SCI-SR 104-08.15 Landslide
SCI County · est $0.8M
Bid dateThursday, August 26—
SCI County · est $0.8M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 67 more items below.
| Item | Quantity | R1Allard Excavation LLC | R2D G M INC | R3Complete General Construction Company | R4Alan Stone CO INC | R5Eclipse CO LLC | R6Shelly & Sands INC | R7Sunesis Construction CO | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 624E10000 MOBILIZATION | 1 LS | $53,000 | $20,000 | $20,000 | $45,000 | $23,254 | $40,000 | $101,172 | 10% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 180 CY | $288 | $185 | $288 | $359 | $175 | $288 | $288 | 10% |
| 203E20000 EMBANKMENT |
| Item | Quantity | R1Allard Excavation LLC | R2D G M INC | R3Complete General Construction Company | R4Alan Stone CO INC | R5Eclipse CO LLC | R6Shelly & Sands INC | R7Sunesis Construction CO |
|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,560 | $41,500 | $10,000 | $25,000 | $31,500 | $43,000 | $11,389 |
| 202E20011 HEADWALL REMOVED, AS PER PLAN | 1 EACH | $1,030 | $500 | $400 | $3,700 | $1,085 | $500 | $1,861 |
| 202E35100 PIPE REMOVED, 24" AND UNDER |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 9,159 CY |
| $5.60 |
| $10.00 |
| $11.00 |
| $9.00 |
| $14.75 |
| $20.00 |
| $19.57 |
| 10% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $44,900 | $55,000 | $60,000 | $70,000 | $46,000 | $55,000 | $48,844 | 8% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 136 CY | $294 | $190 | $294 | $366 | $180 | $294 | $294 | 7% |
| 622E41110 PORTABLE BARRIER, ANCHORED | 1,369 FT | $27.90 | $16.50 | $22.00 | $25.00 | $32.00 | $10.00 | $27.90 | 7% |
| 611E22400 54" CONDUIT, TYPE B , 706.02, 707.01 (aluminized), | 104 FT | $357 | $800 | $600 | $500 | $289 | $500 | $436 | 7% |
| 203E10000 EXCAVATION | 6,442 CY | $5.50 | $9.00 | $7.00 | $8.00 | $17.50 | $18.00 | $11.43 | 7% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $24,750 | $8,500 | $2,000 | $15,000 | $17,227 | $25,000 | $9,100 | 5% |
| 832E30000 EROSION CONTROL | 22,534 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 4% |
| 511E81300 CONCRETE, MISC.: PRECAST LAGGING | 15 EACH | $1,190 | $1,300 | $2,000 | $1,600 | $1,500 | $1,200 | $2,252 | 3% |
| 524E94505 DRILLED SHAFTS, 24" DIAMETER, INTO BEDROCK, AS PER | 160 FT | $111 | $140 | $165 | $60.50 | $196 | $90.00 | $185 | 3% |
| 304E20000 AGGREGATE BASE | 284 CY | $50.00 | $70.00 | $60.00 | $58.00 | $62.75 | $75.00 | $69.43 | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 575 FT | $23.10 | $26.00 | $24.50 | $32.00 | $25.75 | $22.00 | $24.50 | 2% |
| 507E00400 STEEL PILES, MISC.: HP10X42 | 328 FT | $40.00 | $48.00 | $49.00 | $67.50 | $85.00 | $50.00 | $78.92 | 2% |
| 615E25001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B, AS PER | 117 SY | $108 | $75.00 | $170 | $65.00 | $75.75 | $95.00 | $105 | 2% |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $12,000 | $10,000 | $10,500 | $13,000 | $11,634 | $10,501 | $10,500 | 2% |
| 524E94503 DRILLED SHAFTS, 24" DIAMETER, ABOVE BEDROCK, AS PE | 102 FT | $116 | $85.00 | $155 | $62.00 | $175 | $110 | $178 | 2% |
| 611E99574 MANHOLE, NO. 3 | 2 EACH | $5,590 | $6,500 | $6,000 | $9,000 | $14,000 | $8,575 | $5,680 | 2% |
| 611E22600 54" CONDUIT, TYPE C , 706.02, 707.01 (aluminized), | 36 FT | $300 | $500 | $600 | $290 | $267 | $400 | $395 | 2% |
| 20 FT |
| $10.35 |
| $20.00 |
| $20.00 |
| $153 |
| $20.25 |
| $15.00 |
| $30.03 |
| 202E35200 PIPE REMOVED, OVER 24" | 127 FT | $15.65 | $50.00 | $75.00 | $14.50 | $32.25 | $9.00 | $20.49 |
| 202E38000 GUARDRAIL REMOVED | 713 FT | $1.50 | $1.00 | $5.00 | $3.00 | $1.75 | $2.50 | $4.02 |
