DEL-US 42-02.28
DEL County · est $4.8M
Bid dateThursday, February 17—
DEL County · est $4.8M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 111 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Complete General Construction Company | R3Mark Schaffer Excavating & Trucking | % of bid |
|---|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 5,926 CY | $140 | $133 | $155 | 22% |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 3,627 CY | $175 | $176 | $200 | 17% |
| 611E32000 108" CONDUIT, TYPE A, 706.02 OR 120" CONDUIT, TYPE | 147 FT | $2,150 | $1,200 | $1,600 | 8% |
| 832E30000 EROSION CONTROL | 280,000 EACH | $1.00 | $1.00 | $1.00 | 7% |
| 861E11100 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP |
| Item | Quantity | R1Shelly & Sands INC | R2Complete General Construction Company | R3Mark Schaffer Excavating & Trucking |
|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $40,000 | $1,500 |
| 202E11000 STRUCTURE REMOVED | 1 LS | $40,000 | $110,000 | $61,000 |
| 202E20010 HEADWALL REMOVED | 6 EACH | $170 | $350 | $725 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 709 FT | $7.50 | $16.00 | $25.00 |
| 202E38000 GUARDRAIL REMOVED | 100 FT | $2.50 | $2.00 | $3.00 |
| 202E42000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1,790 CY |
| $152 |
| $152 |
| $175 |
| 7% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 5,640 CY | $43.00 | $51.00 | $80.00 | 6% |
| 202E23000 PAVEMENT REMOVED | 20,244 SY | $9.50 | $13.00 | $10.00 | 5% |
| 203E10000 EXCAVATION | 12,216 CY | $15.00 | $28.00 | $60.00 | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE 1-1/2" | 41,408 SY | $2.70 | $1.15 | $1.20 | 3% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 1,285 SY | $85.00 | $75.00 | $60.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $200,000 | $200,000 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $98,000 | $160,000 | $125,000 | 3% |
| 251E01041 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 2,500 SY | $27.00 | $23.00 | $25.00 | 2% |
| 605E11110 6" SHALLOW PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 4,713 FT | $13.00 | $13.00 | $13.50 | 2% |
| 611E26000 72" CONDUIT, TYPE A, 706.02 OR 78" CONDUIT, TYPE A | 79 FT | $745 | $1,000 | $850 | 2% |
| 605E31100 AGGREGATE DRAINS | 4,900 FT | $12.00 | $22.00 | $9.50 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, VARIABLE DEPTH | 14,158 SY | $3.75 | $2.78 | $3.00 | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 3,900 FT | $13.00 | $19.00 | $37.00 | 1% |
| 602E20000 CONCRETE MASONRY | 27 CY | $1,800 | $1,500 | $1,400 | 1% |
| 304E20000 AGGREGATE BASE | 706 CY | $67.00 | $70.00 | $75.00 | 1% |
| 4 EACH |
| $350 |
| $290 |
| $400 |
| 202E58100 CATCH BASIN REMOVED | 2 EACH | $125 | $350 | $500 |
| 202E98000 REMOVAL MISC.:RIPRAP REMOVED | 1 LS | $750 | $12,000 | $500 |
| 202E98000 REMOVAL MISC.:STONE RETAINING WALLS REMOVED | 1 LS | $750 | $3,400 | $500 |
| 202E98100 REMOVAL MISC.:BOULDER REMOVED | 2 EACH | $75.00 | $1,000 | $250 |
| 203E20000 EMBANKMENT | 1,613 CY | $10.00 | $12.00 | $35.00 |
| 204E10000 SUBGRADE COMPACTION | 28,037 SY | $1.25 | $2.50 | $1.50 |
| 204E13000 EXCAVATION OF SUBGRADE | 600 CY | $27.00 | $30.00 | $60.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 600 CY | $42.00 | $45.00 | $80.00 |
| 204E45000 PROOF ROLLING | 27 HOUR | $400 | $305 | $175 |
| 204E50000 GEOTEXTILE FABRIC | 1,800 SY | $0.75 | $3.00 | $2.25 |
| 204E51000 GEOGRID | 1,800 SY | $0.90 | $5.00 | $3.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 1,075 FT | $22.50 | $21.60 | $25.00 |
| 606E17360 GUARDRAIL, TYPE MGS, LONG-SPAN | 75 FT | $28.50 | $24.20 | $30.00 |
| 606E26100 ANCHOR ASSEMBLY, TYPE E | 4 EACH | $2,650 | $2,825 | $3,000 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 9 EACH | $2,700 | $2,940 | $3,000 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 3 EACH | $1,250 | $1,430 | $1,400 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 19 EACH | $200 | $135 | $150 |
