CUY-IR 71-05.71 Barrier
CUY County · est $7.0M
Bid dateThursday, March 17—
CUY County · est $7.0M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 93 more items below.
| Item | Quantity | R1Karvo Companies INC | R2Kokosing Construction Company INC | R3Shelly & Sands INC | R4Great Lakes Construction CO | R5Ruhlin Company | R6Kenmore Construction CO INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 622E10101 CONCRETE BARRIER, SINGLE SLOPE, TYPE B1, AS PER PL | 16,851 FT | $118 | $142 | $141 | $134 | $148 | $164 | 28% |
| 622E25006 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 133 EACH | $4,200 | $3,250 | $4,300 | $3,200 | $3,025 | $2,600 | 8% |
| 625E40000 SPECIAL - MAINTAIN EXISTING LIGHTING | 1 LS | $464,500 | $435,000 |
| Item | Quantity | R1Karvo Companies INC | R2Kokosing Construction Company INC | R3Shelly & Sands INC | R4Great Lakes Construction CO | R5Ruhlin Company | R6Kenmore Construction CO INC |
|---|---|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 159 SY | $20.00 | $15.80 | $21.00 | $30.00 | $40.00 | $25.00 |
| 202E38000 GUARDRAIL REMOVED | 50 FT | $3.60 | $2.40 | $3.00 | $2.40 | $2.40 | $2.50 |
| 203E10000 EXCAVATION | 609 CY | $11.00 | $42.00 | $24.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $490,000 |
| $454,500 |
| $497,500 |
| $456,000 |
| 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $400,000 | $500,000 | $250,000 | $250,000 | $466,500 | $400,000 | 6% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 48,830 FT | $7.50 | $10.00 | $9.00 | $12.00 | $9.50 | $20.00 | 5% |
| 202E30701 CONCRETE BARRIER REMOVED, AS PER PLAN | 22,042 FT | $15.00 | $23.50 | $21.00 | $31.50 | $36.00 | $12.00 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $295,271 | $200,000 | $200,000 | $200,000 | $200,000 | $200,000 | 4% |
| 625E10495 LIGHT POLE, LOW MAST, AS PER PLAN, ALM50 | 88 EACH | $3,300 | $4,000 | $3,500 | $3,300 | $2,955 | $4,500 | 4% |
| 625E14307 MEDIAN LIGHT POLE FOUNDATION, 10' DEEP, AS PER PLA | 72 EACH | $3,800 | $4,000 | $6,300 | $7,500 | $5,710 | $7,500 | 4% |
| 611E99101 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE B1, AS | 59 EACH | $4,300 | $5,000 | $5,700 | $6,500 | $4,595 | $6,500 | 4% |
| 630E72421 OVERHEAD SIGN SUPPORT, TYPE TC-15.116, DESIGN 2, A | 2 EACH | $125,500 | $120,325 | $130,000 | $112,835 | $119,725 | $119,725 | 4% |
| 809E24000 CONDUIT, MULTICELL, JACKED OR DRILLED, 4" | 3,780 FT | $64.00 | $60.00 | $68.00 | $64.00 | $95.00 | $45.00 | 3% |
| 622E10200 BARRIER TRANSITION | 19 EACH | $12,000 | $5,000 | $4,800 | $6,000 | $5,240 | $5,400 | 3% |
| 442E20001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 688 CY | $310 | $300 | $263 | $250 | $250 | $320 | 3% |
| 630E72411 OVERHEAD SIGN SUPPORT, TYPE TC-15.116, DESIGN 1, A | 2 EACH | $93,750 | $93,450 | $100,000 | $87,525 | $92,850 | $92,850 | 3% |
| 625E23200 NO. 4 AWG 2400 VOLT DISTRIBUTION CABLE | 61,187 FT | $3.00 | $4.00 | $3.00 | $3.00 | $3.00 | $3.70 | 3% |
| 442E20001 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 403 CY | $350 | $320 | $265 | $250 | $250 | $315 | 2% |
| 808E18700 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY | 108 SNMT | $1,105 | $430 | $900 | $715 | $695 | $850 | 2% |
| 304E20000 AGGREGATE BASE | 1,538 CY | $68.00 | $112 | $80.00 | $130 | $70.00 | $60.00 | 1% |
| 625E26273 LUMINAIRE, LOW MAST, SOLID STATE (LED), AS PER PLA | 88 EACH | $1,175 | $1,600 | $1,300 | $1,175 | $1,105 | $1,300 | 1% |
| $17.00 |
| $55.00 |
| $25.00 |
| 203E20000 EMBANKMENT | 294 CY | $20.00 | $11.00 | $25.00 | $35.00 | $140 | $20.00 |
