MEG-CR 1-09.04
MEG County · est $0.4M
Bid dateThursday, January 28—
MEG County · est $0.4M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 9.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 24 more items below.
| Item | Quantity | R1D G M INC | R2Alan Stone CO INC | R3J & J Bridge Company INC | R4Axis Civil Construction LLC | R5Shelly & Sands INC | R6George J Igel & CO INC | R7R C Construction Company And Son | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 6 EACH | $11,500 | $13,000 | $11,550 | $12,450 | $11,900 | $10,500 | $15,000 | 25% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 30 CY | $1,175 | $2,100 | $900 | $1,190 | $2,000 | $1,000 | $1,850 | 13% |
| Item | Quantity | R1D G M INC | R2Alan Stone CO INC | R3J & J Bridge Company INC | R4Axis Civil Construction LLC | R5Shelly & Sands INC | R6George J Igel & CO INC | R7R C Construction Company And Son |
|---|---|---|---|---|---|---|---|---|
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 352 SY | $5.00 | $11.00 | $10.00 | $12.00 | $8.00 | $11.00 | $25.00 |
| 204E10000 SUBGRADE COMPACTION | 321 SY | $6.00 | $3.50 | $5.00 | $3.00 | $5.00 | $4.00 | $2.00 |
| 209E60500 LINEAR GRADING |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 72 CY |
| $340 |
| $353 |
| $250 |
| $280 |
| $300 |
| $280 |
| $450 |
| 9% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $20,000 | $12,000 | $20,000 | $20,000 | $13,500 | $60,600 | $15,000 | 7% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 40 CY | $500 | $476 | $800 | $645 | $1,000 | $745 | $750 | 7% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 8,767 LB | $1.50 | $2.00 | $2.00 | $1.75 | $1.50 | $1.50 | $3.00 | 5% |
| 507E00100 STEEL PILES HP10X42, FURNISHED | 250 FT | $47.50 | $29.00 | $26.00 | $27.00 | $25.00 | $27.00 | $28.00 | 4% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 105 CY | $105 | $110 | $105 | $116 | $125 | $160 | $100 | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $11,000 | $568 | $5,000 | $7,500 | $600 | $2,000 | $2,500 | 4% |
| 517E72300 RAILING (DEEP BEAM RAIL WITH STEEL TUBULAR BACKUP | 112.5 FT | $85.00 | $90.00 | $70.00 | $78.50 | $82.00 | $78.00 | $100 | 3% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 127 CY | $75.00 | $52.50 | $100 | $80.00 | $85.00 | $65.00 | $100 | 3% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $8,000 | $1,200 | $3,000 | $4,500 | $3,100 | $3,500 | $55,000 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 18 CY | $390 | $370 | $400 | $370 | $315 | $380 | $650 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,000 | $2,300 | $15,000 | $3,000 | $2,000 | $2,000 | $25,000 | 2% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $5,000 | $4,000 | $20,000 | $11,000 | $15,000 | $7,000 | $40,000 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $5,000 | $13,000 | $10,000 | $20,000 | $10,000 | $10,000 | $23,000 | 2% |
| 606E25000 ANCHOR ASSEMBLY, TYPE A | 3 EACH | $1,400 | $1,600 | $1,600 | $1,585 | $1,340 | $1,340 | $1,500 | 2% |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 516E43100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 24 EACH | $120 | $120 | $120 | $150 | $110 | $125 | $150 | 1% |
| 606E35140 BRIDGE TERMINAL ASSEMBLY, TYPE 4 | 3 EACH | $900 | $1,000 | $900 | $1,375 | $900 | $870 | $850 | 1% |
| 0.04 MILE |
| $10,000 |
| $28,000 |
| $2,500 |
| $10,000 |
| $18,000 |
| $3,700 |
| $12,500 |
| 606E13000 GUARDRAIL, TYPE 5 | 100 FT | $22.00 | $23.00 | $20.00 | $15.85 | $20.00 | $19.75 | $29.00 |
| 606E20000 FLARED END SECTION | 1 EACH | $70.00 | $82.50 | $75.00 | $596 | $70.00 | $70.00 | $75.00 |
| 606E35141 BRIDGE TERMINAL ASSEMBLY, TYPE 4, AS PER PLAN | 1 EACH | $950 | $1,100 | $1,100 | $1,575 | $935 | $935 | $950 |
| 659E10000 SEEDING AND MULCHING | 951 SY | $2.50 | $1.50 | $2.00 | $2.97 | $2.90 | $5.00 | $10.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.09 TON | $650 | $898 | $2,000 | $610 | $754 | $610 | $1,200 |
| 659E31000 LIME | 0.2 ACRE | $80.00 | $235 | $1,000 | $80.00 | $151 | $80.00 | $800 |
| 659E35000 WATER | 8 MGAL | $1.00 | $118 | $10.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 38 FT | $10.00 | $14.50 | $5.00 | $4.00 | $7.00 | $6.00 | $50.00 |
| 407E10000 TACK COAT | 32 GAL | $5.00 | $2.00 | $5.00 | $3.00 | $1.75 | $8.00 | $10.00 |
| 642E00100 EDGE LINE, 4", TYPE 1 | 0.08 MILE | $10,000 | $16,000 | $8,850 | $8,850 | $8,850 | $8,850 | $35,000 |
| 642E00300 CENTER LINE, TYPE 1 | 0.04 MILE | $20,000 | $33,000 | $17,750 | $11,750 | $17,750 | $17,750 | $35,000 |
| 202E23500 WEARING COURSE REMOVED | 58 SY | $8.00 | $12.00 | $1.00 | $25.00 | $32.00 | $6.00 | $25.00 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $2,000 | $1,100 | $12,000 | $14,000 | $6,500 | $20,000 | $6,500 |
| 507E00150 STEEL PILES HP10X42, DRIVEN | 241 FT | $8.00 | $26.00 | $10.00 | $4.50 | $29.00 | $19.00 | $28.00 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 55 SY | $40.00 | $29.50 | $10.00 | $31.00 | $13.50 | $13.50 | $50.00 |
| 512E33000 TYPE 2 WATERPROOFING | 24 SY | $20.00 | $69.50 | $50.00 | $16.00 | $35.00 | $35.00 | $50.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 8 SF | $20.00 | $4.50 | $20.00 | $10.00 | $8.00 | $12.00 | $20.00 |
| 516E41100 1/8" PREFORMED BEARING PAD | 12 EACH | $15.00 | $17.50 | $10.00 | $31.00 | $15.00 | $15.00 | $150 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 124 FT | $15.00 | $14.00 | $15.00 | $10.00 | $14.50 | $15.00 | $25.00 |
| 512E10400 TREATING OF CONCRETE BRIDGE DECK WITH SRS | 139 SY | $8.00 | $21.00 | $10.00 | $20.00 | $15.00 | $14.50 | $140 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,500 | $5,000 | $1,000 | $4,500 | $6,490 | $7,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 6 EACH | $11,500 | $69k | 23% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 30 CY | $1,175 | $35k | 12% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 72 CY | $340 | $24k | 8% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $20,000 | $20k | 7% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 40 CY | $500 | $20k | 7% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 8,767 LB | $1.5 | $13k | 4% |
| 507E00100 STEEL PILES HP10X42, FURNISHED | 250 FT | $47.5 | $12k | 4% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 105 CY | $105 | $11k | 4% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $11,000 | $11k | 4% |
| 517E72300 RAILING (DEEP BEAM RAIL WITH STEEL TUBULAR BACKUP | 112.5 FT | $85 | $10k | 3% |