SCI-US 52-02.44 & 10.15
SCI County · est $0.9M
Bid dateThursday, October 1—
SCI County · est $0.9M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 66 more items below.
| Item | Quantity | R1D G M INC | R2Heavy Highway Construction Company | R3Distel Construction INC | R4Shelly & Sands INC | R5Allard Excavation LLC | R6Sunesis Construction CO | R7Complete General Construction Company | R8Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 611E96497 20' X 6' CONDUIT, TYPE A, 706.05, AS PER PLAN | 76 FT | $1,880 | $1,400 | $1,900 | $2,133 | $1,892 | $1,821 | $1,800 | $1,500 | 21% |
| 611E95600 12' X 4' CONDUIT, TYPE A, 706.05 | 64 FT | $1,260 | $900 | $1,345 | $1,477 | $1,345 |
| Item | Quantity | R1D G M INC | R2Heavy Highway Construction Company | R3Distel Construction INC | R4Shelly & Sands INC | R5Allard Excavation LLC | R6Sunesis Construction CO | R7Complete General Construction Company | R8Alan Stone CO INC |
|---|---|---|---|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 401 SY | $12.00 | $14.00 | $10.00 | $14.75 | $5.25 | $29.35 | $15.00 | $11.50 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 154 FT | $12.00 | $10.00 | $10.00 | $10.50 | $7.70 | $11.97 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $1,013 |
| $1,300 |
| $1,300 |
| 12% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 238 CY | $260 | $250 | $213 | $250 | $250 | $180 | $250 | $250 | 9% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 305 CY | $200 | $230 | $207 | $230 | $230 | $175 | $230 | $270 | 9% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 839 SY | $70.00 | $61.00 | $42.20 | $60.25 | $61.00 | $108 | $58.00 | $75.00 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $44,300 | $15,000 | $59,118 | $34,525 | $111,000 | $88,371 | $58,000 | $65,000 | 6% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,800 | $1,807 | $2,242 | $2,500 | $1,900 | $1,950 | $2,200 | $2,000 | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $24,000 | $3,500 | $12,250 | $7,500 | $8,750 | $17,304 | $13,000 | $15,000 | 3% |
| 202E11002 STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $21,000 | $20,000 | $14,242 | $20,000 | $9,900 | $15,906 | $65,000 | $25,000 | 3% |
| 304E20000 AGGREGATE BASE | 273 CY | $75.00 | $85.00 | $50.00 | $72.00 | $67.90 | $78.63 | $90.00 | $65.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $33,000 | $10,550 | $20,000 | $120,000 | $41,713 | $40,000 | $40,000 | 3% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 49 CY | $400 | $475 | $1,147 | $701 | $468 | $429 | $500 | $850 | 3% |
| 202E11200 PORTIONS OF STRUCTURE REMOVED | 1 LS | $16,000 | $10,000 | $8,242 | $17,500 | $5,000 | $10,920 | $70,000 | $16,000 | 2% |
| 511E46001 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 45 SY | $350 | $500 | $811 | $524 | $477 | $592 | $720 | $600 | 2% |
| 203E20000 EMBANKMENT | 743 CY | $20.00 | $25.00 | $22.00 | $12.00 | $8.65 | $19.32 | $22.00 | $9.00 | 2% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $14,000 | $20,000 | $34,214 | $27,500 | $31,000 | $48,263 | $20,000 | $55,000 | 2% |
| 203E10000 EXCAVATION | 547 CY | $25.00 | $18.00 | $18.00 | $21.25 | $12.20 | $9.62 | $20.00 | $17.00 | 2% |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 25 CY | $500 | $475 | $1,510 | $1,200 | $593 | $546 | $675 | $1,500 | 2% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $12,000 | $25,000 | $16,000 | $25,830 | $31,000 | $36,140 | $18,000 | $55,000 | 2% |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $11,000 | $95,000 | $9,039 | $20,000 | $19,600 | $20,024 | $40,000 | $40,000 | 2% |
| $25.00 |
| $30.50 |
| 202E38000 GUARDRAIL REMOVED | 550 FT | $1.00 | $2.00 | $5.00 | $5.00 | $3.25 | $4.35 | $2.00 | $3.50 |
| 202E42000 ANCHOR ASSEMBLY REMOVED, TYPE A | 6 EACH | $225 | $200 | $300 | $250 | $77.00 | $171 | $245 | $365 |
| 202E42040 ANCHOR ASSEMBLY REMOVED, TYPE T | 2 EACH | $100 | $200 | $300 | $250 | $77.00 | $171 | $95.00 | $365 |