| 204E10000 SUBGRADE COMPACTION | 2,119 SY | $0.56 | $3.00 | $2.00 | $3.00 | $9.00 | $3.00 |
| 209E15001 RESHAPING UNDER GUARDRAIL, AS PER PLAN | 0.88 STA | $750 | $440 | $1,500 | $400 | $2,500 | $500 |
| 606E15050 GUARDRAIL, TYPE MGS | 37.5 FT | $61.60 | $62.40 | $66.00 | $62.40 | $62.40 | $62.40 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) | 1 EACH | $3,975 | $3,980 | $4,200 | $3,980 | $3,980 | $3,980 |
| 622E10101 CONCRETE BARRIER, SINGLE SLOPE, TYPE B1, AS PER PL | 42 FT | $455 | $185 | $293 | $285 | $225 | $265 |
| 622E10141 CONCRETE BARRIER, SINGLE SLOPE, TYPE C1, AS PER PL | 365 FT | $185 | $135 | $148 | $140 | $190 | $280 |
| 622E10201 BARRIER TRANSITION, AS PER PLAN | 5 EACH | $9,000 | $5,000 | $5,350 | $6,350 | $4,000 | $5,300 |
| 622E25007 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 12 EACH | $3,100 | $2,750 | $4,700 | $2,700 | $3,300 | $3,000 |
| 622E25014 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 3 EACH | $4,200 | $3,700 | $5,800 | $3,300 | $3,350 | $4,400 |
| 622E25015 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 3 EACH | $4,000 | $3,500 | $5,800 | $2,800 | $4,525 | $2,800 |
| 622E90000 BARRIER, MISC.: CONCRETE BARRIER, TYPE B50 | 26 FT | $575 | $220 | $246 | $280 | $195 | $400 |
| 622E90000 BARRIER, MISC.: CONCRETE BARRIER, TYPE C50 | 9 FT | $625 | $240 | $424 | $320 | $300 | $450 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $200 | $250 | $100 | $200 | $200 | $200 |
| 659E00300 TOPSOIL | 90 CY | $50.00 | $60.00 | $72.00 | $50.00 | $19.35 | $60.00 |
| 659E10000 SEEDING AND MULCHING | 810 SY | $1.00 | $4.95 | $5.00 | $1.00 | $4.95 | $5.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 41 SY | $3.00 | $1.00 | $1.00 | $3.00 | $1.00 | $2.50 |
| 659E15000 INTER-SEEDING | 41 SY | $0.01 | $0.10 | $1.00 | $1.00 | $0.10 | $2.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.11 TON | $1,000 | $495 | $523 | $1,000 | $495 | $1,200 |
| 659E31000 LIME | 0.17 ACRE | $2.00 | $50.00 | $53.00 | $100 | $50.00 | $397 |
| 659E35000 WATER | 4.38 MGAL | $0.50 | $1.70 | $2.00 | $10.00 | $1.70 | $50.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E99111 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE C1, AS | 3 EACH | $4,700 | $6,600 | $7,500 | $6,500 | $5,500 | $7,400 |
| 611E99155 INLET RECONSTRUCTED TO GRADE, AS PER PLAN | 10 EACH | $3,300 | $2,200 | $2,400 | $3,000 | $3,850 | $2,800 |
| 611E99500 INLET, MISC.: INLET, NO. 3B50 | 5 EACH | $11,000 | $6,300 | $6,800 | $10,000 | $5,980 | $6,400 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 3,000 LB | $2.00 | $3.25 | $2.00 | $1.50 | $2.35 | $3.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 9,666 SY | $5.75 | $3.67 | $3.00 | $4.00 | $4.00 | $6.00 |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 1 | 16,301 SY | $4.45 | $3.00 | $3.00 | $4.00 | $4.00 | $6.00 |
| 305E13010 9" CONCRETE BASE, CLASS QC 1P | 186 SY | $131 | $102 | $123 | $160 | $75.00 | $140 |
| 407E20000 NON-TRACKING TACK COAT | 2,371 GAL | $2.25 | $3.00 | $3.00 | $2.50 | $2.50 | $3.00 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (21 CY | $242 | $480 | $770 | $725 | $725 | $500 |
| 441E50701 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (4 CY | $660 | $500 | $1,300 | $1,200 | $1,200 | $600 |
| 618E40600 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 6.59 MILE | $1,000 | $971 | $2,600 | $971 | $1,660 | $971 |
