PIK-SR 772-02.09
PIK County · est $0.5M
Bid dateThursday, March 30—
PIK County · est $0.5M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 41,299 GAL | $3 | $124k |
ODOT bid tab line items with each bidder’s unit price. Top 18items by winning bid’s extended amount.
| Item | Quantity | R1Sc Construction & Materials LLC | R2Allied Construction, LLC | R3Shelly Company | R4Strawser Construction INC | % of bid |
|---|---|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 41,299 GAL | $3.00 | $4.00 | $2.90 | $3.33 | 26% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 103,247 SY | $0.85 | $0.68 | $0.94 | $1.27 | 18% |
| 886E11000 FOG SEAL | 15,487 GAL | $3.25 | $2.75 | $3.05 | $4.00 | 10% |
| 642E30030 REMOVAL OF PAVEMENT MARKING | 21.06 MILE | $1,680 | $1,680 | $1,680 | $1,470 | 7% |
| 624E10000 MOBILIZATION | 1 LS | $35,000 | $35,000 | $20,000 | $68,800 | 7% |
| 621E00100 RPM | 1,156 EACH | $28.00 | $27.70 | $31.00 | $30.00 | 7% |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 21.06 MILE | $1,160 | $1,160 | $1,160 | $1,150 | 5% |
| 617E10100 COMPACTED AGGREGATE | 250 CY | $80.00 | $45.00 | $84.00 | $105 | 4% |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 42.12 MILE | $450 | $450 | $450 | $875 | 4% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1,156 EACH | $12.00 | $15.00 | $14.00 | $15.00 | 3% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 14.04 MILE | $850 | $850 | $850 | $775 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $10,000 | $25,000 | $50,000 | $50,375 | 2% |
| 642E00300 CENTER LINE, TYPE 1 | 7.02 MILE | $1,272 | $1,272 | $1,272 | $1,050 | 2% |
| 614E12460 WORK ZONE MARKING SIGN | 56 EACH | $125 | $125 | $92.00 | $100 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,500 | $4,000 | $2,750 | $4,500 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,000 | $1,500 | $1,500 | $2,500 | 0% |
| 642E00500 STOP LINE, TYPE 1 | 14 FT | $8.50 | $8.50 | $8.50 | $5.50 | 0% |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 14 FT | $8.00 | $8.00 | $8.00 | $70.00 | 0% |
| 26% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 103,247 SY | $0.85 | $88k | 18% |
| 886E11000 FOG SEAL | 15,487 GAL | $3.25 | $50k | 10% |
| 642E30030 REMOVAL OF PAVEMENT MARKING | 21.06 MILE | $1,680 | $35k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $35,000 | $35k | 7% |
| 621E00100 RPM | 1,156 EACH | $28 | $32k | 7% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 21.06 MILE | $1,160 | $24k | 5% |
| 617E10100 COMPACTED AGGREGATE | 250 CY | $80 | $20k | 4% |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 42.12 MILE | $450 | $19k | 4% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1,156 EACH | $12 | $14k | 3% |