HOL-SR 83-09.98
HOL County · est $0.2M
Bid dateThursday, October 1—
HOL County · est $0.2M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 42 more items below.
| Item | Quantity | R1Glenn O Hawbaker INC | R2Eclipse CO LLC | R3Tucson INC | R4V O Menuez & Son INC | R5Adena Corporation | R6Stanley Miller Construction Company | R7R C Construction Company And Son | R8INC Ohio-west Virginia Excavating CO | R9Buds INC | R10Lockhart Concrete CO | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $29,000 | $48,400 | $55,200 | $41,645 | $53,867 | $37,778 | $24,000 | $41,000 | $10,000 | $10,000 | 16% |
| Item | Quantity | R1Glenn O Hawbaker INC | R2Eclipse CO LLC | R3Tucson INC | R4V O Menuez & Son INC | R5Adena Corporation | R6Stanley Miller Construction Company | R7R C Construction Company And Son | R8INC Ohio-west Virginia Excavating CO | R9Buds INC | R10Lockhart Concrete CO |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,500 | $7,387 | $3,000 | $1,534 | $1,999 | $6,500 | $3,500 | $4,500 | $8,000 | $14,900 |
| 202E20010 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 611E19400 42" CONDUIT, TYPE B |
| 47 FT |
| $400 |
| $366 |
| $625 |
| $587 |
| $461 |
| $511 |
| $475 |
| $1,100 |
| $750 |
| $500 |
| 10% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 330 FT | $55.00 | $45.00 | $30.00 | $58.00 | $45.62 | $53.25 | $30.00 | $17.00 | $35.00 | $45.00 | 10% |
| 203E20000 EMBANKMENT | 326 CY | $48.00 | $17.00 | $35.00 | $13.00 | $23.68 | $19.00 | $30.00 | $28.00 | $30.00 | $15.00 | 8% |
| 203E10000 EXCAVATION | 569 CY | $21.00 | $13.50 | $18.00 | $12.00 | $20.05 | $27.00 | $30.00 | $29.00 | $30.00 | $15.00 | 6% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 42 CY | $260 | $278 | $330 | $275 | $258 | $340 | $325 | $275 | $300 | $306 | 6% |
| 609E26000 CURB, TYPE 6 | 212 FT | $50.00 | $39.00 | $42.00 | $34.00 | $22.39 | $31.00 | $50.00 | $32.00 | $45.00 | $30.00 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $8,000 | $9,000 | $7,000 | $300 | $3,458 | $18,044 | $12,500 | $10,000 | $12,600 | $29,000 | 4% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $7,500 | $3,232 | $2,000 | $29,718 | $7,375 | $939 | $10,000 | $13,000 | $10,000 | $30,000 | 4% |
| 606E15050 GUARDRAIL, TYPE MGS | 125 FT | $60.00 | $22.50 | $23.00 | $22.00 | $30.75 | $27.35 | $45.00 | $27.00 | $35.00 | $16.50 | 4% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $2,500 | $1,957 | $2,410 | $3,410 | $2,570 | $2,478 | $2,500 | $2,500 | $1,900 | $2,000 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,000 | $8,500 | $1,700 | $2,986 | $3,031 | $19,144 | $12,000 | $2,500 | $3,000 | $7,500 | 3% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.02 MILE | $290,000 | $76,071 | $42,930 | $44,350 | $49,966 | $44,166 | $45,000 | $45,000 | $40,000 | $74,000 | 3% |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.32 MILE | $16,000 | $14,218 | $14,580 | $13,100 | $14,392 | $15,000 | $12,500 | $15,000 | $14,000 | $9,000 | 3% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $490 | $349 | $155 | $50.00 | $156 | $120 | $25.00 | $350 | $750 | $200 | 3% |
| 659E00300 TOPSOIL | 39 CY | $110 | $68.50 | $80.00 | $52.50 | $35.89 | $23.00 | $50.00 | $45.00 | $35.00 | $92.00 | 2% |
