MEG-CR 27-03.969
MEG County · est $0.5M
Bid dateThursday, February 23—
MEG County · est $0.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 22 more items below.
| Item | Quantity | R1Axis Civil Construction LLC | R2R C Construction Company And Son INC | R3D G M INC | R4Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|---|
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 6 EACH | $16,000 | $18,000 | $17,750 | $22,000 | 24% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 37 CY | $1,200 | $750 | $2,000 | $1,500 | 11% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 45 CY | $690 | $550 | $600 | $781 | 8% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 85 CY | $340 | $300 | $335 | $350 | 7% |
| 517E72300 RAILING (DEEP BEAM RAIL WITH STEEL TUBULAR BACKUP | 134 FT | $179 | $156 | $185 | $189 | 6% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 9,206 LB | $2.40 | $3.00 | $2.00 |
| Item | Quantity | R1Axis Civil Construction LLC | R2R C Construction Company And Son INC | R3D G M INC | R4Alan Stone CO INC |
|---|---|---|---|---|---|
| 203E10000 EXCAVATION | 165 CY | $25.00 | $10.00 | $25.00 | $32.00 |
| 203E20000 EMBANKMENT | 64 CY | $25.00 | $10.00 | $25.00 | $55.00 |
| 606E13001 GUARDRAIL, TYPE 5, AS PER PLAN | 100 FT | $24.00 | $35.00 | $25.00 | $42.00 |
| 606E20000 FLARED END SECTION | 1 EACH | $50.00 | $35.00 | $75.00 | $42.00 |
| 606E25001 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $3.00 |
| 6% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $12,000 | $6,000 | $25,000 | 5% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $16,500 | $10,000 | $31,500 | $30,000 | 4% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $16,000 | $35,000 | $5,000 | $13,000 | 4% |
| 507E00100 STEEL PILES HP10X42, FURNISHED | 350 FT | $39.00 | $45.00 | $79.00 | $44.00 | 3% |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $13,500 | $4,500 | $2,500 | $4,100 | 3% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 28 CY | $400 | $350 | $660 | $397 | 3% |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 95 CY | $110 | $120 | $90.00 | $104 | 3% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $10,000 | $25,000 | $10,000 | $6,100 | 3% |
| 606E35141 BRIDGE TERMINAL ASSEMBLY, TYPE 4, AS PER PLAN | 4 EACH | $2,200 | $680 | $2,300 | $825 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,500 | $12,500 | $3,500 | $11,000 | 2% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 77 CY | $80.00 | $100 | $90.00 | $125 | 2% |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 41 CY | $150 | $150 | $225 | $211 | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $5,000 | $1,000 | $11,000 | $5,300 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $20,000 | $10,000 | $5,800 | 1% |
| 3 EACH |
| $1,375 |
| $1,270 |
| $1,400 |
| $1,500 |
| 659E10000 SEEDING AND MULCHING | 891 SY | $3.64 | $5.00 | $4.00 | $6.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.08 TON | $1,400 | $1,950 | $1,000 | $25,000 |
| 659E31000 LIME | 0.18 ACRE | $100 | $1,000 | $100 | $11,000 |
| 659E35000 WATER | 7 MGAL | $1.00 | $1.00 | $1.00 | $388 |
| 832E30000 EROSION CONTROL | 3,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 240 SY | $13.00 | $30.00 | $3.00 | $19.00 |
| 204E10000 SUBGRADE COMPACTION | 507 SY | $3.00 | $2.00 | $5.00 | $10.00 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 24 FT | $15.00 | $50.00 | $15.00 | $114 |
| 407E10000 TACK COAT | 51 GAL | $4.00 | $25.00 | $10.00 | $52.00 |
| 507E00150 STEEL PILES HP10X42, DRIVEN | 310 FT | $14.00 | $25.00 | $10.00 | $56.00 |
| 507E00410 STEEL PILES, MISC.:PILE SPLICING | 4 EACH | $500 | $25.00 | $50.00 | $955 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 58 SY | $20.00 | $50.00 | $45.00 | $96.00 |
| 512E33000 TYPE 2 WATERPROOFING | 18 SY | $50.00 | $30.00 | $35.00 | $159 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 2.2 SF | $400 | $35.00 | $50.00 | $850 |
| 516E41100 1/8" PREFORMED BEARING PAD | 24 EACH | $45.00 | $10.00 | $15.00 | $132 |
| 516E43100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES ONLY ( | 24 EACH | $200 | $300 | $165 | $248 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 160 FT | $18.50 | $20.00 | $17.00 | $31.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12050 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 6 EACH | $16,000 | $96k | 22% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 37 CY | $1,200 | $44k | 10% |
| 511E45710 CLASS QC1 CONCRETE, ABUTMENT | 45 CY | $690 | $31k | 7% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 85 CY | $340 | $29k | 7% |
| 517E72300 RAILING (DEEP BEAM RAIL WITH STEEL TUBULAR BACKUP | 134 FT | $178.75 | $24k | 5% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 9,206 LB | $2.4 | $22k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 5% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $16,500 | $17k | 4% |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $16,000 | $16k | 4% |
| 507E00100 STEEL PILES HP10X42, FURNISHED | 350 FT | $39 | $14k | 3% |