SAN-US 6-23.58 Str Rplmnt
SAN County · est $0.8M
Bid dateThursday, April 1—
SAN County · est $0.8M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 45 more items below.
| Item | Quantity | R1Great Lakes Demolition Company | R2R & I Construction INC | R3Mosser Construction INC | R4Miller Bros Const INC | R5Vernon Nagel INC | R6R G Zachrich Construction INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 515E12070 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 10 EACH | $11,750 | $12,850 | $12,800 | $12,000 | $13,900 | $15,000 | 25% |
| 526E25010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 223 SY | $265 | $240 | $235 | $250 | $225 | $266 | 13% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 86 CY | $525 | $550 |
| Item | Quantity | R1Great Lakes Demolition Company | R2R & I Construction INC | R3Mosser Construction INC | R4Miller Bros Const INC | R5Vernon Nagel INC | R6R G Zachrich Construction INC |
|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $250 | $1,000 | $7,000 | $5,000 | $1,000 | $1,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 35 FT | $5.00 | $2.00 | $11.00 | $10.00 | $18.00 | $16.29 |
| 202E35200 PIPE REMOVED, OVER 24" | 30 FT | $8.00 | $2.00 | $13.00 | $15.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $560 |
| $550 |
| $550 |
| $650 |
| 10% |
| 507E00550 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 720 FT | $47.50 | $37.00 | $45.00 | $60.00 | $42.00 | $60.00 | 7% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 159 CY | $164 | $162 | $162 | $162 | $178 | $162 | 6% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 57 CY | $450 | $800 | $825 | $800 | $900 | $800 | 6% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 16,565 LB | $1.35 | $1.50 | $1.10 | $1.25 | $1.25 | $1.10 | 5% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 123 FT | $160 | $159 | $159 | $159 | $159 | $159 | 4% |
| 442E10500 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 88 CY | $201 | $199 | $199 | $199 | $225 | $199 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $12,000 | $33,150 | $20,000 | $20,000 | $20,000 | $50,000 | 3% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 4 EACH | $2,600 | $2,550 | $2,550 | $2,550 | $2,550 | $2,550 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $10,000 | $4,800 | $6,000 | $7,500 | $11,500 | 2% |
| 507E00500 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 640 FT | $15.00 | $5.00 | $12.00 | $5.00 | $5.00 | $24.61 | 2% |
| 526E90011 TYPE A INSTALLATION, AS PER PLAN | 80 FT | $120 | $150 | $130 | $150 | $85.00 | $141 | 2% |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,300 | $2,275 | $2,275 | $2,275 | $2,275 | $2,275 | 2% |
| 516E43100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 40 EACH | $180 | $120 | $150 | $115 | $121 | $100 | 2% |
| 304E20000 AGGREGATE BASE | 159 CY | $45.00 | $50.00 | $65.00 | $50.00 | $55.00 | $64.00 | 2% |
| 202E23000 PAVEMENT REMOVED | 740 SY | $9.00 | $5.00 | $21.00 | $12.00 | $10.00 | $8.48 | 1% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $6,500 | $50,000 | $44,000 | $50,000 | $35,000 | $78,000 | 1% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $1,020 | $500 | $800 | $500 | $1,000 | $1,000 | 1% |
| $32.00 |
| $38.65 |
| 202E38000 GUARDRAIL REMOVED | 620 FT | $1.50 | $1.00 | $1.50 | $1.50 | $4.00 | $1.50 |
| 202E75000 FENCE REMOVED | 326 FT | $2.00 | $1.00 | $6.00 | $1.00 | $4.00 | $3.32 |
| 203E10000 EXCAVATION | 421 CY | $12.00 | $7.00 | $26.00 | $20.00 | $14.00 | $14.34 |
| 203E20000 EMBANKMENT | 290 CY | $12.00 | $10.00 | $9.00 | $20.00 | $14.00 | $11.49 |
| 204E10000 SUBGRADE COMPACTION | 864 SY | $1.00 | $1.50 | $4.00 | $1.25 | $1.00 | $1.85 |
| 606E15050 GUARDRAIL, TYPE MGS | 275 FT | $18.50 | $17.90 | $17.90 | $17.90 | $17.90 | $17.90 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 3 SY | $125 | $50.00 | $150 | $100 | $23.00 | $32.69 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 107.8 CY | $30.00 | $75.00 | $85.00 | $75.00 | $80.00 | $91.62 |
| 659E10000 SEEDING AND MULCHING | 1,175 SY | $2.00 | $2.00 | $2.50 | $2.50 | $3.30 | $3.30 |
| 659E14000 REPAIR SEEDING AND MULCHING | 59 SY | $1.00 | $1.00 | $1.00 | $1.00 | $3.30 | $3.30 |