| 202E53100 MAILBOX REMOVED | 3 EACH | $39.00 | $50.00 | $150 | $415 | $51.50 | $50.00 | $111 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $392 | $400 | $500 | $184 | $409 | $300 | $547 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT 24" | 55 FT | $59.00 | $35.00 | $50.00 | $42.50 | $66.75 | $40.00 | $30.53 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT 36" | 47 FT | $81.00 | $50.00 | $75.00 | $53.00 | $89.75 | $60.00 | $52.25 |
| 202E98000 REMOVAL MISC.: STEEL PILINGS AND RAIL TIES | 1 LS | $3,710 | $2,000 | $15,000 | $5,000 | $3,802 | $2,500 | $2,999 |
| 204E10000 SUBGRADE COMPACTION | 1,618 SY | $1.75 | $4.00 | $3.00 | $2.50 | $1.50 | $7.00 | $6.26 |
| 204E45000 PROOF ROLLING | 4 HOUR | $97.00 | $50.00 | $300 | $350 | $214 | $200 | $284 |
| 606E15150 GUARDRAIL, TYPE MGS HALF POST SPACING | 75 FT | $28.98 | $32.00 | $29.50 | $42.00 | $36.25 | $37.00 | $29.50 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 1 EACH | $1,650 | $1,700 | $2,050 | $1,800 | $1,640 | $1,500 | $2,050 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,200 | $1,250 | $2,000 | $1,600 | $1,402 | $1,100 | $2,000 |
| 623E38500 MONUMENT ASSEMBLY | 5 EACH | $700 | $600 | $1,000 | $2,500 | $1,074 | $1,100 | $979 |
| 690E50000 SPECIAL - MAILBOX SUPPORT | 3 EACH | $175 | $150 | $350 | $270 | $176 | $125 | $55.00 |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 14 CY | $57.50 | $100 | $95.00 | $143 | $77.00 | $105 | $192 |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 40 CY | $64.00 | $70.00 | $105 | $149 | $78.00 | $115 | $139 |
| 659E00301 TOPSOIL, AS PER PLAN | 530 CY | $15.00 | $12.00 | $30.00 | $40.00 | $48.00 | $30.00 | $28.02 |
| 659E10000 SEEDING AND MULCHING | 4,770 SY | $2.00 | $1.75 | $2.00 | $1.00 | $1.50 | $0.90 | $2.30 |
| 659E14000 REPAIR SEEDING AND MULCHING | 239 SY | $2.00 | $0.05 | $2.00 | $0.90 | $1.50 | $0.70 | $1.00 |
| 659E15000 INTER-SEEDING | 239 SY | $2.00 | $0.05 | $2.00 | $0.90 | $1.00 | $0.70 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.67 TON | $650 | $650 | $650 | $800 | $693 | $645 | $500 |
| 659E31000 LIME | 0.99 ACRE | $75.00 | $80.00 | $75.00 | $190 | $88.75 | $152 | $200 |
| 659E35000 WATER | 27 MGAL | $4.00 | $1.00 | $4.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 670E00700 DITCH EROSION PROTECTION | 238 SY | $1.95 | $3.00 | $1.95 | $2.00 | $2.50 | $1.70 | $2.35 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,700 | $2,000 | $1,450 | $1,800 | $3,500 | $2,000 | $1,450 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $7,100 | $8,000 | $1,360 | $6,800 | $9,500 | $8,700 | $2,720 |
| 602E20000 CONCRETE MASONRY | 5 CY | $1,168 | $1,300 | $1,000 | $963 | $892 | $1,500 | $2,284 |
| 605E13402 6" UNCLASSIFIED PIPE UNDERDRAINS FOR SPRINGS | 100 FT | $8.00 | $8.00 | $10.00 | $12.00 | $9.00 | $12.00 | $27.09 |
| 605E31100 AGGREGATE DRAINS | 144 FT | $10.00 | $20.00 | $20.00 | $22.50 | $14.00 | $18.00 | $16.00 |
| 605E32200 AGGREGATE DRAINS FOR SPRINGS | 100 FT | $13.15 | $6.00 | $12.00 | $15.00 | $14.00 | $18.00 | $22.44 |
| 611E07900 18" CONDUIT, TYPE D | 84 FT | $50.35 | $75.00 | $75.00 | $87.00 | $64.50 | $100 | $106 |
| 611E13400 30" CONDUIT, TYPE B , 706.02, 707.01 (aluminized), | 48 FT | $147 | $575 | $205 | $196 | $170 | $250 | $191 |
| 611E13600 30" CONDUIT, TYPE C , 706.02, 707.01 (aluminized), | 32 FT | $154 | $225 | $150 | $132 | $145 | $225 | $140 |
| 611E16400 36" CONDUIT, TYPE B , 706.02, 707.01 (aluminized), | 52 FT | $155 | $600 | $200 | $206 | $178 | $300 | $465 |
| 611E16600 36" CONDUIT, TYPE C , 706.02, 707.01 (aluminized), | 32 FT | $164 | $225 | $200 | $138 | $163 | $250 | $225 |
| 611E98260 CATCH BASIN, NO. 4 WITHOUT APRON | 2 EACH | $3,140 | $3,750 | $3,000 | $3,300 | $4,155 | $3,900 | $4,376 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $1,380 | $1,300 | $2,000 | $2,600 | $2,024 | $2,350 | $3,349 |