| 690E50200 SPECIAL - MAILBOX SUPPORT SYSTEM, DOUBLE | 1 EACH | $250 | $265 | $300 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 18 SY | $125 | $75.00 | $125 |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 94 CY | $110 | $150 | $85.00 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 3 CY | $150 | $200 | $275 |
| 601E32201 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER, AS PE | 2 CY | $200 | $270 | $375 |
| 659E00300 TOPSOIL | 2,636 CY | $10.00 | $25.00 | $20.00 |
| 659E10000 SEEDING AND MULCHING | 23,746 SY | $0.80 | $0.85 | $0.90 |
| 659E14000 REPAIR SEEDING AND MULCHING | 1,187 SY | $0.70 | $0.85 | $0.60 |
| 659E15000 INTER-SEEDING | 1,187 SY | $0.85 | $0.85 | $0.30 |
| 659E20000 COMMERCIAL FERTILIZER | 3.32 TON | $650 | $800 | $650 |
| 659E31000 LIME | 4.91 ACRE | $155 | $80.00 | $12.00 |
| 659E35000 WATER | 131 MGAL | $1.00 | $1.00 | $5.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,500 | $2,500 | $1,500 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $5,000 | $6,300 | $3,500 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $9,000 | $8,806 | $10,000 |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS (707.31 TYPE CP OR 707 | 60 FT | $17.00 | $14.00 | $16.00 |
| 605E13410 6" UNCLASSIFIED PIPE UNDERDRAINS WITH GEOTEXTILE F | 2,333 FT | $12.00 | $17.00 | $12.50 |
| 611E00400 4" CONDUIT, TYPE E | 50 FT | $12.00 | $10.00 | $30.00 |
| 611E00406 4" CONDUIT, TYPE F | 50 FT | $12.00 | $11.00 | $30.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 211 FT | $17.00 | $27.00 | $30.00 |
| 611E00900 6" CONDUIT, TYPE B, 706.08 | 42 FT | $75.00 | $56.00 | $45.00 |
| 611E01400 6" CONDUIT, TYPE E | 50 FT | $13.00 | $20.00 | $35.00 |
| 611E01500 6" CONDUIT, TYPE F | 50 FT | $13.00 | $20.00 | $35.00 |
| 611E04400 12" CONDUIT, TYPE B | 63 FT | $100 | $125 | $105 |
| 611E04600 12" CONDUIT, TYPE C | 16 FT | $110 | $90.00 | $80.00 |
| 611E04900 12" CONDUIT, TYPE D | 449 FT | $60.00 | $80.00 | $70.00 |
| 611E06100 15" CONDUIT, TYPE C | 19 FT | $125 | $125 | $90.00 |
| 611E07900 18" CONDUIT, TYPE D | 29 FT | $90.00 | $120 | $95.00 |
| 611E10200 24" CONDUIT, TYPE A, 706.02, 707.33 W/ WELDED BELL | 60 FT | $175 | $180 | $285 |
| 611E10900 24" CONDUIT, TYPE D | 50 FT | $95.00 | $135 | $110 |
| 611E52200 14" X 23" CONDUIT, TYPE A, 706.04 | 123 FT | $200 | $300 | $325 |
| 611E52900 34" X 53" CONDUIT, TYPE A, 706.04 | 64 FT | $390 | $450 | $480 |
| 611E98390 CATCH BASIN, NO. 7 | 1 EACH | $5,000 | $3,200 | $3,000 |
| 611E98470 CATCH BASIN, NO. 2-2B | 1 EACH | $2,500 | $3,000 | $2,500 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 10 EACH | $300 | $450 | $500 |
| 670E00500 SLOPE EROSION PROTECTION | 1,666 SY | $1.50 | $3.00 | $3.00 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 20,475 FT | $0.20 | $2.00 | $3.00 |
| 255E10010 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 130 SY | $300 | $243 | $200 |
| 305E14010 10" CONCRETE BASE, CLASS QC 1P | 130 SY | $130 | $160 | $140 |
| 407E20000 NON-TRACKING TACK COAT | 10,003 GAL | $3.00 | $3.05 | $4.00 |
| 442E20200 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 99 CY | $140 | $280 | $300 |
| 451E30000 SPECIAL - PRESSURE RELIEF JOINT, TYPE A | 62 FT | $92.00 | $92.00 | $100 |
| 617E10100 COMPACTED AGGREGATE | 233 CY | $90.00 | $93.00 | $75.00 |
| 617E25000 WATER | 0.47 MGAL | $200 | $1,600 | $1.00 |
| 618E41000 RUMBLE STRIPES, EDGE LINE (ASPHALT CONCRETE) | 3.99 MILE | $1,175 | $1,050 | $1,100 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 1.97 MILE | $1,175 | $1,050 | $1,100 |
| 621E00100 RPM | 531 EACH | $30.50 | $30.50 | $35.00 |
| 630E02101 GROUND MOUNTED SUPPORT, NO. 2 POST, AS PER PLAN | 159 FT | $8.50 | $14.50 | $15.00 |
