LOR-SR 254-06.39
LOR County · est $0.6M
Bid dateThursday, June 17—
LOR County · est $0.6M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 30 more items below.
| Item | Quantity | R1Kokosing Construction Company INC | R2Ronyak Paving INC | R3Chagrin Valley Paving INC | R4Karvo Companies INC | % of bid |
|---|---|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 1,121 CY | $190 | $195 | $160 | $200 | 38% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 80 CY | $560 | $495 | $500 | $475 | 8% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.50 INCH) | 26,268 SY | $1.60 | $1.25 | $1.50 | $1.55 | 8% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 120 CY | $325 | $215 | $250 | $350 |
| Item | Quantity | R1Kokosing Construction Company INC | R2Ronyak Paving INC | R3Chagrin Valley Paving INC | R4Karvo Companies INC |
|---|---|---|---|---|---|
| 202E32000 CURB REMOVED | 125 FT | $10.00 | $9.00 | $5.00 | $15.00 |
| 202E32500 CURB AND GUTTER REMOVED | 175 FT | $10.00 | $18.00 | $15.00 | $15.00 |
| 202E32501 CURB AND GUTTER REMOVED, AS PER PLAN | 45 FT | $10.00 | $25.00 | $20.00 | $18.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 3 CY | $30.00 | $245 | $250 | $130 |
| 209E80000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 7% |
| 608E52000 CURB RAMP | 2,025 SF | $15.50 | $25.00 | $24.00 | $15.00 | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $28,517 | $37,395 | $77,000 | $70,000 | 5% |
| 611E98635 CATCH BASIN RECONSTRUCTED TO GRADE, AS PER PLAN | 14 EACH | $2,000 | $1,300 | $1,250 | $1,350 | 5% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 20 EACH | $1,100 | $975 | $1,100 | $1,100 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $44,100 | $50,000 | $28,040 | 4% |
| 617E10100 COMPACTED AGGREGATE | 186 CY | $85.00 | $70.00 | $60.00 | $65.00 | 3% |
| 209E60501 LINEAR GRADING, AS PER PLAN | 2.19 MILE | $4,720 | $2,000 | $750 | $2,500 | 2% |
| 253E02000 PAVEMENT REPAIR (LONGITUDINAL) | 20 CY | $500 | $265 | $250 | $300 | 2% |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 16 EACH | $575 | $850 | $750 | $800 | 2% |
| 608E10000 4" CONCRETE WALK | 1,040 SF | $8.00 | $7.00 | $10.00 | $7.00 | 1% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $70.00 | $75.00 | $75.00 | $70.00 | 1% |
| 202E30000 WALK REMOVED | 3,285 SF | $2.00 | $1.25 | $1.00 | $5.00 | 1% |
| 253E02000 PAVEMENT REPAIR (TRANSVERSE) | 10 CY | $560 | $510 | $750 | $485 | 1% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 6 SNMT | $900 | $900 | $900 | $900 | 1% |
| AA2 644E00600 CROSSWALK LINE (ALTERNATE 2) | 1,125 FT | $4.10 | $3.75 | $3.75 | $3.75 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 2,144 GAL | $1.90 | $2.00 | $2.00 | $2.25 | 1% |
| 34 EACH |
| $40.00 |
| $125 |
| $25.00 |
| $100 |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 15 FT | $50.00 | $60.00 | $75.00 | $45.00 |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 35 FT | $50.00 | $53.00 | $75.00 | $55.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 4 EACH | $800 | $1,025 | $1,100 | $1,200 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 3 EACH | $775 | $1,000 | $1,100 | $1,200 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 1,000 LB | $1.60 | $2.00 | $2.00 | $2.00 |
| 254E01010 PAVEMENT PLANING, PORTLAND CEMENT CONCRETE (2.50 I | 68 SY | $14.50 | $10.00 | $5.00 | $10.00 |
| 254E01600 PATCHING PLANED SURFACE | 133 SY | $1.25 | $2.00 | $10.00 | $1.00 |
| 408E10001 PRIME COAT, AS PER PLAN | 1,087 GAL | $3.45 | $2.50 | $2.00 | $4.00 |
| 617E20000 SHOULDER PREPARATION | 2,714 SY | $0.60 | $1.00 | $0.25 | $2.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 65 EACH | $12.00 | $1.00 | $1.00 | $2.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 2.26 MILE | $650 | $650 | $650 | $650 |
| 642E00300 CENTER LINE, TYPE 1 | 1.44 MILE | $885 | $885 | $885 | $885 |
| AA2 644E00400 CHANNELIZING LINE, 8" (ALTERNATE 2) | 1,142 FT | $1.65 | $1.50 | $1.50 | $1.50 |
| AA2 644E00500 STOP LINE (ALTERNATE 2) | 283 FT | $6.60 | $6.00 | $6.00 | $6.00 |
| AA2 644E00700 TRANSVERSE/DIAGONAL LINE (ALTERNATE 2) | 551 FT | $6.60 | $6.00 | $6.00 | $6.00 |
| AA2 644E01100 SCHOOL SYMBOL MARKING, 72" (ALTERNATE 2) | 2 EACH | $330 | $300 | $300 | $300 |
| AA2 644E01300 LANE ARROW (ALTERNATE 2) | 38 EACH | $88.00 | $80.00 | $80.00 | $80.00 |
| 614E12460 WORK ZONE MARKING SIGN | 8 EACH | $75.00 | $75.00 | $75.00 | $75.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 25 CY | $100 | $125 | $75.00 | $150 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 2.88 MILE | $900 | $900 | $900 | $900 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 2,284 FT | $0.50 | $0.50 | $0.50 | $0.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 434 FT | $3.50 | $3.50 | $3.50 | $3.50 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,400 | $5,000 | $5,000 | $5,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $900 | $2,036 | $500 | $2,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 1,121 CY | $190 | $213k | 35% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 80 CY | $560 | $45k | 7% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.50 INCH) | 26,268 SY | $1.6 | $42k | 7% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 120 CY | $325 | $39k | 6% |
| 608E52000 CURB RAMP | 2,025 SF | $15.5 | $31k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $28,517 | $29k | 5% |
| 611E98635 CATCH BASIN RECONSTRUCTED TO GRADE, AS PER PLAN | 14 EACH | $2,000 | $28k | 5% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 20 EACH | $1,100 | $22k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 3% |
| 617E10100 COMPACTED AGGREGATE | 186 CY | $85 | $16k | 3% |