BRO-SR 221-06.80 Landslide Site
BRO County · est $1.6M
Bid dateThursday, May 27—
BRO County · est $1.6M
Published by ODOTon this contract’s Proposal PDF · EDGE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 29 more items below.
| Item | Quantity | R1Kokosing Construction Company INC | R2Shelly & Sands INC | R3Alan Stone CO INC | R4Sunesis Construction CO | R5Beaty Construction INC | R6John R Jurgensen Company | % of bid |
|---|---|---|---|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:W SECTION | 2,737 FT | $285 | $329 | $324 | $396 | $323 | $428 | 58% |
| 524E94903 DRILLED SHAFTS, 48" DIAMETER ABOVE BEDROCK, AS PER | 2,063 FT | $78.00 | $95.00 | $134 | $167 | $145 | $189 | 12% |
| 524E94905 DRILLED SHAFTS, 48" DIAMETER, INTO BEDROCK, AS PER | 710 FT | $141 | $115 |
| Item | Quantity | R1Kokosing Construction Company INC | R2Shelly & Sands INC | R3Alan Stone CO INC | R4Sunesis Construction CO | R5Beaty Construction INC | R6John R Jurgensen Company |
|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,000 | $5,500 | $5,000 | $4,725 | $40,000 | $16,368 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 40 FT | $56.00 | $45.00 | $18.50 | $36.07 | $65.00 | $54.74 |
| 202E35200 PIPE REMOVED, OVER 24" | 83 FT | $15.00 | $32.00 | $9.00 | $40.22 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $190 |
| $194 |
| $294 |
| $185 |
| 7% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILES, 30" DIAMETER, U | 1,986 FT | $43.00 | $50.00 | $45.00 | $74.80 | $123 | $110 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $26,000 | $48,686 | $100,000 | $100,000 | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 249 CY | $150 | $203 | $225 | $156 | $167 | $203 | 3% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (71 CY | $250 | $253 | $259 | $215 | $194 | $253 | 1% |
| 304E20000 AGGREGATE BASE | 259 CY | $68.00 | $68.00 | $57.00 | $73.47 | $65.00 | $80.23 | 1% |
| 203E10000 EXCAVATION | 802 CY | $19.00 | $20.00 | $22.50 | $22.71 | $37.00 | $19.14 | 1% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 51 CY | $250 | $415 | $281 | $230 | $210 | $415 | 1% |
| 605E06000 4" BASE PIPE UNDERDRAINS | 957 FT | $13.00 | $12.00 | $8.50 | $11.43 | $15.00 | $22.36 | 1% |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $9,500 | $11,500 | $7,300 | $7,750 | $8,750 | $9,069 | 1% |
| 606E15050 GUARDRAIL, TYPE MGS | 412.5 FT | $22.80 | $22.80 | $27.00 | $23.52 | $22.80 | $22.00 | 1% |
| 611E16400 36" CONDUIT, TYPE B, 706.02; 707.02(0.249); 707.33 | 45 FT | $188 | $225 | $250 | $201 | $208 | $246 | 1% |
| 614E12420 DETOUR SIGNING | 1 LS | $7,000 | $5,800 | $5,000 | $5,636 | $4,915 | $4,915 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $7,000 | $1,500 | $3,000 | $5,221 | $62,454 | $24,950 | 1% |
| 511E81300 CONCRETE, MISC.: PRECAST REINFORCED CONCRETE LAGGI | 1 EACH | $6,500 | $3,000 | $3,600 | $3,351 | $6,500 | $5,443 | 0% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,700 | $9,800 | $10,000 | $11,102 | $10,000 | $12,138 | 0% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, NCHRP 350/MASH 2016 | 2 EACH | $2,560 | $2,560 | $3,100 | $2,300 | $3,947 | $2,500 | 0% |
| $90.00 |
| $72.44 |