| 304E20000 AGGREGATE BASE | 35 CY | $110 | $80.00 | $60.00 | $132 | $83.79 | $194 | $100 | $125 | $120 | $55.00 | 2% |
| 621E00100 RPM | 3 EACH | $1,200 | $721 | $778 | $1,300 | $984 | $150 | $1,500 | $1,100 | $1,000 | $1,640 | 2% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (8 CY | $400 | $284 | $807 | $280 | $737 | $830 | $425 | $400 | $325 | $745 | 2% |
| 601E32010 ROCK CHANNEL PROTECTION, TYPE A WITH AGGREGATE FIL | 14 CY | $220 | $115 | $134 | $170 | $196 | $159 | $100 | $110 | $125 | $120 | 2% |
| 1 EACH |
| $1,000 |
| $321 |
| $1,000 |
| $50.00 |
| $1,250 |
| $250 |
| $1,000 |
| $1,500 |
| $1,000 |
| $2,000 |
| 202E23000 PAVEMENT REMOVED | 172 SY | $11.00 | $14.50 | $8.00 | $13.75 | $14.97 | $21.50 | $20.00 | $20.00 | $25.00 | $15.00 |
| 202E32000 CURB REMOVED | 212 FT | $4.00 | $5.50 | $3.00 | $5.00 | $1.41 | $2.00 | $10.00 | $10.00 | $15.00 | $5.00 |
| 202E38000 GUARDRAIL REMOVED | 115 FT | $4.00 | $5.00 | $5.00 | $11.00 | $3.60 | $2.50 | $3.00 | $2.25 | $3.00 | $4.00 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $450 | $563 | $350 | $105 | $1,100 | $250 | $500 | $500 | $1,000 | $100 |
| 204E10000 SUBGRADE COMPACTION | 205 SY | $2.00 | $2.50 | $2.00 | $2.35 | $2.03 | $1.00 | $2.00 | $6.00 | $5.00 | $2.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP 350 OR MASH 201 | 1 EACH | $2,400 | $3,296 | $3,450 | $3,300 | $2,997 | $2,745 | $2,800 | $2,600 | $2,200 | $4,800 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $2,400 | $1,056 | $1,100 | $1,050 | $1,285 | $1,095 | $1,200 | $1,100 | $950 | $1,600 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 43 SY | $70.00 | $89.50 | $67.00 | $100 | $91.49 | $70.00 | $100 | $70.00 | $35.00 | $69.00 |
| 601E23000 ARTICULATING CONCRETE BLOCK REVETMENT SYSTEM, TYPE | 14 SY | $145 | $516 | $512 | $585 | $601 | $546 | $300 | $650 | $800 | $1,000 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $180 | $206 | $50.00 | $88.00 | $190 | $110 | $50.00 | $50.00 | $35.00 | $150 |
| 659E10000 SEEDING AND MULCHING | 355 SY | $7.00 | $10.50 | $3.00 | $4.50 | $4.64 | $8.25 | $15.00 | $7.00 | $5.00 | $5.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 18 SY | $7.00 | $1.00 | $2.00 | $1.00 | $1.00 | $1.00 | $0.20 | $1.00 | $0.10 | $5.00 |
| 659E15000 INTER-SEEDING | 18 SY | $7.00 | $0.01 | $2.00 | $1.00 | $1.00 | $1.00 | $0.20 | $1.00 | $0.10 | $5.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.05 TON | $1,200 | $515 | $3,700 | $650 | $12,909 | $650 | $1,200 | $500 | $750 | $1,000 |
| 659E31000 LIME | 0.07 ACRE | $800 | $206 | $2,400 | $175 | $8,891 | $450 | $800 | $500 | $150 | $700 |
| 659E35000 WATER | 2 MGAL | $95.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $50.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 1 CY | $3,000 | $1,498 | $1,800 | $1,513 | $2,111 | $1,836 | $1,500 | $1,600 | $2,500 | $1,000 |
| 605E14000 6" BASE PIPE UNDERDRAINS | 130 FT | $20.00 | $16.00 | $12.00 | $15.44 | $12.44 | $23.40 | $75.00 | $30.00 | $25.00 | $20.00 |
| 611E00406 4" CONDUIT, TYPE F | 6 FT | $70.00 | $34.50 | $40.00 | $52.73 | $24.97 | $10.00 | $10.00 | $15.00 | $35.00 | $20.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 10 FT | $23.00 | $22.50 | $40.00 | $33.00 | $61.83 | $10.00 | $25.00 | $17.00 | $35.00 | $20.00 |