| 630E03101 GROUND MOUNTED SUPPORT, NO. 3 POST, AS PER PLAN | 27 FT | $25.00 | $15.50 | $16.00 |
| 630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST | 27 FT | $20.00 | $17.00 | $18.00 |
| 630E80100 SIGN, FLAT SHEET | 103 SF | $20.00 | $19.00 | $20.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 18 EACH | $20.00 | $10.00 | $11.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 18 EACH | $20.00 | $15.00 | $16.00 |
| 642E00300 CENTER LINE, TYPE 1 | 2 MILE | $1,100 | $1,100 | $1,550 |
| 644E00104 EDGE LINE, 6" | 7.6 MILE | $3,900 | $3,900 | $5,500 |
| 644E00300 CENTER LINE | 4.17 MILE | $3,780 | $3,780 | $5,500 |
| 644E00400 CHANNELIZING LINE, 8" | 1,815 FT | $1.50 | $1.50 | $2.50 |
| 644E00500 STOP LINE | 151 FT | $6.25 | $6.25 | $10.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 614 FT | $6.00 | $6.00 | $10.00 |
| 644E01300 LANE ARROW | 14 EACH | $89.00 | $59.00 | $125 |
| 646E10010 EDGE LINE, 6" | 0.82 MILE | $6,590 | $6,590 | $9,000 |
| 646E10200 CENTER LINE | 0.91 MILE | $10,933 | $10,933 | $15,000 |
| 646E10300 CHANNELIZING LINE, 8" | 655 FT | $2.30 | $2.30 | $3.25 |
| 646E10400 STOP LINE | 74 FT | $11.20 | $11.20 | $16.00 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 462 FT | $8.00 | $8.00 | $11.00 |
| 646E20300 LANE ARROW | 8 EACH | $160 | $160 | $225 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 340 EACH | $4.00 | $8.00 | $4.00 |
| 304E20000 AGGREGATE BASE | 225 CY | $95.00 | $70.00 | $80.00 |
| 410E11000 TRAFFIC COMPACTED SURFACE, TYPE B | 50 CY | $105 | $50.00 | $65.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 60 HOUR | $72.00 | $81.00 | $90.00 |
| 614E11630 INCREASED BARRIER DELINEATION | 990 FT | $0.50 | $3.00 | $3.25 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,800 | $2,400 | $1,850 |
| 614E12420 DETOUR SIGNING | 1 LS | $30,000 | $45,000 | $30,000 |
| 614E12600 REPLACEMENT DRUM | 20 EACH | $55.00 | $200 | $55.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 200 CY | $215 | $275 | $400 |
| 614E13310 BARRIER REFLECTOR, TYPE 1(ONE-WAY) OR BI-DIRECTION | 48 EACH | $6.00 | $12.00 | $17.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 42 EACH | $12.00 | $15.00 | $17.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $750 | $1,100 | $700 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 3.73 MILE | $1,652 | $1,652 | $2,300 |
| 614E22010 WORK ZONE EDGE LINE, CLASS I, 6" | 12.92 MILE | $1,125 | $1,125 | $1,550 |
| 616E10000 WATER | 33 MGAL | $50.00 | $450 | $1.00 |
| 622E41110 PORTABLE BARRIER, ANCHORED | 360 FT | $40.00 | $50.00 | $38.00 |
| 644E30030 REMOVAL OF PAVEMENT MARKING | 0.2 MILE | $12,408 | $12,408 | $17,000 |
| 646E50000 REMOVAL OF PAVEMENT MARKING | 3 EACH | $120 | $120 | $165 |
| 646E50300 REMOVAL OF PAVEMENT MARKING | 0.63 MILE | $12,408 | $12,408 | $17,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $27,000 | $32,000 | $50,000 |
| 619E16010 FIELD OFFICE, TYPE B | 7 MNTH | $2,400 | $2,000 | $1,300 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $38,000 | $90,000 | $50,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 5,926 CY | $140 | $830k | 17% |
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 3,627 CY | $175 | $635k | 13% |
| 611E32000 108" CONDUIT, TYPE A, 706.02 OR 120" CONDUIT, TYPE | 147 FT | $2,150 | $316k | 7% |
| 832E30000 EROSION CONTROL | 280,000 EACH | $1 | $280k | 6% |
| 861E11100 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 1,790 CY | $152 | $272k | 6% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 5,640 CY | $43 | $243k | 5% |
| 202E23000 PAVEMENT REMOVED | 20,244 SY | $9.5 | $192k | 4% |
| 203E10000 EXCAVATION | 12,216 CY | $15 | $183k | 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE 1-1/2" | 41,408 SY | $2.7 | $112k | 2% |
| 615E25000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS B | 1,285 SY | $85 | $109k | 2% |