POR-SR 14-06.43
POR County · est $1.3M
Bid dateThursday, January 26—
POR County · est $1.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 87 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Eclipse CO LLC | R3Karvo Companies INC | R4Chagrin Valley Paving INC | R5Perk Company INC | % of bid |
|---|---|---|---|---|---|---|---|
| 441E70101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), AS | 943 CY | $235 | $200 | $210 | $240 | $200 | 21% |
| 441E70200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (914 CY | $200 | $180 | $189 | $210 | $180 | 17% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 814 CY | $176 | $180 | $190 | $200 | $180 | 13% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=3.0") | 19,235 SY | $5.00 | $2.00 | $2.75 | $5.00 | $2.00 | 9% |
| 203E10000 EXCAVATION | 2,839 CY | $18.00 | $40.00 | $28.00 | $34.11 | $23.25 | 5% |
| 304E20000 |
| Item | Quantity | R1Shelly & Sands INC | R2Eclipse CO LLC | R3Karvo Companies INC | R4Chagrin Valley Paving INC | R5Perk Company INC |
|---|---|---|---|---|---|---|
| 202E23500 WEARING COURSE REMOVED | 2 SY | $190 | $260 | $175 | $250 | $250 |
| 202E32600 GUTTER REMOVED | 407 FT | $5.00 | $11.00 | $16.50 | $38.40 | $25.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 244 FT | $28.00 | $25.00 | $41.00 | $24.57 | $25.00 |
| 202E58100 CATCH BASIN REMOVED | 2 EACH | $931 | $549 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 600 CY |
| $78.00 |
| $111 |
| $89.00 |
| $100 |
| $70.00 |
| 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $55,056 | $50,000 | $90,000 | $156,800 | 4% |
| 690E98300 SPECIAL - SQUARE YARD PAVEMENT OVERLAY FABRIC COMP | 1,276 SY | $26.00 | $25.00 | $24.45 | $30.00 | $24.50 | 3% |
| 605E14020 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 2,127 FT | $14.00 | $10.00 | $26.00 | $16.78 | $23.00 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,000 | $95,000 | $107,000 | $175,000 | $176,525 | 3% |
| 832E30000 EROSION CONTROL | 26,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 203E20000 EMBANKMENT | 681 CY | $32.00 | $23.00 | $30.00 | $20.55 | $9.50 | 2% |
| 202E23000 PAVEMENT REMOVED | 1,607 SY | $12.00 | $11.00 | $31.00 | $28.11 | $46.25 | 2% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $3,200 | $684 | $2,300 | $1,500 | $2,100 | 2% |
| 646E10200 CENTER LINE | 4.03 MILE | $4,700 | $6,172 | $6,500 | $6,500 | $4,500 | 2% |
| 659E00300 TOPSOIL | 1,101 CY | $17.00 | $53.00 | $25.00 | $25.00 | $50.00 | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 189 CY | $99.00 | $65.00 | $90.00 | $90.00 | $65.00 | 2% |
| 204E10000 SUBGRADE COMPACTION | 3,584 SY | $5.00 | $1.00 | $0.75 | $1.07 | $1.60 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $16,000 | $13,000 | $47,000 | $8,000 | $64,200 | 2% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 200 SY | $77.00 | $85.00 | $80.00 | $125 | $85.00 | 1% |
| $210 |
| $369 |
| $850 |
| 202E98100 REMOVAL MISC.: INSPECTION WELL | 1 EACH | $305 | $222 | $195 | $476 | $425 |
| 202E98200 REMOVAL MISC.: CONDUIT | 5 FT | $61.00 | $27.00 | $6.00 | $94.53 | $25.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 50 CY | $15.00 | $25.00 | $60.00 | $14.86 | $82.00 |
| 203E35110 GRANULAR MATERIAL, TYPE B | 45 CY | $106 | $100 | $67.00 | $81.77 | $130 |
| 204E13000 EXCAVATION OF SUBGRADE | 45 CY | $32.00 | $78.00 | $25.00 | $64.71 | $87.50 |
| 204E45000 PROOF ROLLING | 3 HOUR | $228 | $326 | $300 | $287 | $375 |
| 204E50000 GEOTEXTILE FABRIC | 134 SY | $4.00 | $1.00 | $5.00 | $2.26 | $9.30 |
| 209E60200 LINEAR GRADING | 54 STA | $179 | $394 | $270 | $50.00 | $260 |
| 209E72000 PREPARING SUBGRADE FOR SHOULDER PAVING | 46 STA | $268 | $104 | $280 | $50.00 | $100 |
| 623E39500 MONUMENT ASSEMBLY ADJUSTED TO GRADE | 1 EACH | $1,230 | $2,241 | $1,500 | $1,500 | $2,550 |
