D07-CHIP-FY21 (A)
D07 County · est $0.7M
Bid dateThursday, February 11—
D07 County · est $0.7M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 5.0%
Bid form · ODOT
| Item | Qty | Unit price |
|---|
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 3 more items below.
| Item | Quantity | R1Ward Construction CO | R2Strawser Construction INC | R3Henry W Bergman INC | R4Shelly Company | % of bid |
|---|---|---|---|---|---|---|
| 422E25001 EMULSION, CHIP SEAL, AS PER PLAN | 82,412 GAL | $2.42 | $2.12 | $2.93 | $2.39 | 35% |
| 422E11001 AGGREGATE, SINGLE CHIP SEAL, TYPE A, AS PER PLAN | 206,025 SY | $0.55 | $0.65 | $0.42 | $0.65 | 20% |
| 253E01001 PAVEMENT REPAIR, AS PER PLAN | 1,150 SY | $34.50 | $75.00 | $70.00 | $48.75 | 7% |
| 642E30030 REMOVAL OF PAVEMENT MARKING EDGE LINE | 24.7 MILE | $1,320 | $1,350 | $1,000 | $1,338 | 6% |
| Item | Quantity | R1Ward Construction CO | R2Strawser Construction INC | R3Henry W Bergman INC | R4Shelly Company |
|---|---|---|---|---|---|
| 642E30000 REMOVAL OF PAVEMENT MARKING CHANNELIZING LINE | 166 FT | $1.00 | $1.00 | $0.75 | $2.50 |
| 642E30000 REMOVAL OF PAVEMENT MARKING STOP LINE | 37 FT | $5.00 | $5.05 | $2.60 | $10.00 |
| 642E30020 REMOVAL OF PAVEMENT MARKING ARROW | 2 EACH | $150 | $155 | $40.00 | $200 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $32,500 | $34,089 | $26,000 | $63,500 | 6% |
| 621E00100 RPM | 997 EACH | $29.00 | $29.00 | $29.00 | $29.00 | 5% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 49.4 MILE | $525 | $530 | $600 | $735 | 5% |
| 642E30030 REMOVAL OF PAVEMENT MARKING CENTER LINE | 12.35 MILE | $1,980 | $2,000 | $2,000 | $1,338 | 4% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1,573 EACH | $10.15 | $10.00 | $18.00 | $12.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $14,000 | $36,089 | $30,000 | $30,000 | 2% |
| 642E00300 CENTER LINE, TYPE 1 | 24.7 MILE | $540 | $545 | $700 | $640 | 2% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 24.7 MILE | $540 | $545 | $850 | $705 | 2% |
| 614E12460 WORK ZONE MARKING SIGN | 113 EACH | $80.00 | $105 | $100 | $100 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,600 | $3,500 | $10,000 | $3,500 | 1% |
| 642E00500 STOP LINE, TYPE 1 | 208 FT | $3.00 | $3.00 | $3.00 | $3.50 | 0% |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 208 FT | $3.00 | $3.05 | $3.00 | $3.00 | 0% |
| 642E01300 LANE ARROW, TYPE 1 RIGHT | 4 EACH | $100 | $105 | $40.00 | $92.00 | 0% |
| 644E30000 REMOVAL OF PAVEMENT MARKING STOP LINE | 67 FT | $5.00 | $5.15 | $3.50 | $10.00 | 0% |
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 332 FT | $1.00 | $1.00 | $1.00 | $1.30 | 0% |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 332 FT | $1.00 | $1.00 | $1.00 | $0.65 | 0% |
| Extended |
|---|
| % |
|---|
| 422E25001 EMULSION, CHIP SEAL, AS PER PLAN | 82,412 GAL | $2.42 | $199k | 35% |
| 422E11001 AGGREGATE, SINGLE CHIP SEAL, TYPE A, AS PER PLAN | 206,025 SY | $0.55 | $113k | 20% |
| 253E01001 PAVEMENT REPAIR, AS PER PLAN | 1,150 SY | $34.5 | $40k | 7% |
| 642E30030 REMOVAL OF PAVEMENT MARKING EDGE LINE | 24.7 MILE | $1,320 | $33k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $32,500 | $33k | 6% |
| 621E00100 RPM | 997 EACH | $29 | $29k | 5% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 49.4 MILE | $525 | $26k | 5% |
| 642E30030 REMOVAL OF PAVEMENT MARKING CENTER LINE | 12.35 MILE | $1,980 | $24k | 4% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1,573 EACH | $10.15 | $16k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $14,000 | $14k | 2% |