| 202E38000 GUARDRAIL REMOVED | 162 FT | $2.50 | $2.50 | $3.50 | $3.84 | $2.77 | $11.50 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $730 | $225 | $374 | $163 | $900 | $2,445 |
| 203E20000 EMBANKMENT | 184 CY | $3.00 | $13.00 | $7.00 | $7.73 | $15.50 | $17.31 |
| 204E10000 SUBGRADE COMPACTION | 1,634 SY | $2.00 | $3.00 | $2.50 | $2.35 | $2.95 | $3.00 |
| 204E45000 PROOF ROLLING | 1 HOUR | $125 | $200 | $305 | $312 | $220 | $195 |
| 623E40500 REFERENCE MONUMENT | 14 EACH | $350 | $650 | $320 | $497 | $275 | $423 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 2 SY | $172 | $100 | $291 | $121 | $435 | $424 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 9 CY | $160 | $125 | $180 | $129 | $300 | $304 |
| 659E10000 SEEDING AND MULCHING | 991 SY | $4.73 | $3.25 | $3.00 | $4.69 | $3.25 | $3.25 |
| 659E14000 REPAIR SEEDING AND MULCHING | 50 SY | $1.08 | $1.00 | $5.50 | $1.00 | $1.00 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.14 TON | $539 | $500 | $600 | $500 | $500 | $500 |
| 659E31000 LIME | 0.21 ACRE | $65.90 | $200 | $700 | $200 | $200 | $200 |
| 659E35000 WATER | 6 MGAL | $1.20 | $1.00 | $122 | $1.00 | $1.00 | $1.00 |
| 611E00410 4" CONDUIT, TYPE F FOR UNDERDRAIN OUTLET | 128 FT | $30.00 | $22.00 | $29.50 | $7.83 | $33.00 | $46.00 |
| 611E98540 CATCH BASIN, NO. 2-4 | 1 EACH | $2,750 | $2,800 | $2,100 | $2,360 | $3,125 | $2,225 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $360 | $250 | $310 | $215 | $705 | $1,187 |
| 407E10000 TACK COAT, .06 GAL/SY | 174 GAL | $5.00 | $5.00 | $2.50 | $4.50 | $1.85 | $5.00 |
| 621E00100 RPM | 5 EACH | $503 | $397 | $485 | $397 | $397 | $397 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 5 EACH | $76.00 | $35.00 | $6.00 | $0.01 | $75.00 | $21.69 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 2 EACH | $25.00 | $25.00 | $11.50 | $25.00 | $25.00 | $45.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $35.00 | $35.00 | $114 | $25.00 | $35.00 | $60.00 |
| 642E00100 EDGE LINE, 4", TYPE 1 | 0.2 MILE | $4,064 | $4,064 | $5,600 | $4,622 | $4,622 | $4,622 |
| 642E00300 CENTER LINE, TYPE 1 | 0.1 MILE | $8,178 | $8,178 | $11,000 | $9,245 | $9,245 | $9,245 |
| 616E10000 WATER | 3 MGAL | $59.00 | $25.00 | $0.40 | $11.56 | $20.00 | $145 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $100 | $500 | $122 | $5,907 | $5,000 | $3,719 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $4,300 | $450 | $3,200 | $1,417 | $35,000 | $7,939 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 507E00400 STEEL PILES, MISC.:W SECTION | 2,737 FT | $285 | $780k | 56% |
| 524E94903 DRILLED SHAFTS, 48" DIAMETER ABOVE BEDROCK, AS PER | 2,063 FT | $78 | $161k | 12% |
| 524E94905 DRILLED SHAFTS, 48" DIAMETER, INTO BEDROCK, AS PER | 710 FT | $141 | $100k | 7% |
| 524E95000 DRILLED SHAFTS, MISC.: PLUG PILES, 30" DIAMETER, U | 1,986 FT | $43 | $85k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 249 CY | $150 | $37k | 3% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (71 CY | $250 | $18k | 1% |
| 304E20000 AGGREGATE BASE | 259 CY | $68 | $18k | 1% |
| 203E10000 EXCAVATION | 802 CY | $19 | $15k | 1% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 51 CY | $250 | $13k | 1% |