| 690E98400 SPECIAL - SURVEY CONTROL VERIFICATION | 1 LS | $2,541 | $4,141 | $1,480 | $8,000 | $1,500 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 4 SY | $242 | $101 | $275 | $319 | $200 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 5 CY | $276 | $232 | $180 | $572 | $450 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 1 CY | $582 | $619 | $180 | $600 | $450 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $105 | $26.00 | $200 | $200 | $750 |
| 659E10000 SEEDING AND MULCHING | 11,414 SY | $1.00 | $0.93 | $0.83 | $0.83 | $1.50 |
| 659E14000 REPAIR SEEDING AND MULCHING | 496 SY | $1.00 | $1.00 | $1.00 | $1.00 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 1.54 TON | $954 | $312 | $1,200 | $1,200 | $1,000 |
| 659E31000 LIME | 2.36 ACRE | $164 | $26.00 | $1.00 | $1.00 | $1,000 |
| 659E35000 WATER | 35.1 MGAL | $1.00 | $0.10 | $1.00 | $1.00 | $25.00 |
| 670E00700 DITCH EROSION PROTECTION | 232 SY | $2.00 | $1.00 | $2.50 | $6.77 | $5.75 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,580 | $4,800 | $1,475 | $5,000 | $2,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $6,505 | $9,600 | $645 | $9,000 | $3,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $9,700 | $9,070 | $1,200 | $20,000 | $15,350 |
| 602E20000 CONCRETE MASONRY | 3 CY | $1,050 | $1,452 | $1,250 | $2,868 | $1,675 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 20 FT | $43.00 | $14.00 | $30.00 | $22.22 | $18.00 |
| 605E13410 6" UNCLASSIFIED PIPE UNDERDRAINS WITH GEOTEXTILE F | 98 FT | $27.00 | $14.00 | $40.00 | $22.28 | $18.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 47 FT | $37.00 | $26.00 | $17.00 | $24.31 | $23.00 |
| 611E00900 6" CONDUIT, TYPE B | 20 FT | $34.00 | $69.00 | $29.00 | $24.41 | $68.00 |
| 611E01400 6" CONDUIT, TYPE E | 20 FT | $34.00 | $58.00 | $11.00 | $24.41 | $68.00 |
| 611E01500 6" CONDUIT, TYPE F | 40 FT | $34.00 | $58.00 | $15.00 | $24.30 | $68.00 |
| 611E04400 12" CONDUIT, TYPE B | 134 FT | $82.00 | $97.00 | $88.00 | $138 | $98.00 |
| 611E04400 12" CONDUIT, TYPE B, 706.02 | 39 FT | $83.00 | $139 | $108 | $141 | $118 |
| 611E04900 12" CONDUIT, TYPE D | 43 FT | $82.00 | $97.00 | $83.00 | $109 | $76.00 |
| 611E04900 12" CONDUIT, TYPE D, 706.02 | 91 FT | $78.00 | $113 | $100 | $119 | $95.00 |
| 611E05900 15" CONDUIT, TYPE B, 706.02 | 5 FT | $319 | $447 | $600 | $315 | $185 |
| 611E05900 15" CONDUIT, TYPE B, 707.01 | 5 FT | $326 | $482 | $700 | $315 | $118 |
| 611E97400 CONDUIT, MISC.: TYPE B FOR DRAINAGE DISCHARGE CONT | 5 FT | $117 | $91.00 | $47.00 | $38.65 | $98.00 |
| 611E97400 CONDUIT, MISC.: TYPE C FOR DRAINAGE DISCHARGE CONT | 5 FT | $117 | $83.00 | $35.00 | $38.65 | $98.00 |
| 611E97400 CONDUIT, MISC.: TYPE E FOR DRAINAGE DISCHARGE CONT | 5 FT | $117 | $71.00 | $35.00 | $38.65 | $98.00 |
| 611E97400 CONDUIT, MISC.: TYPE F FOR DRAINAGE DISCHARGE CONT | 5 FT | $117 | $71.00 | $20.00 | $38.65 | $98.00 |
| 611E98470 CATCH BASIN, NO. 2-2B | 3 EACH | $3,032 | $4,638 | $1,700 | $2,555 | $4,275 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 2 EACH | $523 | $602 | $420 | $254 | $1,500 |
| 611E99720 INSPECTION WELL | 1 EACH | $746 | $1,205 | $400 | $1,429 | $2,060 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 2,459 FT | $3.00 | $5.00 | $3.75 | $6.25 | $3.00 |
| 407E20000 NON-TRACKING TACK COAT | 3,588 GAL | $3.00 | $3.00 | $3.00 | $2.00 | $3.00 |
| 408E10001 PRIME COAT, AS PER PLAN @ 0.40 GAL/SY | 1,355 GAL | $4.00 | $3.00 | $5.50 | $2.00 | $3.00 |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $1,000 | $675 | $450 | $1,500 | $675 |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 6,694 FT | $0.35 | $0.26 | $0.25 | $0.25 | $2.00 |
| 618E43000 RUMBLE STRIPES, CENTER LINE (ASPHALT CONCRETE) | 3.39 MILE | $1,500 | $1,400 | $1,400 | $1,400 | $1,000 |
| 874E20000 LONGITUDINAL JOINT PREPARATION | 1,796 FT | $2.00 | $4.00 | $4.00 | $3.00 | $4.00 |