| 611E04600 12" CONDUIT, TYPE C | 12 FT | $47.00 | $53.50 | $94.00 | $43.20 | $88.80 | $15.00 | $75.00 | $100 | $75.00 | $100 |
| 611E98540 CATCH BASIN, NO. 2-4 | 1 EACH | $2,600 | $3,030 | $3,000 | $2,347 | $1,700 | $2,868 | $3,000 | $3,200 | $3,500 | $2,000 |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 1 EACH | $920 | $807 | $375 | $391 | $1,988 | $600 | $1,500 | $1,200 | $1,500 | $500 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $2,400 | $236 | $340 | $229 | $1,521 | $150 | $250 | $400 | $300 | $500 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 73 FT | $22.00 | $2.00 | $7.00 | $5.72 | $2.05 | $9.00 | $20.00 | $8.00 | $10.00 | $5.00 |
| 407E10000 TACK COAT | 18 GAL | $9.00 | $15.50 | $3.75 | $16.00 | $15.23 | $3.90 | $5.00 | $10.00 | $15.00 | $3.50 |
| 408E10001 PRIME COAT, AS PER PLAN | 3 GAL | $9.00 | $103 | $108 | $100 | $165 | $111 | $300 | $20.00 | $10.00 | $100 |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 7 CY | $400 | $320 | $688 | $315 | $817 | $707 | $425 | $425 | $350 | $635 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 3 EACH | $240 | $26.00 | $54.00 | $60.00 | $1.00 | $25.00 | $50.00 | $48.00 | $10.00 | $50.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, (BI-DIRECTIONAL) | 5 EACH | $62.00 | $14.50 | $7.60 | $16.00 | $130 | $8.00 | $25.00 | $55.00 | $9.00 | $15.00 |
| 642E00300 CENTER LINE, TYPE 1 | 0.01 MILE | $290,000 | $76,261 | $85,320 | $58,800 | $66,620 | $87,778 | $45,000 | $85,000 | $80,000 | $75,000 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 7 EACH | $52.00 | $11.50 | $48.00 | $16.00 | $17.28 | $49.00 | $25.00 | $50.00 | $7.00 | $11.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 7 EACH | $57.00 | $15.50 | $52.00 | $21.00 | $23.05 | $53.00 | $25.00 | $55.00 | $10.00 | $15.00 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.11 MILE | $14,500 | $10,731 | $13,500 | $9,960 | $11,805 | $13,889 | $12,500 | $14,000 | $13,000 | $7,000 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 26 FT | $15.00 | $6.00 | $13.00 | $8.00 | $13.83 | $13.34 | $50.00 | $13.00 | $15.00 | $3.90 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $24.00 | $11,500 | $1,936 | $8,900 | $9,044 | $2,083 | $10,000 | $3,400 | $51,620 | $56,316 |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 189 SY | $14.00 | $90.50 | $85.00 | $91.00 | $107 | $106 | $125 | $65.00 | $20.00 | $50.00 |
| 616E10000 WATER | 10 MGAL | $38.00 | $18.50 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $12.00 | $1.00 | $50.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $600 | $5,800 | $3,800 | $3,000 | $2,504 | $3,600 | $9,500 | $5,000 | $5,000 | $5,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $29,000 | $29k | 12% |
| 611E19400 42" CONDUIT, TYPE B | 47 FT | $400 | $19k | 8% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 330 FT | $55 | $18k | 8% |
| 203E20000 EMBANKMENT | 326 CY | $48 | $16k | 7% |
| 203E10000 EXCAVATION | 569 CY | $21 | $12k | 5% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 42 CY | $260 | $11k | 5% |
| 609E26000 CURB, TYPE 6 | 212 FT | $50 | $11k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $8,000 | $8k | 3% |
| 202E11000 STRUCTURE REMOVED | 1 LS | $7,500 | $8k | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 125 FT | $60 | $8k | 3% |