COL-SR 170-11.42
COL County · est $1.0M
Bid dateThursday, June 16—
COL County · est $1.0M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 10 more items below.
| Item | Quantity | R1Shelly Company | R2Shelly & Sands INC | R3Barbicas Construction Company INC | R4Chagrin Valley Paving INC | % of bid |
|---|---|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 1,640 CY | $215 | $258 | $275 | $250 | 34% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (1211 CY | $195 | $232 | $275 | $250 | 23% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $95,000 | $75,521 | $55,000 | $150,000 | 9% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1-1/4") | 32,788 SY | $1.75 | $2.85 | $5.00 | $5.00 | 5% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 125 CY | $415 | $349 | $280 | $425 | 5% |
| 253E02000 PAVEMENT REPAIR | 100 CY | $450 | $389 | $280 |
| Item | Quantity | R1Shelly Company | R2Shelly & Sands INC | R3Barbicas Construction Company INC | R4Chagrin Valley Paving INC |
|---|---|---|---|---|---|
| 209E60500 LINEAR GRADING | 1.02 MILE | $3,485 | $5,000 | $800 | $750 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 100 FT | $5.00 | $26.00 | $12.00 | $25.00 |
| 617E20000 SHOULDER PREPARATION | 6,219 SY | $0.50 | $1.00 | $2.30 | $0.25 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $500 |
| 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $50,000 | $25,000 | $125,000 | 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (2-1/4") | 14,189 SY | $2.25 | $4.35 | $5.50 | $7.00 | 3% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 389 CY | $60.00 | $102 | $100 | $125 | 2% |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $620 | $650 | $650 | $500 | 2% |
| 407E20000 NON-TRACKING TACK COAT | 6,447 GAL | $2.50 | $3.50 | $4.00 | $2.00 | 2% |
| 646E10010 EDGE LINE, 6" | 5.7 MILE | $2,500 | $2,500 | $2,501 | $4,235 | 1% |
| 621E00100 RPM | 377 EACH | $36.00 | $36.00 | $44.30 | $36.00 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 8.55 MILE | $1,225 | $900 | $1,152 | $1,225 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 2,488 GAL | $4.00 | $3.75 | $6.50 | $2.00 | 1% |
| 646E10200 CENTER LINE | 2.85 MILE | $3,160 | $3,162 | $3,162 | $6,997 | 1% |
| 209E72050 PREPARING SUBGRADE FOR SHOULDER PAVING | 5.3 MILE | $1,350 | $1,800 | $900 | $750 | 1% |
| 614E21500 WORK ZONE CENTER LINE, CLASS II, 642 PAINT | 8.55 MILE | $730 | $1,050 | $707 | $1,225 | 1% |
| 202E23500 WEARING COURSE REMOVED | 593 SY | $9.00 | $12.00 | $10.00 | $5.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $4,000 | $7,000 | $15,000 | $15,000 | 0% |
| 377 EACH |
| $5.00 |
| $7.00 |
| $10.80 |
| $1.00 |
| 646E10400 STOP LINE | 18 FT | $15.00 | $13.18 | $13.20 | $16.50 |
| 646E20000 RAILROAD SYMBOL MARKING | 2 EACH | $435 | $433 | $433 | $810 |
| 614E12460 WORK ZONE MARKING SIGN | 10 EACH | $150 | $150 | $111 | $150 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 54 FT | $14.00 | $14.00 | $4.30 | $14.00 |
| 100E00300 PREMIUM ON RAILROADS' PROTECTIVE PUBLIC LIABILITY | 1 LS | $2,500 | $6,000 | $5,000 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 1,640 CY | $215 | $353k | 33% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (1211 CY | $195 | $236k | 22% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $95,000 | $95k | 9% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1-1/4") | 32,788 SY | $1.75 | $57k | 5% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 125 CY | $415 | $52k | 5% |
| 253E02000 PAVEMENT REPAIR | 100 CY | $450 | $45k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 4% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (2-1/4") | 14,189 SY | $2.25 | $32k | 3% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 389 CY | $60 | $23k | 2% |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $620 | $17k | 2% |