CUY-IR 480-00.09 Replace
Cuyahoga County · est $1.0M
Bid dateThursday, May 25—
Cuyahoga County · est $1.0M
Bid tab · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20 items by low bid’s extended amount · 10 more items below.
| Item | Quantity | R1S E T INC | R2Turn-key Tunneling INC | R3Eclipse CO LLC | % of bid |
|---|---|---|---|---|---|
| 837E10001 LINER PIPE, AS PER PLAN, 148"x93" | 308 FT | $1,400 | $2,037 | $1,495 | 52% |
| 837E21001 BACKFILL FOR LINER PIPE, AS PER PLAN | 289 FT | $608 | $364 | $1,308 | 10% |
| 611E96560 CONDUIT, FIELD PAVING OF PIPE (148"x93") | 308 FT | $207 | $56.00 | $200 | 9% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 430 FT | $110 | $75.00 | $54.00 | 5% |
| 602E20000 CONCRETE MASONRY | 7.12 CY | $2,000 | $1,350 | $1,576 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $43,000 | $15,251 | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $100,000 | $70,250 | $45,694 |
| Item | Quantity | R1S E T INC | R2Turn-key Tunneling INC | R3Eclipse CO LLC |
|---|---|---|---|---|
| 202E35501 PIPE REMOVED FOR REUSE, 24" AND UNDER, AS PER PLAN | 30 FT | $130 | $84.00 | $88.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $200 | $250 | $110 |
| 659E00300 TOPSOIL | 29 CY | $90.00 | $136 | $91.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 13 SY | $4.00 | $2.50 | $4.20 |
| 659E20000 COMMERCIAL FERTILIZER | 0.04 TON | $2,500 | $850 | $2,048 |
| 659E31000 LIME | 0.05 ACRE | $120 | $60.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 3% |
| 203E20000 EMBANKMENT | 472 CY | $28.00 | $30.00 | $25.00 | 2% |
| 203E10000 EXCAVATION | 434 CY | $40.00 | $18.00 | $26.00 | 2% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $60,000 | $8,500 | $4,500 | 2% |
| 601E11001 RIPRAP, TYPE D, AS PER PLAN | 150 SY | $169 | $450 | $128 | 1% |
| 659E10000 SEEDING AND MULCHING | 4,100 SY | $3.00 | $10.00 | $2.73 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $9,500 | $5,420 | 1% |
| 202E98200 REMOVAL MISC.: PORTIONS OF EXISTING 14'-8" x 8'-11 | 19 FT | $600 | $405 | $264 | 1% |
| 601E32100 ROCK CHANNEL PROTECTION, TYPE B WITH FILTER | 52 CY | $195 | $120 | $156 | 1% |
| 832E30000 EROSION CONTROL | 8,000 EACH | $1.00 | $1.00 | $1.00 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,089 | $5,500 | $4,764 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $9,008 | $10,250 | $12,493 | 1% |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $3,000 | $3,623 | $2,751 | 1% |
| 202E20010 HEADWALL REMOVED | 1 EACH | $3,000 | $3,500 | $1,364 | 0% |
| $189 |
| 659E35000 WATER | 1 MGAL | $1.00 | $5.00 | $1.00 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (ONE WAY) | 10 EACH | $16.00 | $15.45 | $21.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 10 EACH | $20.00 | $20.60 | $21.00 |
| 616E10000 WATER | 5 MGAL | $100 | $5.00 | $70.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 837E10001 LINER PIPE, AS PER PLAN, 148"x93" | 308 FT | $1,655 | $510k | 51% |
| 837E21001 BACKFILL FOR LINER PIPE, AS PER PLAN | 289 FT | $325 | $94k | 9% |
| 611E96560 CONDUIT, FIELD PAVING OF PIPE (148"x93") | 308 FT | $300 | $92k | 9% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 430 FT | $108 | $46k | 5% |
| 602E20000 CONCRETE MASONRY | 7.12 CY | $5,600 | $40k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $35,000 | $35k | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $26,000 | $26k | 3% |
| 203E20000 EMBANKMENT | 472 CY | $40 | $19k | 2% |
| 203E10000 EXCAVATION | 434 CY | $40 | $17k | 2% |
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $15,000 | $15k | 2% |