| 611E98570 CATCH BASIN, NO. 2-5 | 1 EACH | $4,265 | $5,500 | $5,000 | $4,000 | $7,511 | $6,200 | $6,660 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 5 EACH | $325 | $75.00 | $275 | $345 | $212 | $350 | $302 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE1.5" | 1,163 SY | $7.25 | $7.50 | $7.25 | $9.00 | $7.25 | $7.25 | $8.05 |
| 407E10000 TACK COAT | 231 GAL | $1.75 | $5.00 | $1.75 | $2.00 | $5.50 | $1.75 | $1.75 |
| 411E10000 STABILIZED CRUSHED AGGREGATE | 64 CY | $54.00 | $110 | $90.00 | $62.50 | $84.25 | $85.00 | $78.54 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (19 CY | $294 | $190 | $294 | $366 | $180 | $294 | $294 |
| 644E00100 EDGE LINE, 4" | 0.29 MILE | $5,390 | $11,000 | $5,390 | $6,700 | $7,202 | $6,500 | $5,390 |
| 644E00300 CENTER LINE | 0.14 MILE | $10,100 | $14,000 | $10,100 | $13,000 | $8,199 | $7,400 | $20,800 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 16 HOUR | $85.00 | $50.00 | $80.00 | $81.00 | $72.00 | $65.00 | $68.65 |
| 614E11630 INCREASED BARRIER DELINEATION | 370 FT | $1.70 | $2.00 | $1.70 | $2.00 | $5.50 | $0.50 | $1.70 |
| 614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,900 | $1,900 | $3,000 | $2,900 | $2,438 | $2,000 | $2,100 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 29 EACH | $28.50 | $15.00 | $28.50 | $35.50 | $6.75 | $8.00 | $28.50 |
| 614E13314 BARRIER REFLECTOR, TYPE 3 (BI-DIRECTIONAL) | 13 EACH | $52.00 | $15.00 | $52.00 | $65.00 | $6.75 | $9.00 | $52.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 42 EACH | $29.50 | $15.00 | $29.50 | $37.00 | $11.00 | $12.00 | $29.50 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.38 MILE | $16,600 | $14,000 | $16,600 | $21,000 | $14,625 | $16,600 | $16,600 |
| 614E22200 WORK ZONE EDGE LINE, CLASS I, 4", 740.06, TYPE I | 0.58 MILE | $8,750 | $7,500 | $8,750 | $11,000 | $6,728 | $8,750 | $8,750 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 48 FT | $12.00 | $12.00 | $12.00 | $15.00 | $4.50 | $12.00 | $12.00 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $2,750 | $1,000 | $5,000 | $11,000 | $6,500 | $14,000 | $4,124 |
| 616E10000 WATER | 30 MGAL | $1.00 | $1.00 | $60.00 | $0.10 | $30.75 | $30.00 | $11.94 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $2,500 | $2,000 | $4,000 | $10,000 | $5,000 | $7,050 | $15,823 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 61 CY | $77.00 | $85.00 | $75.00 | $121 | $82.25 | $120 | $65.49 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 100 FT | $5.80 | $20.00 | $16.50 | $5.00 | $4.50 | $7.00 | $3.43 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 15 FT | $6.25 | $20.00 | $25.00 | $27.50 | $15.50 | $30.00 | $22.45 |
| 601E20000 CRUSHED AGGREGATE SLOPE PROTECTION | 2 SY | $120 | $200 | $250 | $461 | $51.25 | $200 | $180 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $5,720 | $2,500 | $10,000 | $5,600 | $3,500 | $2,600 | $6,923 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,200 | $10,000 | $9,000 | $6,000 | $15,400 | $7,015 | $6,499 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $1,200 | $1,500 | $2,000 | $2,600 | $600 | $4,450 | $1,552 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 624E10000 MOBILIZATION | 1 LS | $53,000 | $53k | 7% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 180 CY | $288 | $52k | 7% |
| 203E20000 EMBANKMENT | 9,159 CY | $5.6 | $51k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $44,900 | $45k | 6% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 136 CY | $294 | $40k | 6% |
| 622E41110 PORTABLE BARRIER, ANCHORED | 1,369 FT | $27.9 | $38k | 5% |
| 611E22400 54" CONDUIT, TYPE B , 706.02, 707.01 (aluminized), | 104 FT | $357 | $37k | 5% |
| 203E10000 EXCAVATION | 6,442 CY | $5.5 | $35k | 5% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $24,750 | $25k | 3% |
| 832E30000 EROSION CONTROL | 22,534 EACH | $1 | $23k | 3% |