GUE-US 22-14.57
GUE County · est $0.4M
Bid dateThursday, September 16—
GUE County · est $0.4M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 5.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 22 more items below.
| Item | Quantity | R1Alan Stone CO INC | R2Ohio-west Virginia Excavating CO | R3Shelly & Sands INC | R4Great Lakes Construction CO | R5Wolf Creek Contracting Company LLC | R6Dot Construction CORP | R7Kokosing Construction Company INC | R8George J Igel & CO INC | R9Craig Edward Susany INC | R10Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 1,184 FT | $80.50 | $106 | $100 | $100 | $111 | $90.00 | $110 | $90.00 | $90.00 | $98.00 |
| Item | Quantity | R1Alan Stone CO INC | R2Ohio-west Virginia Excavating CO | R3Shelly & Sands INC | R4Great Lakes Construction CO | R5Wolf Creek Contracting Company LLC | R6Dot Construction CORP | R7Kokosing Construction Company INC | R8George J Igel & CO INC | R9Craig Edward Susany INC | R10Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 1 EACH | $1,800 | $1,000 | $150 | $250 | $440 | $500 | $500 | $320 | $100 | $400 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 27% |
| 507E00400 STEEL PILES, MISC.: W21X68 SOLDIER PILE | 1,256 FT | $57.50 | $60.00 | $57.00 | $65.00 | $65.80 | $80.00 | $78.00 | $90.00 | $68.00 | $87.00 | 20% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 767 FT | $68.00 | $116 | $115 | $110 | $128 | $110 | $124 | $130 | $150 | $150 | 15% |
| 624E10000 MOBILIZATION | 1 LS | $21,000 | $12,500 | $10,000 | $50,000 | $54,848 | $20,000 | $10,000 | $12,000 | $20,000 | $20,000 | 6% |
| 611E05900 15" CONDUIT, TYPE B | 94 FT | $213 | $130 | $200 | $125 | $27.22 | $50.00 | $225 | $135 | $100 | $100 | 6% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 143 CY | $79.50 | $91.00 | $155 | $150 | $62.95 | $80.00 | $150 | $120 | $110 | $88.00 | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 400 FT | $26.00 | $22.50 | $27.00 | $27.00 | $26.35 | $27.00 | $22.40 | $23.00 | $28.00 | $27.00 | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22, 10" DEPTH | 8 CY | $1,100 | $420 | $1,000 | $500 | $1,049 | $892 | $1,000 | $725 | $1,000 | $892 | 2% |
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 10 CY | $827 | $400 | $1,000 | $300 | $771 | $655 | $1,000 | $570 | $1,000 | $655 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $7,600 | $3,500 | $2,000 | $3,500 | $4,000 | $15,000 | $2,585 | $12,000 | $30,000 | $5,000 | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $7,000 | $5,200 | $4,500 | $3,575 | $6,118 | $5,570 | $6,943 | $12,000 | $6,000 | $5,570 | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 85 CY | $81.00 | $95.00 | $55.00 | $130 | $81.67 | $80.00 | $197 | $80.00 | $100 | $135 | 2% |
| 518E40001 6" PERFORATED CORRUGATED PLASTIC PIPE, AS PER PLAN | 405 FT | $16.50 | $6.00 | $2.75 | $5.00 | $7.22 | $40.00 | $13.00 | $18.90 | $10.00 | $8.00 | 2% |
| 606E15100 GUARDRAIL, TYPE MGS WITH LONG POSTS | 225 FT | $29.50 | $25.50 | $31.00 | $31.00 | $29.65 | $31.00 | $25.20 | $36.50 | $29.00 | $31.00 | 2% |
| 209E60200 LINEAR GRADING | 8 STA | $720 | $475 | $200 | $325 | $176 | $300 | $515 | $730 | $800 | $700 | 2% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $5,300 | $1,000 | $7,500 | $10,500 | $2,941 | $8,000 | $6,500 | $6,500 | $4,000 | $4,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,000 | $6,500 | $3,450 | $5,000 | $5,476 | $5,000 | $1,973 | $4,500 | $20,000 | $6,000 | 1% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP350 OR MASH 2016 | 1 EACH | $3,300 | $2,800 | $3,150 | $3,150 | $3,271 | $3,150 | $2,780 | $2,925 | $2,849 | $3,150 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $3,200 | $3,500 | $5,750 | $2,000 | $1,355 | $15,000 | $5,000 | $15,000 | $2,500 | $30,000 | 1% |
