CUY-US 6-23.30
CUY County · est $2.3M
Bid dateThursday, May 11—
CUY County · est $2.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 70 more items below.
| Item | Quantity | R1Perk Company INC | R2Karvo Companies INC | R3Ronyak Paving INC | % of bid |
|---|---|---|---|---|---|
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (2030 CY | $200 | $225 | $190 | 16% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 1,450 CY | $260 | $275 | $235 | 15% |
| 255E10011 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 1,488 SY | $225 | $175 | $190 | 14% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $202,323 | $150,000 | $650,000 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $180,400 | $300,600 | $600,000 | 7% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 3,871 SY | $40.00 | $80.00 | $60.00 | 6% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 73 EACH | $1,480 | $1,500 | $1,525 | 4% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (T | 41,764 SY | $2.50 | $4.00 | $5.00 | 4% |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 6,007 SF | $13.00 | $8.00 | $10.00 | 3% |
| 608E52001 CURB RAMP, AS PER PLAN | 2,704 SF | $27.50 | $15.00 | $20.00 | 3% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 50 EACH | $1,480 | $1,500 | $1,175 | 3% |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 300 CY | $200 | $275 | $85.00 | 2% |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 44 EACH | $1,160 | $1,250 | $925 | 2% |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 797 FT | $61.00 | $50.00 | $55.00 | 2% |
| 614E18000 MAINTAINING TRAFFIC, MISC.: MAINTAINING EXISTING T | 12 EACH | $3,900 | $9,575 | $2,500 | 2% |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 20,000 LB | $2.00 | $3.00 | $2.00 | 2% |
| 202E30001 WALK REMOVED, AS PER PLAN | 9,212 SF | $4.00 | $5.00 | $3.00 | 1% |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 2.63 MILE | $12,900 | $6,000 | $6,000 | 1% |
| 202E98200 REMOVAL MISC.: RAILING REMOVED AND REFURBISHED | 240 FT | $140 | $35.00 | $30.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $30,000 | $15,000 | $25,000 | 1% |
| Item | Quantity | R1Perk Company INC | R2Karvo Companies INC | R3Ronyak Paving INC |
|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $15,000 | $7,000 | $10,000 |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 127 SY | $40.00 | $60.00 | $20.00 |
| 202E32001 CURB REMOVED, AS PER PLAN | 1,288 FT | $3.00 | $25.00 | $12.00 |
| 202E38000 GUARDRAIL REMOVED | 13 FT | $30.00 | $60.00 | $30.00 |
| 202E58100 CATCH BASIN REMOVED | 3 EACH | $785 | $1,500 | $500 |
| 202E98100 REMOVAL MISC.: POST FOUNDATION REMOVED |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 EACH |
| $2,195 |
| $800 |
| $500 |
| 203E10000 EXCAVATION | 22 CY | $65.00 | $1,575 | $60.00 |
| 203E20000 EMBANKMENT | 51 CY | $73.00 | $200 | $60.00 |
| 608E53021 DETECTABLE WARNING, AS PER PLAN | 216 SF | $137 | $80.00 | $55.00 |
| 623E39501 MONUMENT BOX ADJUSTED TO GRADE, AS PER PLAN | 15 EACH | $1,160 | $1,500 | $850 |
| 623E40001 MONUMENT ASSEMBLY REMOVED AND RESET, AS PER PLAN | 4 EACH | $1,350 | $1,500 | $1,050 |
| 623E40900 MONUMENT, MISC.: MONUMENT REFERENCING | 14 EACH | $125 | $233 | $233 |
| 690E98000 SPECIAL - SPECIAL: ADJUST STREET CASTINGS TO GRADE | 2 EACH | $1,940 | $1,750 | $2,275 |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 111 CY | $75.00 | $70.00 | $70.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $500 | $300 | $300 |
| 659E00501 SEEDING AND MULCHING, CLASS 1, AS PER PLAN | 1,000 SY | $2.00 | $2.00 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.15 TON | $1,000 | $1,200 | $1,200 |
| 659E31000 LIME | 0.21 ACRE | $1,000 | $1.00 | $10.00 |
| 659E35000 WATER | 5.4 MGAL | $10.00 | $0.25 | $10.00 |
| 832E30001 EROSION CONTROL, AS PER PLAN | 10,000 EACH | $1.00 | $1.00 | $1.00 |
| 605E11110 6" SHALLOW PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 432 FT | $22.90 | $15.00 | $25.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 50 FT | $22.90 | $15.00 | $23.00 |
| 611E04401 12" CONDUIT, TYPE B, AS PER PLAN | 18 FT | $190 | $250 | $200 |
| 611E98645 CATCH BASIN GRATE, AS PER PLAN | 1 EACH | $500 | $500 | $950 |
| 611E98690 CATCH BASIN, MISC.:CITY OF CLEVELAND CB-1 | 3 EACH | $4,600 | $8,000 | $4,500 |
| 611E99661 MANHOLE RECONSTRUCTED TO GRADE, AS PER PLAN | 2 EACH | $2,480 | $2,000 | $2,200 |
| 254E01600 PATCHING PLANED SURFACE | 2,044 SY | $10.00 | $1.00 | $1.00 |
