HIG-TR 239-00.88
HIG County · est $0.8M
Bid dateThursday, November 17—
HIG County · est $0.8M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 38 more items below.
| Item | Quantity | R1Coopers Excavating LLC | R2D G M INC | R3Heavy Highway Construction Company | R4LLC George J Igel & CO INC | R5Sunesis Construction CO | R6Allard Excavation LLC | R7Axis Civil Construction LLC | R8Complete General Construction Company | R9Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 515E12090 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 6 EACH | $33,000 | $35,750 | $30,500 | $34,000 | $36,725 | $43,000 | $33,000 | $34,000 | $42,000 | 31% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 93 CY |
| Item | Quantity | R1Coopers Excavating LLC | R2D G M INC | R3Heavy Highway Construction Company | R4LLC George J Igel & CO INC | R5Sunesis Construction CO | R6Allard Excavation LLC | R7Axis Civil Construction LLC | R8Complete General Construction Company | R9Alan Stone CO INC |
|---|---|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $11,000 | $5,000 | $2,000 | $1,468 | $14,700 | $3,500 | $5,000 | $12,000 |
| 202E23000 PAVEMENT REMOVED | 557 SY | $10.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $450 |
| $625 |
| $500 |
| $740 |
| $900 |
| $615 |
| $840 |
| $1,100 |
| $940 |
| 6% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 50 CY | $825 | $1,200 | $1,100 | $1,250 | $1,324 | $1,251 | $1,250 | $1,125 | $1,950 | 6% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 86 CY | $468 | $325 | $298 | $298 | $300 | $315 | $350 | $298 | $300 | 6% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 22,870 LB | $1.75 | $1.00 | $2.00 | $1.75 | $1.77 | $3.00 | $1.82 | $1.75 | $1.50 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $20,000 | $22,401 | $20,000 | $35,074 | $55,000 | $30,000 | $20,000 | $47,000 | 6% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 182 FT | $193 | $200 | $200 | $200 | $211 | $193 | $210 | $215 | $205 | 5% |
| 524E94704 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK | 63 FT | $500 | $575 | $905 | $735 | $1,002 | $566 | $1,390 | $750 | $600 | 5% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $30,000 | $20,000 | $11,000 | $5,000 | $0.01 | $20,000 | $5,500 | $9,000 | $10,000 | 5% |
| 202E11002 STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $25,000 | $35,000 | $50,000 | $74,000 | $32,041 | $25,500 | $32,000 | $40,000 | $57,000 | 4% |
| 203E20000 EMBANKMENT | 671 CY | $35.00 | $25.00 | $27.00 | $25.00 | $9.92 | $12.00 | $26.00 | $21.00 | $15.00 | 4% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 34 CY | $480 | $545 | $350 | $350 | $353 | $535 | $480 | $350 | $355 | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $15,000 | $3,000 | $6,000 | $20,000 | $14,007 | $8,000 | $25,000 | $30,000 | $8,000 | 2% |
| 846E00110 POLYMER MODIFIED ASPHALT EXPANSION JOINT SYSTEM | 20 CF | $745 | $850 | $750 | $750 | $751 | $745 | $650 | $745 | $1,000 | 2% |
| 203E10000 EXCAVATION | 540 CY | $20.00 | $10.00 | $18.00 | $20.00 | $42.03 | $13.00 | $26.00 | $30.00 | $20.00 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $8,000 | $2,500 | $3,000 | $4,537 | $6,200 | $7,000 | $2,500 | $5,500 | 2% |
| 304E20000 AGGREGATE BASE | 133 CY | $75.00 | $60.00 | $65.00 | $120 | $63.37 | $62.00 | $100 | $75.00 | $85.00 | 2% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 121 CY | $75.00 | $70.00 | $125 | $85.00 | $106 | $77.00 | $95.00 | $115 | $150 | 1% |
| 606E32160 BRIDGE TERMINAL ASSEMBLY, TYPE TST | 4 EACH | $2,020 | $2,100 | $2,550 | $2,020 | $2,369 | $2,020 | $2,350 | $2,020 | $2,550 | 1% |
| 832E30000 EROSION CONTROL | 7,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| $4.00 |
| $11.00 |
| $13.00 |
| $9.77 |
| $5.62 |
| $12.00 |
| $10.00 |
| $16.16 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 15 FT | $5.00 | $20.00 | $100 | $15.00 | $52.50 | $8.60 | $40.00 | $75.00 | $50.00 |
| 204E10000 SUBGRADE COMPACTION | 871 SY | $2.00 | $4.00 | $2.00 | $7.00 | $2.39 | $4.25 | $3.00 | $7.00 | $4.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 100 FT | $48.24 | $55.00 | $21.50 | $48.24 | $44.36 | $48.24 | $44.00 | $48.24 | $22.00 |
| 606E25550 ANCHOR ASSEMBLY, MGS TYPE A | 3 EACH | $1,300 | $1,350 | $1,600 | $1,300 | $2,672 | $1,300 | $2,650 | $1,300 | $1,800 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,150 | $1,200 | $1,250 | $1,150 | $1,915 | $1,150 | $1,900 | $1,150 | $1,300 |
| 623E40500 REFERENCE MONUMENT, TYPE A | 4 EACH | $750 | $350 | $350 | $1,000 | $812 | $495 | $1,000 | $1,000 | $1,500 |