| 659E15000 INTER-SEEDING | 59 SY | $1.00 | $1.00 | $0.50 | $0.50 | $3.00 | $3.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.16 TON | $500 | $500 | $550 | $550 | $600 | $600 |
| 659E35000 WATER | 7 MGAL | $5.00 | $1.00 | $10.00 | $10.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 6,100 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 1.1 CY | $1,100 | $1,000 | $1,800 | $1,550 | $2,200 | $1,494 |
| 605E31100 AGGREGATE DRAINS | 71 FT | $8.00 | $10.00 | $10.00 | $14.00 | $12.00 | $11.25 |
| 611E07600 18" CONDUIT, TYPE C | 43 FT | $40.00 | $30.00 | $65.00 | $55.00 | $45.00 | $65.32 |
| 611E16600 36" CONDUIT, TYPE C | 39 FT | $65.00 | $100 | $95.00 | $115 | $100 | $171 |
| 611E99575 MANHOLE, NO. 3, AS PER PLAN | 2 EACH | $2,250 | $2,000 | $3,600 | $3,200 | $5,000 | $5,131 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3.25" | 610 SY | $4.00 | $10.00 | $3.85 | $8.00 | $9.50 | $6.00 |
| 407E20000 NON-TRACKING TACK COAT | 165 GAL | $4.50 | $4.00 | $4.00 | $4.00 | $2.00 | $4.00 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 6 CY | $320 | $319 | $319 | $319 | $600 | $318 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 5 EACH | $100 | $5.00 | $55.00 | $7.00 | $12.00 | $8.83 |
| 626E00116 BARRIER REFLECTOR, TYPE 5, BI-DIRECTIONAL | 12 EACH | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 30.9 FT | $12.50 | $12.00 | $12.00 | $15.00 | $12.00 | $12.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 3 EACH | $77.00 | $75.00 | $27.00 | $65.00 | $75.00 | $75.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 3 EACH | $27.00 | $10.00 | $40.00 | $25.00 | $25.00 | $25.00 |
| 202E22900 APPROACH SLAB REMOVED | 81 SY | $10.00 | $30.00 | $46.00 | $30.00 | $32.00 | $40.00 |
| 202E23500 WEARING COURSE REMOVED | 139 SY | $4.00 | $10.00 | $7.00 | $8.00 | $13.00 | $6.54 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $4,500 | $500 | $100 | $1.00 | $2,000 | $2,000 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $3,500 | $15,000 | $5,300 | $15,000 | $25,000 | $19,226 |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $3,500 | $10,000 | $10,750 | $10,000 | $20,000 | $13,000 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 85 SY | $20.00 | $10.00 | $11.00 | $10.00 | $10.00 | $9.45 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 38 SF | $15.00 | $4.00 | $6.00 | $5.50 | $6.00 | $8.61 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 109 FT | $22.00 | $25.00 | $42.00 | $27.00 | $30.00 | $33.67 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 67 CY | $85.00 | $50.00 | $75.00 | $80.00 | $65.00 | $100 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 129 FT | $10.00 | $10.00 | $22.00 | $14.00 | $12.00 | $15.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 114 FT | $8.00 | $10.00 | $12.00 | $9.00 | $10.00 | $10.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 30 FT | $8.00 | $10.00 | $12.00 | $20.00 | $10.00 | $10.00 |
| 523E20000 DYNAMIC LOAD TESTING | 1 EACH | $3,500 | $3,300 | $4,500 | $3,875 | $3,230 | $4,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,000 | $3,750 | $3,375 | $4,000 | $3,750 | $6,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,000 | $2,000 | $3,700 | $7,500 | $6,000 | $12,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12070 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 10 EACH | $11,750 | $118k | 22% |
| 526E25010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 223 SY | $265 | $59k | 11% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 86 CY | $525 | $45k | 8% |
| 507E00550 12" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 720 FT | $47.5 | $34k | 6% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 159 CY | $164 | $26k | 5% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 57 CY | $450 | $26k | 5% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 16,565 LB | $1.35 | $22k | 4% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 123 FT | $160 | $20k | 4% |
| 442E10500 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 88 CY | $201 | $18k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $12,000 | $12k | 2% |