| 255E10200 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 41 SY | $225 | $250 | $300 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 3,292 FT | $2.00 | $5.00 | $4.00 |
| 407E13900 TACK COAT, 702.13 | 4,176 GAL | $4.00 | $2.75 | $4.00 |
| 407E20000 NON-TRACKING TACK COAT | 3,132 GAL | $4.00 | $2.75 | $4.00 |
| 441E50201 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (14 CY | $575 | $825 | $475 |
| 872E10000 VOID REDUCING ASPHALT MEMBRANE (VRAM) | 6,526 FT | $3.00 | $2.00 | $1.94 |
| 630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST | 186 FT | $17.00 | $20.00 | $22.00 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 33 EACH | $145 | $295 | $265 |
| 630E80100 SIGN, FLAT SHEET | 221 SF | $29.00 | $25.00 | $21.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 15 EACH | $25.00 | $15.00 | $10.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 14 EACH | $30.00 | $20.00 | $20.00 |
| 630E87500 REMOVAL OF POLE MOUNTED SIGN AND DISPOSAL | 31 EACH | $30.00 | $25.00 | $30.00 |
| 644E00100 EDGE LINE, 4" | 0.12 MILE | $5,400 | $3,500 | $3,500 |
| 644E00200 LANE LINE, 4" | 2.03 MILE | $3,700 | $1,500 | $1,500 |
| 644E00301 CENTER LINE, AS PER PLAN | 1.88 MILE | $4,900 | $5,500 | $5,500 |
| 644E00400 CHANNELIZING LINE, 8" | 898 FT | $3.00 | $1.50 | $1.50 |
| 644E00500 STOP LINE | 993 FT | $8.00 | $6.00 | $6.00 |
| 644E00620 CROSSWALK LINE, 12" | 3,938 FT | $7.00 | $3.50 | $3.50 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 168 FT | $8.00 | $6.00 | $6.00 |
| 644E01300 LANE ARROW | 56 EACH | $120 | $95.00 | $95.00 |
| 625E30701 PULL BOX, 725.08, 18", AS PER PLAN | 1 EACH | $1,325 | $4,380 | $2,000 |
| 625E31600 PULL BOX, MISC.:PULL BOX ADJUSTED TO GRADE | 10 EACH | $890 | $240 | $850 |
| 631E92001 SIGN FLASHER ASSEMBLY, AS PER PLAN | 1 EACH | $2,315 | $5,050 | $5,500 |
| 632E20731 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, | 6 EACH | $705 | $775 | $650 |
| 632E26001 PEDESTRIAN PUSHBUTTON, AS PER PLAN | 6 EACH | $1,890 | $320 | $650 |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 18 EACH | $1,505 | $2,600 | $1,850 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 600 FT | $3.70 | $4.00 | $5.00 |
| 614E11111 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 128 HOUR | $75.00 | $85.00 | $95.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 8 SNMT | $1,050 | $900 | $900 |
| 614E20100 WORK ZONE LANE LINE, CLASS I, 4", 642 PAINT | 2.57 MILE | $990 | $1,500 | $1,500 |
| 614E20200 WORK ZONE LANE LINE, CLASS I, 4", 740.06, TYPE I | 0.03 MILE | $3,600 | $3,000 | $3,000 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 2.5 MILE | $1,500 | $2,000 | $2,000 |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 3.9 MILE | $770 | $1,750 | $1,750 |
| 614E22200 WORK ZONE EDGE LINE, CLASS I, 4", 740.06, TYPE I | 1.66 MILE | $6,900 | $3,000 | $3,000 |
| 614E23400 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 740.06, | 180 FT | $3.00 | $6.00 | $6.00 |
| 614E24400 WORK ZONE DOTTED LINE, CLASS I, 4", 740.06, TYPE I | 167 FT | $2.60 | $3.50 | $3.50 |
| 614E25400 WORK ZONE TRANSVERSE/DIAGONAL LINE, CLASS I, 740.0 | 140 FT | $6.50 | $20.00 | $20.00 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 40 FT | $4.00 | $3.50 | $3.50 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 160 FT | $13.00 | $20.00 | $20.00 |
| 614E30400 WORK ZONE ARROW, CLASS I, 740.06, TYPE I | 60 EACH | $200 | $150 | $150 |
| 616E10000 WATER | 10 MGAL | $25.00 | $1.00 | $3.00 |
| 616E20000 CALCIUM CHLORIDE | 1 TON | $500 | $1.00 | $1.00 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $10,000 | $5,000 | $25,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (2030 CY | $200 | $406k | 14% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 1,450 CY | $260 | $377k | 13% |
| 255E10011 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 1,488 SY | $225 | $335k | 11% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $202,323 | $202k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $180,400 | $180k | 6% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 3,871 SY | $40 | $155k | 5% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 73 EACH | $1,480 | $108k | 4% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (T | 41,764 SY | $2.5 | $104k | 4% |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 6,007 SF | $13 | $78k | 3% |
| 608E52001 CURB RAMP, AS PER PLAN | 2,704 SF | $27.5 | $74k | 3% |