SUM-SR 93/SR 162-09.10/07.26
SUM County · est $2.6M
Bid dateThursday, March 17—
SUM County · est $2.6M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 43 more items below.
| Item | Quantity | R1Karvo Companies INC | R2Barbicas Construction Company INC | R3Shelly Company | R4Chagrin Valley Paving INC | R5Shelly & Sands INC | % of bid |
|---|---|---|---|---|---|---|---|
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (2906 CY | $166 | $200 | $145 | $175 | $225 | 21% |
| 424E10001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE A, AS P | 1,665 CY | $230 | $245 | $215 | $230 | $245 | 17% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 145 EACH | $1,340 | $1,200 | $1,450 | $1,600 | $2,500 | 9% |
| 254E01000 |
| Item | Quantity | R1Karvo Companies INC | R2Barbicas Construction Company INC | R3Shelly Company | R4Chagrin Valley Paving INC | R5Shelly & Sands INC |
|---|---|---|---|---|---|---|
| 203E10000 EXCAVATION (FOR PAVEMENT REPAIR) | 140 CY | $25.00 | $20.00 | $40.00 | $10.00 | $150 |
| 203E10000 EXCAVATION (FOR WALK OR CURB RAMP INSTALLATION) | 421 CY | $25.00 | $30.00 | $55.00 | $10.00 | $50.00 |
| 203E40000 BORROW | 6 CY | $100 | $50.00 | $60.00 | $100 | $180 |
| 608E10000 4" CONCRETE WALK | 567 SF | $8.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 83,679 SY |
| $2.20 |
| $4.00 |
| $2.00 |
| $5.00 |
| $3.20 |
| 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $150,000 | $100,000 | $385,000 | $195,000 | $299,371 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $125,000 | $150,000 | $100,000 | $101,530 | $100,000 | 5% |
| 255E10500 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 500 SY | $230 | $200 | $200 | $500 | $350 | 5% |
| 608E52000 CURB RAMP | 10,777 SF | $8.00 | $15.00 | $15.25 | $20.00 | $16.50 | 4% |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 80 EACH | $1,075 | $750 | $1,000 | $1,600 | $2,550 | 4% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 2,500 SY | $32.00 | $28.00 | $42.50 | $40.00 | $40.00 | 3% |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 90 EACH | $875 | $800 | $1,050 | $750 | $1,800 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 215 CY | $325 | $300 | $310 | $300 | $600 | 3% |
| 623E39501 MONUMENT BOX ADJUSTED TO GRADE, AS PER PLAN | 42 EACH | $1,125 | $900 | $1,450 | $1,200 | $2,000 | 2% |
| 202E30000 WALK REMOVED | 11,518 SF | $4.00 | $2.00 | $3.00 | $5.00 | $5.00 | 2% |
| 644E60000 GREEN COLORED PAVEMENT FOR BIKE LANES | 3,384 SF | $12.85 | $12.85 | $11.25 | $12.85 | $12.85 | 2% |
| 253E01000 PAVEMENT REPAIR | 300 SY | $100 | $80.00 | $80.00 | $100 | $120 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 10,880 GAL | $2.25 | $2.80 | $2.85 | $2.00 | $3.00 | 1% |
| 614E11111 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 350 HOUR | $65.00 | $65.00 | $65.00 | $80.00 | $70.00 | 1% |
| 611E98634 CATCH BASIN RECONSTRUCTED TO GRADE | 15 EACH | $1,275 | $1,050 | $1,400 | $2,200 | $2,800 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $18,000 | $20,000 | $28,500 | $25,000 | $18,000 | 1% |
| $10.00 |
| $7.50 |
| $10.00 |
| $7.00 |
| 608E53020 DETECTABLE WARNING | 24 SF | $18.00 | $75.00 | $75.00 | $100 | $40.00 |
| 625E31600 PULL BOX, MISC.: ADJUSTED TO GRADE | 3 EACH | $200 | $300 | $750 | $600 | $3,400 |
| 202E32000 CURB REMOVED | 166 FT | $30.00 | $12.00 | $15.00 | $12.00 | $20.00 |
| 659E10000 SEEDING AND MULCHING | 152 SY | $1.50 | $5.50 | $20.00 | $15.00 | $10.50 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 4 EACH | $300 | $500 | $1,400 | $1,600 | $1,550 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 600 LB | $1.75 | $2.00 | $3.00 | $4.00 | $5.00 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 4,800 FT | $2.50 | $3.00 | $4.00 | $5.00 | $6.00 |
