D07-CHIP-FY24 (B)
D07 County · est $1.6M
Bid dateThursday, November 9—
D07 County · est $1.6M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 186,994 GAL | $3.75 | $701k |
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 1 more items below.
| Item | Quantity | R1Henry W Bergman INC | R2Shelly Company | R3Strawser Construction INC | R4Allied Construction, LLC | % of bid |
|---|---|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 186,994 GAL | $3.75 | $3.20 | $3.15 | $5.80 | 41% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 467,483 SY | $0.70 | $1.02 | $1.20 | $0.81 | 19% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 114.24 MILE | $978 | $830 | $800 | $770 | 7% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 57.12 MILE | $1,400 | $843 | $1,000 | $970 | 5% |
| 621E00100 RPM | 2,170 EACH | $35.00 | $40.00 | $32.00 | $31.00 | 4% |
| 642E30030 REMOVAL OF PAVEMENT MARKING EDGE LINE | 57.12 MILE | $1,300 | $1,528 | $1,150 | $1,100 |
| Item | Quantity | R1Henry W Bergman INC | R2Shelly Company | R3Strawser Construction INC | R4Allied Construction, LLC |
|---|---|---|---|---|---|
| 644E30000 REMOVAL OF PAVEMENT MARKING STOP LINE | 40 FT | $10.00 | $8.00 | $5.25 | $5.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 4% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 725 SY | $85.00 | $111 | $190 | $185 | 4% |
| 642E00300 CENTER LINE, TYPE 1 | 57.12 MILE | $1,000 | $815 | $1,250 | $1,210 | 3% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 2,170 EACH | $23.00 | $14.50 | $23.00 | $35.00 | 3% |
| 642E30030 REMOVAL OF PAVEMENT MARKING CENTER LINE | 28.56 MILE | $1,600 | $1,310 | $1,300 | $1,250 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $45,000 | $140,000 | $110,500 | $25,000 | 3% |
| 614E12460 WORK ZONE MARKING SIGN | 233 EACH | $120 | $100 | $100 | $105 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $40,000 | $135,050 | $25,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $8,500 | $11,000 | $26,000 | 1% |
| 614E31744 WORK ZONE SCHOOL SYMBOL MARKING, 96", CLASS I, 642 | 8 EACH | $500 | $350 | $205 | $200 | 0% |
| 642E01110 SCHOOL SYMBOL MARKING, 96", TYPE 1 | 8 EACH | $400 | $520 | $425 | $400 | 0% |
| 642E00500 STOP LINE, TYPE 1 | 220 FT | $10.00 | $5.30 | $8.50 | $8.00 | 0% |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 220 FT | $10.00 | $5.00 | $5.00 | $5.00 | 0% |
| 644E30020 REMOVAL OF PAVEMENT MARKING SCHOOL SYMBOL MARKING | 4 EACH | $500 | $200 | $210 | $200 | 0% |
| 642E30000 REMOVAL OF PAVEMENT MARKING STOP LINE | 70 FT | $10.00 | $8.00 | $1.55 | $1.50 | 0% |
| 41% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 467,483 SY | $0.7 | $327k | 19% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 114.24 MILE | $977.5 | $112k | 7% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 57.12 MILE | $1,400 | $80k | 5% |
| 621E00100 RPM | 2,170 EACH | $35 | $76k | 4% |
| 642E30030 REMOVAL OF PAVEMENT MARKING EDGE LINE | 57.12 MILE | $1,300 | $74k | 4% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 725 SY | $85 | $62k | 4% |
| 642E00300 CENTER LINE, TYPE 1 | 57.12 MILE | $1,000 | $57k | 3% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 2,170 EACH | $23 | $50k | 3% |
| 642E30030 REMOVAL OF PAVEMENT MARKING CENTER LINE | 28.56 MILE | $1,600 | $46k | 3% |