| 202E53100 MAILBOX REMOVED | 3 EACH | $20.00 | $25.00 | $50.00 | $115 | $33.00 | $32.56 | $155 | $122 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $250 | $250 | $350 | $385 | $128 | $252 | $500 | $469 |
| 202E98200 REMOVAL MISC.: CONDUIT | 18 FT | $5.00 | $5.00 | $100 | $45.00 | $7.25 | $30.04 | $38.00 | $142 |
| 203E20001 EMBANKMENT, AS PER PLAN | 50 CY | $10.00 | $25.00 | $22.00 | $19.00 | $37.70 | $28.16 | $38.00 | $27.50 |
| 204E10000 SUBGRADE COMPACTION | 1,609 SY | $4.00 | $3.00 | $3.00 | $5.00 | $2.50 | $4.98 | $3.00 | $3.50 |
| 606E15050 GUARDRAIL, TYPE MGS | 300 FT | $17.00 | $32.50 | $27.35 | $16.50 | $33.46 | $16.40 | $23.20 | $28.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 2 EACH | $3,000 | $2,300 | $2,927 | $2,950 | $2,150 | $2,950 | $2,480 | $3,600 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $3,000 | $950 | $1,215 | $975 | $840 | $975 | $1,030 | $1,400 |
| 626E00112 BARRIER REFLECTOR, TYPE 3 (BIDIRECTIONAL) | 6 EACH | $15.00 | $8.75 | $9.00 | $10.00 | $12.00 | $12.00 | $7.50 | $2.00 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 1 EACH | $150 | $100 | $200 | $250 | $150 | $150 | $145 | $38.50 |
| 690E50200 SPECIAL - MAILBOX SUPPORT SYSTEM, DOUBLE | 1 EACH | $225 | $150 | $300 | $350 | $250 | $200 | $235 | $86.00 |
| 659E10000 SEEDING AND MULCHING | 2,925 SY | $1.75 | $1.30 | $4.00 | $1.30 | $1.00 | $1.78 | $1.00 | $2.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 146 SY | $0.05 | $1.30 | $9.00 | $1.30 | $0.50 | $1.25 | $1.25 | $7.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.4 TON | $650 | $610 | $480 | $610 | $750 | $750 | $750 | $796 |
| 659E31000 LIME | 0.61 ACRE | $80.00 | $80.00 | $100 | $80.00 | $200 | $200 | $200 | $1,000 |
| 659E35000 WATER | 15.8 MGAL | $1.00 | $1.00 | $5.00 | $1.00 | $1.00 | $1.39 | $5.00 | $145 |
| 832E30000 EROSION CONTROL | 4,100 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 0.6 CY | $1,500 | $1,000 | $4,375 | $2,500 | $3,200 | $1,954 | $2,000 | $3,100 |
| 605E31100 AGGREGATE DRAINS | 144 FT | $20.00 | $20.00 | $17.00 | $20.50 | $14.75 | $10.65 | $16.00 | $35.00 |
| 611E04900 12" CONDUIT, TYPE D, (706.02) | 20 FT | $75.00 | $50.00 | $75.00 | $57.75 | $81.36 | $63.63 | $115 | $111 |
| 611E05900 15" CONDUIT, TYPE B | 30 FT | $90.00 | $75.00 | $75.00 | $77.00 | $60.66 | $67.67 | $95.00 | $91.00 |
| 611E06100 15" CONDUIT, TYPE C | 105 FT | $75.00 | $70.00 | $50.00 | $65.50 | $74.80 | $59.12 | $88.00 | $86.00 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $1,100 | $1,200 | $1,860 | $2,350 | $1,673 | $2,214 | $2,000 | $2,900 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 95 FT | $5.00 | $3.00 | $15.00 | $4.00 | $4.54 | $55.06 | $4.00 | $70.00 |
| 407E10000 TACK COAT | 355 GAL | $7.00 | $1.75 | $5.00 | $1.75 | $1.75 | $4.00 | $1.75 | $1.75 |
| 621E00100 RPM | 16 EACH | $185 | $210 | $248 | $210 | $185 | $210 | $210 | $410 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 16 EACH | $1.00 | $20.00 | $25.00 | $15.00 | $9.75 | $1.00 | $45.00 | $30.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.52 MILE | $3,000 | $3,575 | $4,219 | $3,575 | $2,779 | $3,625 | $3,575 | $7,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.26 MILE | $6,000 | $6,550 | $7,729 | $6,550 | $5,557 | $6,716 | $6,550 | $7,200 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 16 HOUR | $40.00 | $65.00 | $80.00 | $68.00 | $75.00 | $75.00 | $85.00 | $94.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 770 FT | $2.25 | $1.50 | $2.00 | $1.00 | $1.50 | $1.50 | $1.50 | $0.70 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 24 EACH | $15.00 | $15.00 | $42.50 | $7.00 | $12.00 | $36.00 | $36.00 | $2.50 |
| 614E13314 BARRIER REFLECTOR, TYPE 3 (BIDIRECTIONAL) | 10 EACH | $15.00 | $62.00 | $73.15 | $12.00 | $12.00 | $62.00 | $62.00 | $3.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 29 EACH | $15.00 | $37.50 | $44.25 | $12.25 | $12.00 | $37.50 | $29.00 | $46.50 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 0.9 MILE | $6,000 | $4,950 | $5,841 | $4,950 | $4,950 | $4,950 | $4,950 | $2,000 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 47 FT | $15.00 | $14.50 | $17.10 | $14.50 | $14.50 | $14.50 | $14.50 | $2.50 |