| 621E00100 RPM | 159 EACH | $37.00 | $45.90 | $48.00 | $48.00 | $56.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 116 EACH | $9.00 | $1.00 | $8.00 | $1.00 | $25.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 212 FT | $17.00 | $16.00 | $14.05 | $14.05 | $15.00 |
| 630E80100 SIGN, FLAT SHEET | 33 SF | $34.00 | $24.00 | $28.00 | $28.00 | $18.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 3 EACH | $27.00 | $10.00 | $70.45 | $70.45 | $25.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 16 EACH | $91.00 | $68.00 | $85.00 | $85.00 | $85.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 15 EACH | $32.00 | $16.00 | $55.95 | $55.95 | $35.00 |
| 646E10000 EDGE LINE, 4" | 1.4 MILE | $3,200 | $3,983 | $4,400 | $4,400 | $2,600 |
| 646E10100 LANE LINE, 4" | 0.45 MILE | $3,100 | $4,077 | $1,200 | $1,200 | $1,900 |
| 646E10300 CHANNELIZING LINE, 8" | 900 FT | $2.00 | $3.00 | $2.50 | $2.50 | $2.10 |
| 646E10400 STOP LINE | 90 FT | $12.00 | $15.00 | $13.00 | $13.00 | $15.00 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 185 FT | $11.00 | $14.00 | $9.50 | $9.50 | $10.00 |
| 646E20300 LANE ARROW | 17 EACH | $203 | $267 | $195 | $195 | $175 |
| 646E20350 LANE REDUCTION ARROW | 2 EACH | $375 | $492 | $380 | $350 | $285 |
| 646E20510 DOTTED LINE, 12" | 1,403 FT | $3.00 | $4.00 | $2.50 | $2.50 | $5.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $81.00 | $68.00 | $85.00 | $125 | $75.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 20 CY | $268 | $312 | $150 | $350 | $250 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 8 SNMT | $843 | $1,476 | $950 | $950 | $1,100 |
| 614E20000 WORK ZONE LANE LINE, CLASS I, 4" | 0.45 MILE | $856 | $1,125 | $350 | $350 | $1,100 |
| 614E20560 WORK ZONE LANE LINE, CLASS III, 6", 642 PAINT | 0.45 MILE | $856 | $1,125 | $235 | $235 | $1,100 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 4.91 MILE | $1,257 | $1,652 | $2,790 | $2,790 | $1,350 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 4.03 MILE | $990 | $1,301 | $1,240 | $1,240 | $1,350 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 3.45 MILE | $942 | $1,237 | $1,395 | $1,395 | $700 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 1.4 MILE | $845 | $1,111 | $930 | $930 | $800 |
| 614E23000 WORK ZONE CHANNELIZING LINE, CLASS I, 8" | 1,243 FT | $0.75 | $1.00 | $0.80 | $0.80 | $1.00 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 900 FT | $0.65 | $1.00 | $0.60 | $0.60 | $1.00 |
| 614E26000 WORK ZONE STOP LINE, CLASS I | 90 FT | $3.00 | $4.00 | $2.80 | $2.80 | $4.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 90 FT | $3.00 | $4.00 | $3.10 | $3.10 | $4.00 |
| 614E30000 WORK ZONE ARROW, CLASS I | 2 EACH | $64.00 | $84.00 | $65.00 | $65.00 | $65.00 |
| 614E32700 WORK ZONE ISLAND MARKING, CLASS I | 40 SF | $3.00 | $4.00 | $2.50 | $2.50 | $2.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,600 | $18,000 | $15,000 | $15,000 | $15,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $14,000 | $18,000 | $19,700 | $10,000 | $35,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E70101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), AS | 943 CY | $235 | $222k | 17% |
| 441E70200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (914 CY | $200 | $183k | 14% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 814 CY | $176 | $143k | 11% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T=3.0") | 19,235 SY | $5 | $96k | 7% |
| 203E10000 EXCAVATION | 2,839 CY | $18 | $51k | 4% |
| 304E20000 AGGREGATE BASE | 600 CY | $78 | $47k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| 690E98300 SPECIAL - SQUARE YARD PAVEMENT OVERLAY FABRIC COMP | 1,276 SY | $26 | $33k | 3% |
| 605E14020 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 2,127 FT | $14 | $30k | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $27,000 | $27k | 2% |