| 625E00450 CONNECTION, FUSED PULL APART | 88 EACH | $85.00 | $140 | $90.00 | $85.00 | $127 | $125 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 77 EACH | $85.00 | $120 | $90.00 | $85.00 | $125 | $100 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 100 EACH | $85.00 | $120 | $90.00 | $85.00 | $115 | $100 |
| 625E14306 MEDIAN LIGHT POLE FOUNDATION, 10' DEEP | 2 EACH | $3,950 | $6,000 | $6,200 | $8,200 | $6,735 | $7,500 |
| 625E14307 MEDIAN LIGHT POLE FOUNDATION, 10' DEEP, AS PER PLA | 1 EACH | $3,950 | $6,000 | $6,200 | $7,200 | $7,025 | $8,500 |
| 625E14600 LIGHT POLE FOUNDATION, MISC.: MEDIAN FOUNDATION ON | 9 EACH | $4,850 | $5,950 | $5,200 | $9,250 | $6,150 | $8,500 |
| 625E15201 LIGHT TOWER FOUNDATION, 36" X 25' DEEP, AS PER PLA | 1 EACH | $12,750 | $14,000 | $13,500 | $17,500 | $22,800 | $35,000 |
| 625E15301 LIGHT TOWER FOUNDATION, 36" X 30' DEEP, AS PER PLA | 1 EACH | $14,250 | $15,000 | $15,000 | $19,250 | $23,500 | $45,000 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 15,400 FT | $1.60 | $1.10 | $2.00 | $1.60 | $1.50 | $2.25 |
| 625E24320 1-1/2" DUCT CABLE WITH THREE NO. 4 AWG 2400 VOLT C | 50 FT | $18.00 | $20.00 | $19.00 | $18.00 | $20.00 | $200 |
| 625E29002 TRENCH, 24" DEEP | 160 FT | $16.00 | $12.50 | $17.00 | $16.00 | $7.00 | $25.00 |
| 625E29931 MEDIAN JUNCTION BOX, AS PER PLAN B | 18 EACH | $2,100 | $2,200 | $4,700 | $2,100 | $5,450 | $1,600 |
| 625E29931 MEDIAN JUNCTION BOX, AS PER PLAN C | 32 EACH | $1,550 | $1,300 | $4,300 | $1,550 | $6,750 | $1,600 |
| 625E30700 PULL BOX, 725.08, 18" | 2 EACH | $950 | $1,300 | $1,000 | $950 | $800 | $850 |
| 625E30711 PULL BOX, 725.08, 32", AS PER PLAN | 24 EACH | $2,900 | $2,000 | $3,000 | $2,900 | $2,250 | $2,100 |
| 625E32000 GROUND ROD | 87 EACH | $292 | $300 | $280 | $265 | $300 | $150 |
| 625E35021 RE-ERECT EXISTING LIGHT TOWER, AS PER PLAN | 2 EACH | $5,800 | $2,850 | $6,200 | $5,800 | $3,500 | $5,500 |
| 625E75400 LIGHT POLE REMOVED | 88 EACH | $260 | $585 | $275 | $260 | $245 | $325 |
| 625E75506 LUMINAIRE REMOVED | 176 EACH | $55.00 | $125 | $58.00 | $55.00 | $30.00 | $100 |
| 625E75800 DISCONNECT CIRCUIT | 1 EACH | $250 | $350 | $265 | $250 | $200 | $2,050 |
| 625E98200 LIGHTING, MISC.: LIGHT POLE IDENTIFIERS | 1 LS | $969 | $4,000 | $1,000 | $969 | $4,500 | $5,000 |
| 809E24500 CONDUIT, 4", MULTICELL, HDPE WITH 4 ? 1? INNERDUCT | 240 FT | $34.00 | $30.00 | $36.00 | $34.00 | $18.00 | $45.00 |
| 620E00500 DELINEATOR, POST GROUND MOUNTED, TYPE C | 1 EACH | $80.00 | $85.00 | $160 | $148 | $85.00 | $85.00 |
| 625E29931 MEDIAN JUNCTION BOX, AS PER PLAN A | 2 EACH | $1,550 | $2,000 | $1,700 | $1,550 | $5,875 | $1,600 |
| 626E00102 BARRIER REFLECTOR, TYPE 1, ONE WAY | 442 EACH | $9.10 | $6.50 | $9.00 | $8.00 | $8.00 | $8.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, ONE WAY | 2 EACH | $11.00 | $58.00 | $12.00 | $11.00 | $11.00 | $15.00 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 2 EACH | $175 | $185 | $200 | $335 | $185 | $185 |
| 630E79610 SIGN SUPPORT ASSEMBLY, BARRIER MOUNTED | 38 EACH | $395 | $395 | $420 | $295 | $395 | $395 |
| 630E80100 SIGN, FLAT SHEET | 180 SF | $19.50 | $17.50 | $19.00 | $12.25 | $17.50 | $17.50 |
| 630E84010 CONCRETE BARRIER MEDIAN OVERHEAD SIGN SUPPORT FOUN | 4 EACH | $11,200 | $15,210 | $15,000 | $11,100 | $18,500 | $11,300 |
| 630E84510 RIGID OVERHEAD SIGN SUPPORT FOUNDATION | 4 EACH | $9,800 | $9,180 | $9,800 | $9,755 | $9,180 | $9,180 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 16 EACH | $60.00 | $65.00 | $70.00 | $47.15 | $65.00 | $65.00 |
| 630E87100 REMOVAL OF OVERHEAD MOUNTED SIGN AND REERECTION | 18 EACH | $575 | $395 | $420 | $965 | $395 | $395 |