| 659E00300 TOPSOIL | 146 CY | $20.00 | $15.00 | $50.00 | $20.00 | $14.31 | $30.00 | $62.00 | $20.00 | $25.00 |
| 659E10000 SEEDING AND MULCHING | 1,317 SY | $3.00 | $2.50 | $3.00 | $5.00 | $2.69 | $2.00 | $3.00 | $3.00 | $3.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 66 SY | $3.00 | $0.05 | $3.00 | $3.00 | $0.88 | $0.05 | $3.00 | $3.00 | $5.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.18 TON | $1,400 | $1,500 | $1,400 | $1,400 | $918 | $1,500 | $1,400 | $1,400 | $1,000 |
| 659E31000 LIME | 0.27 ACRE | $80.00 | $100 | $80.00 | $80.00 | $157 | $1,500 | $80.00 | $80.00 | $800 |
| 659E35000 WATER | 7 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.01 | $1.00 | $1.00 | $1.00 | $0.01 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,455 | $2,000 | $2,500 | $1,455 | $1,467 | $1,850 | $2,500 | $1,455 | $3,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $2,190 | $4,000 | $7,050 | $3,000 | $1,129 | $9,100 | $7,400 | $1,200 | $9,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $5,281 | $5,500 | $6,000 | $4,500 | $5,325 | $6,700 | $6,500 | $6,000 | $7,000 |
| 611E00100 4" CONDUIT, TYPE B | 25 FT | $5.00 | $6.00 | $10.00 | $10.00 | $19.62 | $18.35 | $20.00 | $4.00 | $27.00 |
| 611E00900 6" CONDUIT, TYPE B | 25 FT | $7.00 | $8.00 | $14.00 | $15.00 | $22.61 | $19.60 | $20.00 | $6.00 | $28.00 |
| 611E06400 15" CONDUIT, TYPE D | 39 FT | $30.00 | $60.00 | $20.00 | $75.00 | $50.64 | $75.50 | $70.00 | $150 | $70.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5") | 66 SY | $29.50 | $100 | $200 | $35.00 | $237 | $98.75 | $60.00 | $235 | $60.00 |
| 407E10000 TACK COAT | 76 GAL | $18.00 | $2.25 | $15.00 | $15.00 | $15.12 | $2.25 | $4.00 | $15.00 | $20.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $6,020 | $7,500 | $5,000 | $10,000 | $7,289 | $6,020 | $6,020 | $7,230 | $8,000 |
| 616E10000 WATER | 2 MGAL | $1.00 | $1.00 | $1.00 | $28.00 | $37.61 | $1.00 | $1.00 | $80.00 | $1.00 |
| 202E23500 WEARING COURSE REMOVED | 139 SY | $50.00 | $4.00 | $21.00 | $9.00 | $4.97 | $5.65 | $10.00 | $45.00 | $3.19 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $1.00 | $6,000 | $10,000 | $25,000 | $10,659 | $6,700 | $15,000 | $45,000 | $4,500 |
| 503E31100 ROCK EXCAVATION | 7 CY | $75.00 | $100 | $150 | $234 | $118 | $60.00 | $150 | $60.00 | $400 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 145 SY | $35.00 | $35.00 | $20.00 | $32.00 | $28.96 | $29.28 | $27.00 | $27.00 | $35.00 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 35 SF | $5.00 | $25.00 | $5.00 | $9.00 | $5.38 | $6.50 | $9.00 | $15.00 | $4.00 |
| 516E14020 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 77 FT | $36.50 | $45.00 | $22.00 | $45.00 | $53.66 | $32.00 | $35.00 | $45.00 | $45.00 |
| 516E41100 1/8" PREFORMED BEARING PAD | 12 EACH | $29.50 | $40.00 | $25.00 | $80.00 | $63.23 | $69.00 | $30.00 | $30.00 | $50.00 |
| 516E43100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 24 EACH | $182 | $250 | $230 | $250 | $257 | $318 | $290 | $207 | $300 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 61 CY | $85.00 | $80.00 | $100 | $110 | $103 | $90.85 | $90.00 | $100 | $85.00 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 218 FT | $15.00 | $20.00 | $12.00 | $15.00 | $25.89 | $13.50 | $18.00 | $14.00 | $31.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 96 FT | $5.00 | $20.00 | $8.00 | $25.00 | $5.87 | $7.60 | $12.00 | $10.00 | $7.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 59 FT | $5.00 | $20.00 | $8.00 | $20.00 | $14.56 | $7.90 | $12.00 | $20.00 | $7.50 |
| 619E16000 FIELD OFFICE, TYPE A | 4 MNTH | $100 | $750 | $1,200 | $1,400 | $1,523 | $2,000 | $1,500 | $1,000 | $1,200 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $5,000 | $5,000 | $5,001 | $6,500 | $5,041 | $8,100 | $7,500 | $3,000 | $10,009 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12090 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 6 EACH | $33,000 | $198k | 27% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 93 CY | $450 | $42k | 6% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 50 CY | $825 | $41k | 6% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 86 CY | $467.5 | $40k | 5% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 22,870 LB | $1.75 | $40k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 5% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 182 FT | $193 | $35k | 5% |
| 524E94704 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK | 63 FT | $500 | $32k | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $30,000 | $30k | 4% |
| 202E11002 STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $25,000 | $25k | 3% |