| 304E20000 AGGREGATE BASE | 140 CY | $38.00 | $50.00 | $50.00 | $140 | $70.00 |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 18 FT | $55.00 | $50.00 | $65.00 | $75.00 | $52.00 |
| 609E26000 CURB, TYPE 6 | 166 FT | $22.00 | $40.00 | $40.00 | $60.00 | $53.00 |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 7 EACH | $200 | $350 | $860 | $750 | $400 |
| 644E00104 EDGE LINE, 6" | 3.67 MILE | $3,000 | $3,000 | $3,600 | $3,000 | $3,000 |
| 644E00204 LANE LINE, 6" | 0.66 MILE | $1,500 | $1,500 | $1,600 | $1,500 | $1,500 |
| 644E00300 CENTER LINE | 3.58 MILE | $3,950 | $3,950 | $3,300 | $3,950 | $3,950 |
| 644E00400 CHANNELIZING LINE, 8" | 10,538 FT | $1.45 | $1.45 | $0.95 | $1.45 | $1.45 |
| 644E00500 STOP LINE | 364 FT | $6.00 | $6.00 | $5.50 | $6.00 | $6.00 |
| 644E00620 CROSSWALK LINE, 12" | 2,365 FT | $3.15 | $3.15 | $2.75 | $3.15 | $3.15 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 268 FT | $5.50 | $5.50 | $5.50 | $5.50 | $5.50 |
| 644E00900 ISLAND MARKING | 339 SF | $5.00 | $5.00 | $3.00 | $5.00 | $5.00 |
| 644E01110 SCHOOL SYMBOL MARKING, 96" | 2 EACH | $300 | $300 | $750 | $300 | $300 |
| 644E01300 LANE ARROW | 112 EACH | $75.00 | $1.00 | $85.00 | $75.00 | $75.00 |
| 644E01510 DOTTED LINE, 6" | 590 FT | $1.00 | $1.00 | $2.50 | $1.00 | $1.00 |
| 644E01630 BIKE LANE SYMBOL MARKING | 49 EACH | $250 | $250 | $295 | $250 | $250 |
| 644E00404 CHANNELIZING LINE, 12" | 34 FT | $2.50 | $2.50 | $5.00 | $2.50 | $2.50 |
| 614E12460 WORK ZONE MARKING SIGN | 40 EACH | $50.00 | $75.00 | $50.00 | $50.00 | $50.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 20 CY | $300 | $200 | $225 | $300 | $325 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $400 | $1,200 | $920 | $600 | $975 |
| 614E20110 WORK ZONE LANE LINE, CLASS I, 6", 642 PAINT | 8.52 MILE | $585 | $585 | $400 | $585 | $585 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 0.66 MILE | $585 | $585 | $975 | $585 | $585 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 7.16 MILE | $1,000 | $1,000 | $900 | $1,000 | $1,000 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 3.58 MILE | $825 | $825 | $900 | $825 | $825 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 1.75 MILE | $500 | $500 | $750 | $500 | $500 |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 19,200 FT | $0.40 | $0.40 | $0.40 | $0.40 | $0.40 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 21,190 FT | $0.40 | $0.40 | $0.40 | $0.40 | $0.40 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 704 FT | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 409 FT | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 619E16010 FIELD OFFICE, TYPE B | 8 MNTH | $1,500 | $700 | $2,500 | $1,500 | $2,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,990 | $250 | $3,000 | $500 | $7,525 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (2906 CY | $166 | $482k | 19% |
| 424E10001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE A, AS P | 1,665 CY | $230 | $383k | 15% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 145 EACH | $1,340 | $194k | 8% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 2") | 83,679 SY | $2.2 | $184k | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $150,000 | $150k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $125,000 | $125k | 5% |
| 255E10500 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 500 SY | $230 | $115k | 5% |
| 608E52000 CURB RAMP | 10,777 SF | $8 | $86k | 3% |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 80 EACH | $1,075 | $86k | 3% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 2,500 SY | $32 | $80k | 3% |