| 408E10000 PRIME COAT | 26 GAL | $120 | $10.00 | $10.00 | $10.00 | $112 | $95.00 | $57.70 | $17.50 | $100 | $95.00 | 1% |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 88 FT | $16.50 | $15.00 | $12.00 | $10.00 | $4.40 | $20.00 | $7.00 | $38.50 | $25.00 | $20.00 |
| 202E38000 GUARDRAIL REMOVED | 449 FT | $3.00 | $3.00 | $7.50 | $7.50 | $2.35 | $7.50 | $2.00 | $4.00 | $4.00 | $7.50 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $179 | $1,150 | $250 | $500 | $118 | $500 | $850 | $450 | $100 | $450 |
| 203E10000 EXCAVATION | 160 CY | $8.50 | $17.00 | $9.00 | $35.00 | $12.05 | $40.00 | $50.00 | $37.50 | $25.00 | $30.00 |
| 203E20000 EMBANKMENT | 214 CY | $4.00 | $24.00 | $20.00 | $18.00 | $16.61 | $60.00 | $16.00 | $14.00 | $25.00 | $34.00 |
| 204E10000 SUBGRADE COMPACTION | 430 SY | $2.50 | $4.00 | $7.00 | $4.00 | $1.93 | $2.00 | $3.00 | $6.60 | $3.00 | $3.00 |
| 601E32304 ROCK CHANNEL PROTECTION, TYPE D WITH GEOTEXTILE FA | 15 CY | $166 | $120 | $180 | $300 | $261 | $200 | $146 | $130 | $110 | $120 |
| 659E00510 SEEDING AND MULCHING, CLASS 2 | 1,404 SY | $1.50 | $4.00 | $1.85 | $1.84 | $2.47 | $3.25 | $1.84 | $1.95 | $4.00 | $1.84 |
| 659E20000 COMMERCIAL FERTILIZER | 0.19 TON | $752 | $650 | $667 | $667 | $824 | $500 | $667 | $700 | $700 | $667 |
| 659E31000 LIME | 0.29 ACRE | $179 | $60.00 | $155 | $154 | $94.10 | $200 | $154 | $160 | $70.00 | $154 |
| 659E35000 WATER | 8 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.18 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 10 FT | $17.00 | $40.00 | $20.00 | $25.00 | $8.42 | $40.00 | $18.00 | $56.50 | $20.00 | $30.00 |
| 602E20000 CONCRETE MASONRY | 2 CY | $490 | $1,100 | $700 | $2,500 | $602 | $2,500 | $1,500 | $700 | $1,000 | $700 |
| 611E98500 CATCH BASIN, NO. 2-2B WITH APRON | 1 EACH | $1,700 | $2,700 | $3,500 | $2,750 | $2,029 | $5,000 | $3,600 | $2,350 | $4,000 | $5,000 |
| 611E98635 CATCH BASIN RECONSTRUCTED TO GRADE, AS PER PLAN | 1 EACH | $748 | $1,800 | $1,000 | $1,400 | $781 | $2,500 | $225 | $350 | $2,500 | $700 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 1 EACH | $327 | $500 | $300 | $325 | $219 | $500 | $500 | $310 | $200 | $250 |
| 304E20000 AGGREGATE BASE | 10 CY | $78.00 | $190 | $135 | $125 | $101 | $200 | $185 | $122 | $100 | $130 |
| 407E10000 TACK COAT | 30 GAL | $5.00 | $10.00 | $3.00 | $3.00 | $4.71 | $4.00 | $3.00 | $15.00 | $5.00 | $4.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 13 EACH | $10.50 | $9.00 | $10.00 | $9.50 | $10.59 | $9.50 | $9.00 | $10.00 | $10.00 | $15.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 4 SNMT | $750 | $1,600 | $900 | $715 | $1,882 | $750 | $750 | $715 | $800 | $750 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 524E94703 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK, AS PE | 1,184 FT | $80.5 | $95k | 25% |
| 507E00400 STEEL PILES, MISC.: W21X68 SOLDIER PILE | 1,256 FT | $57.5 | $72k | 19% |
| 524E94705 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK, AS PER | 767 FT | $68 | $52k | 14% |
| 624E10000 MOBILIZATION | 1 LS | $21,000 | $21k | 5% |
| 611E05900 15" CONDUIT, TYPE B | 94 FT | $213 | $20k | 5% |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 143 CY | $79.5 | $11k | 3% |
| 606E15050 GUARDRAIL, TYPE MGS | 400 FT | $26 | $10k | 3% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22, 10" DEPTH | 8 CY | $1,100 | $9k | 2% |
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 10 CY | $827 | $8k | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $7,600 | $8k | 2% |