MAH-/TRU MCRO FY2022
MAH County · est $0.7M
Bid dateThursday, April 15—
MAH County · est $0.7M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 4%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 8 more items below.
| Item | Quantity | R1American Pavements INC | R2Strawser Construction INC | R3Pavement Maintenance Systems LLC | % of bid |
|---|---|---|---|---|---|
| 421E10011 MICROSURFACING, SURFACE COURSE, AS PER PLAN | 126,445 SY | $2.99 | $2.80 | $2.93 | 59% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 1,300 SY | $53.00 | $55.00 | $75.00 | 11% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $38,400 | $58,475 | $37,100 | 6% |
| 646E10010 EDGE LINE, 6" | 13.5 MILE | $2,000 | $2,100 | $2,000 | 4% |
| 646E50300 REMOVAL OF PAVEMENT MARKING | 20.25 MILE | $1,056 |
| Item | Quantity | R1American Pavements INC | R2Strawser Construction INC | R3Pavement Maintenance Systems LLC |
|---|---|---|---|---|
| 646E10300 CHANNELIZING LINE, 8" | 750 FT | $1.75 | $1.80 | $1.75 |
| 646E10500 CROSSWALK LINE | 144 FT | $6.50 | $6.75 | $6.50 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 48 FT | $8.50 | $8.55 | $8.50 |
| 646E50100 REMOVAL OF PAVEMENT MARKING | 1,152 FT | $1.50 | $1.55 | $1.50 |
| 614E12460 WORK ZONE MARKING SIGN | 20 EACH | $85.00 | $90.00 | $85.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $1,075 |
| $1,056 |
| 3% |
| 621E00100 RPM | 614 EACH | $27.35 | $26.00 | $25.90 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $16,600 | $52,085 | $32,910 | 3% |
| 646E10200 CENTER LINE | 6.75 MILE | $2,360 | $2,400 | $2,360 | 2% |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 27 MILE | $405 | $410 | $405 | 2% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 3 EACH | $2,500 | $1,385 | $2,500 | 1% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 491 EACH | $15.00 | $15.00 | $22.70 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 13.5 MILE | $455 | $460 | $450 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,760 | $1,000 | $5,800 | 1% |
| 623E39501 MONUMENT BOX ADJUSTED TO GRADE, AS PER PLAN | 6 EACH | $905 | $750 | $950 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $650 | $1,500 | $4,880 | 1% |
| 103E06000 PREMIUM FOR CONTRACT PERFORMANCE BOND, PAYMENT BON | 1 LS | $3,625 | $4,000 | $7,180 | 1% |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | 0% |
| 646E10400 STOP LINE | 210 FT | $10.25 | $10.25 | $10.25 | 0% |
| 646E20300 LANE ARROW | 13 EACH | $150 | $155 | $150 | 0% |
| 646E50000 REMOVAL OF PAVEMENT MARKING | 13 EACH | $150 | $155 | $150 | 0% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $65.00 | $200 | $450 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 1,500 FT | $0.55 | $0.55 | $0.55 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 420 FT | $2.50 | $2.50 | $2.50 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 421E10011 MICROSURFACING, SURFACE COURSE, AS PER PLAN | 126,445 SY | $2.99 | $378k | 58% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 1,300 SY | $53 | $69k | 11% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $38,400 | $38k | 6% |
| 646E10010 EDGE LINE, 6" | 13.5 MILE | $2,000 | $27k | 4% |
| 646E50300 REMOVAL OF PAVEMENT MARKING | 20.25 MILE | $1,056 | $21k | 3% |
| 621E00100 RPM | 614 EACH | $27.35 | $17k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $16,600 | $17k | 3% |
| 646E10200 CENTER LINE | 6.75 MILE | $2,360 | $16k | 2% |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 27 MILE | $405 | $11k | 2% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 3 EACH | $2,500 | $8k | 1% |