| 616E10000 WATER | 2 MGAL | $1.00 | $1.00 | $5.00 | $32.00 | $1.00 | $23.89 | $68.00 | $0.01 |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 570 FT | $13.00 | $12.00 | $34.80 | $14.00 | $24.00 | $67.54 | $19.00 | $35.00 |
| 622E41110 PORTABLE BARRIER, ANCHORED | 150 FT | $20.00 | $15.00 | $34.80 | $36.00 | $27.50 | $67.16 | $28.00 | $50.00 |
| 202E23500 WEARING COURSE REMOVED | 81 SY | $6.00 | $15.00 | $10.00 | $6.75 | $2.60 | $9.68 | $10.00 | $6.00 |
| 503E21301 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1 LS | $1,000 | $4,000 | $7,500 | $20,000 | $9,900 | $41,608 | $18,000 | $10,000 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 3,796 LB | $2.00 | $2.00 | $2.00 | $2.00 | $2.55 | $1.98 | $1.90 | $1.50 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 80 SY | $35.00 | $26.00 | $30.00 | $26.00 | $25.00 | $39.96 | $25.00 | $45.00 |
| 512E33000 TYPE 2 WATERPROOFING | 145 SY | $15.00 | $26.00 | $30.00 | $26.00 | $23.50 | $16.30 | $23.50 | $24.00 |
| 512E33010 TYPE 3 WATERPROOFING | 203 SY | $25.00 | $31.00 | $37.00 | $31.00 | $28.42 | $31.58 | $28.50 | $48.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 38 SF | $15.00 | $5.00 | $15.00 | $1.75 | $1.58 | $3.37 | $13.00 | $2.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 24 CY | $80.00 | $100 | $100 | $130 | $148 | $95.19 | $120 | $400 |
| 601E32010 ROCK CHANNEL PROTECTION, TYPE A WITH AGGREGATE FIL | 91 CY | $80.00 | $125 | $92.00 | $71.50 | $79.90 | $92.88 | $75.00 | $35.00 |
| 202E23500 WEARING COURSE REMOVED | 41 SY | $10.00 | $15.00 | $10.00 | $7.00 | $6.80 | $16.65 | $10.00 | $7.00 |
| 503E21301 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1 LS | $1,000 | $3,500 | $5,700 | $12,150 | $5,000 | $29,981 | $9,000 | $10,000 |
| 509E10000 EPOXY COATED REINFORCING STEEL | 2,048 LB | $2.00 | $2.00 | $2.00 | $2.00 | $2.55 | $2.02 | $1.90 | $2.00 |
| 511E46001 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 27 SY | $400 | $500 | $994 | $625 | $523 | $942 | $1,100 | $800 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 43 SY | $35.00 | $26.00 | $30.00 | $26.00 | $25.00 | $38.45 | $25.00 | $50.00 |
| 512E33000 TYPE 2 WATERPROOFING | 88 SY | $17.00 | $26.00 | $30.00 | $26.00 | $23.50 | $19.45 | $23.50 | $28.00 |
| 512E33010 TYPE 3 WATERPROOFING | 114 SY | $30.00 | $31.00 | $37.00 | $31.00 | $30.00 | $31.71 | $30.00 | $50.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 26 SF | $15.00 | $5.00 | $15.00 | $1.75 | $1.58 | $3.99 | $13.00 | $2.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 10 CY | $100 | $100 | $100 | $250 | $165 | $103 | $130 | $400 |
| 601E32110 ROCK CHANNEL PROTECTION, TYPE B WITH AGGREGATE FIL | 26 CY | $100 | $125 | $95.00 | $100 | $98.00 | $102 | $100 | $80.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,000 | $12,600 | $13,906 | $5,250 | $11,000 | $6,625 | $10,000 | $7,000 |
| 619E16000 FIELD OFFICE, TYPE A | 5 MNTH | $700 | $1,500 | $1,800 | $3,500 | $1,200 | $1,085 | $2,000 | $850 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $11,000 | $8,000 | $12,000 | $13,500 | $9,350 | $8,305 | $9,000 | $16,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 611E96497 20' X 6' CONDUIT, TYPE A, 706.05, AS PER PLAN | 76 FT | $1,880 | $143k | 17% |
| 611E95600 12' X 4' CONDUIT, TYPE A, 706.05 | 64 FT | $1,260 | $81k | 9% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 238 CY | $260 | $62k | 7% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 305 CY | $200 | $61k | 7% |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 839 SY | $70 | $59k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $44,300 | $44k | 5% |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,800 | $25k | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $24,000 | $24k | 3% |
| 202E11002 STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $21,000 | $21k | 2% |
| 304E20000 AGGREGATE BASE | 273 CY | $75 | $20k | 2% |