jurgensen Company | R3Sunesis Construction CO | R4Scioto Valley Paving | R5Prus Construction Company | R6Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $27,791 | $2,000 | $66,000 | $41,000 | $45,000 | $45,000 | 16% |
| 611E06700 15" CONDUIT, TYPE F 707.05 TYPE C OR 707.21 | 108 FT | $205 | $519 | $378 | $1,000 | $600 | $550 | 13% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $20,551 | $9,300 |
| Item | Quantity | R1Barrett Paving Materials INC | R2John R Jurgensen Company | R3Sunesis Construction CO | R4Scioto Valley Paving | R5Prus Construction Company | R6Eclipse CO LLC |
|---|---|---|---|---|---|---|---|
| 659E35000 WATER | 16.5 MGAL | $1.00 | $1.00 | $2.00 | $1.00 | $1.00 | $1.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $7,000 |
| $6,000 |
| $18,500 |
| 12% |
| 659E00300 TOPSOIL | 340 CY | $41.00 | $41.00 | $18.00 | $5.00 | $60.00 | $69.50 | 8% |
| 611E05200 12" CONDUIT, TYPE F 707.05 TYPE C OR 707.21 | 26 FT | $500 | $601 | $830 | $500 | $1,750 | $850 | 8% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 600 FT | $18.00 | $18.00 | $25.00 | $22.00 | $18.00 | $19.00 | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $43,578 | $8,897 | $4,000 | $10,000 | $45,000 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10,000 | $34,000 | $10,000 | $10,000 | $61,908 | 6% |
| 611E97400 CONDUIT, MISC.: VIDEO LOG | 200 FT | $44.80 | $42.50 | $40.00 | $30.00 | $25.00 | $4.00 | 5% |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 134 FT | $48.00 | $30.71 | $137 | $125 | $100 | $63.00 | 4% |
| 832E30000 EROSION CONTROL | 6,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 4% |
| 659E10000 SEEDING AND MULCHING | 3,063 SY | $1.42 | $1.42 | $1.50 | $1.50 | $3.00 | $1.85 | 3% |
| 611E98300 CATCH BASIN, NO. 5 | 1 EACH | $4,285 | $5,787 | $4,100 | $5,000 | $7,500 | $6,000 | 3% |
| 202E35201 PIPE REMOVED, OVER 24", AS PER PLAN | 40 FT | $105 | $156 | $74.00 | $100 | $150 | $108 | 2% |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $2,750 | $1,203 | $865 | $500 | $800 | $954 | 2% |
| 614E13350 OBJECT MARKER, ONE WAY | 12 EACH | $180 | $15.00 | $15.00 | $20.00 | $15.00 | $16.00 | 1% |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (ONE-WAY) | 12 EACH | $132 | $11.00 | $11.00 | $15.00 | $11.00 | $11.50 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $1,000 | $1,570 | $1,750 | $8,000 | $2,500 | $7,500 | 1% |
| 659E20000 COMMERCIAL FERTILIZER | 0.41 TON | $750 | $750 | $350 | $400 | $750 | $507 | 0% |
| 659E31000 LIME | 0.63 ACRE | $100 | $100 | $100 | $100 | $90.00 | $104 | 0% |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN | 1 LS | $27,791 | $28k | 16% |
| 611E06700 15" CONDUIT, TYPE F 707.05 TYPE C OR 707.21 | 108 FT | $205 | $22k | 13% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $20k | 12% |
| 659E00300 TOPSOIL | 340 CY | $41 | $14k | 8% |
| 611E05200 12" CONDUIT, TYPE F 707.05 TYPE C OR 707.21 | 26 FT | $500 | $13k | 8% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 600 FT | $18 | $11k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $10k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 6% |
| 611E97400 CONDUIT, MISC.: VIDEO LOG | 200 FT | $44.8 | $9k | 5% |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 134 FT | $48 | $6k | 4% |