| 630E89802 REMOVAL OF OVERHEAD SIGN SUPPORT AND DISPOSAL, TYP | 4 EACH | $2,175 | $1,320 | $1,400 | $2,425 | $1,320 | $1,320 |
| 646E10010 EDGE LINE, 6" | 19.42 MILE | $3,575 | $2,750 | $3,000 | $2,750 | $2,750 | $2,750 |
| 646E10110 LANE LINE, 6" | 18.44 MILE | $2,340 | $1,800 | $1,900 | $1,800 | $1,800 | $1,800 |
| 646E10310 CHANNELIZING LINE, 12" | 8,482 FT | $3.51 | $2.70 | $3.00 | $2.70 | $2.70 | $2.70 |
| 646E10620 CHEVRON MARKING | 327 FT | $16.25 | $12.50 | $13.00 | $12.50 | $12.50 | $12.50 |
| 646E20504 DOTTED LINE, 6" | 5,885 FT | $2.99 | $2.30 | $3.00 | $2.30 | $2.30 | $2.30 |
| 646E20510 DOTTED LINE, 12" | 2,285 FT | $2.99 | $3.40 | $4.00 | $3.40 | $3.40 | $3.40 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 300 HOUR | $75.00 | $85.00 | $82.00 | $75.00 | $85.00 | $100 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $1,945 | $1,470 | $820 | $2,100 | $1,865 | $2,600 |
| 614E12484 WORK ZONE INCREASED PENALTIES SIGN | 20 EACH | $241 | $525 | $196 | $160 | $185 | $185 |
| 614E12800 WORK ZONE RAISED PAVEMENT MARKER | 1,613 EACH | $8.45 | $6.00 | $7.00 | $6.15 | $6.50 | $6.50 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 25 CY | $465 | $640 | $352 | $300 | $500 | $240 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE WAY | 957 EACH | $19.50 | $6.00 | $10.00 | $5.35 | $15.00 | $15.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 953 EACH | $20.80 | $13.00 | $14.00 | $13.80 | $16.00 | $16.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $600 | $580 | $1,200 | $815 | $1,050 | $1,200 |
| 614E20110 WORK ZONE LANE LINE, CLASS I, 6", 642 PAINT | 15.62 MILE | $780 | $600 | $635 | $600 | $600 | $600 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 16.99 MILE | $1,203 | $925 | $980 | $925 | $925 | $925 |
| 614E23210 WORK ZONE CHANNELIZING LINE, CLASS I, 12", 642 PAI | 15,994 FT | $0.78 | $0.60 | $1.00 | $0.60 | $0.60 | $0.60 |
| 614E24202 WORK ZONE DOTTED LINE, CLASS I, 6", 642 PAINT | 7,661 FT | $0.91 | $0.70 | $1.00 | $0.70 | $0.70 | $0.70 |
| 630E97800 SIGNING, MISC.: ADDITIONAL SIGNS, GROUND MOUNTED, | 300 SF | $52.00 | $25.00 | $42.00 | $18.25 | $40.00 | $40.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $80,000 | $40,000 | $45,000 | $50,500 | $20,000 | $75,000 |
| 108E10000 CPM PROGRESS SCHEDULE | 1 LS | $5,000 | $3,000 | $1,500 | $250 | $5,000 | $15,000 |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 6 MNTH | $2,000 | $2,200 | $5,000 | $2,500 | $2,500 | $3,000 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $25,000 | $45,000 | $22,000 | $10,000 | $45,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 622E10101 CONCRETE BARRIER, SINGLE SLOPE, TYPE B1, AS PER PL | 16,851 FT | $118 | $1.99M | 23% |
| 622E25006 CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE | 133 EACH | $4,200 | $559k | 7% |
| 625E40000 SPECIAL - MAINTAIN EXISTING LIGHTING | 1 LS | $464,500 | $465k | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $400,000 | $400k | 5% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 48,830 FT | $7.5 | $366k | 4% |
| 202E30701 CONCRETE BARRIER REMOVED, AS PER PLAN | 22,042 FT | $15 | $331k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $295,271 | $295k | 3% |
| 625E10495 LIGHT POLE, LOW MAST, AS PER PLAN, ALM50 | 88 EACH | $3,300 | $290k | 3% |
| 625E14307 MEDIAN LIGHT POLE FOUNDATION, 10' DEEP, AS PER PLA | 72 EACH | $3,800 | $274k | 3% |
| 611E99101 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE B1, AS | 59 EACH | $4,300 | $254k | 3% |