CUY-SR 17-12.58
CUY County · est $2.5M
Bid dateThursday, December 14—
CUY County · est $2.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 59 more items below.
| Item | Quantity | R1Shelly Company | R2Kokosing Construction Company INC | R3Ronyak Paving INC | R4Karvo Companies INC | % of bid |
|---|---|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 3,800 CY | $198 | $227 | $210 | $240 | 36% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (2748 CY | $185 | $199 | $195 | $235 | 25% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $220,000 | $125,140 | $163,700 | $275,000 | 11% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN | — | $1.75 | $2.00 | $2.00 | $4.47 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 | $145,000 | $300,000 | 5% |
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 319 CY | $210 | $255 | $325 |
| Item | Quantity | R1Shelly Company | R2Kokosing Construction Company INC | R3Ronyak Paving INC | R4Karvo Companies INC |
|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 659 SF | $5.00 | $5.00 | $4.00 | $15.00 |
| 202E32000 CURB REMOVED | 111 FT | $8.00 | $8.00 | $12.00 | $75.00 |
| 202E38000 GUARDRAIL REMOVED | 25 FT | $7.20 | $11.00 | $8.00 | $6.80 |
| 203E10000 EXCAVATION | 96 CY | $40.00 | $40.00 | $60.00 | $50.00 |
| 203E20000 EMBANKMENT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $275 |
| 3% |
| 407E20000 NON-TRACKING TACK COAT | 14,832 GAL | $3.00 | $2.60 | $3.00 | $3.00 | 2% |
| 255E10161 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 100 SY | $340 | $227 | $225 | $285 | 2% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 26 EACH | $975 | $975 | $1,350 | $1,875 | 1% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 15 EACH | $1,350 | $1,350 | $1,350 | $1,350 | 1% |
| 646E10000 EDGE LINE, 4" | 7.45 MILE | $2,235 | $2,235 | $2,235 | $3,510 | 1% |
| 875E10000 LONGITUDINAL JOINT ADHESIVE | 9,687 LB | $1.50 | $0.55 | $2.00 | $1.00 | 1% |
| 608E52001 CURB RAMP, AS PER PLAN | 502 SF | $27.00 | $27.00 | $30.00 | $25.00 | 1% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN, (1.5") AVG. | 188 CY | $65.00 | $120 | $135 | $100 | 1% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 80 HOUR | $150 | $95.00 | $100 | $90.00 | 1% |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 6 MNTH | $2,000 | $3,900 | $2,000 | $2,000 | 1% |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 14 EACH | $850 | $800 | $700 | $1,150 | 1% |
| 646E20800 YIELD LINE | 395 FT | $27.50 | $27.50 | $27.50 | $11.00 | 1% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 11 EACH | $960 | $960 | $1,350 | $1,300 | 1% |
| 609E10000 ASPHALT CONCRETE CURB, TYPE 1 | 955 FT | $10.50 | $10.50 | $20.00 | $15.00 | 0% |
| 86 CY |
| $25.00 |
| $25.00 |
| $50.00 |
| $70.00 |
| 204E21000 GRANULAR EMBANKMENT | 5 CY | $35.00 | $100 | $125 | $295 |
| 204E51000 GEOGRID | 11 SY | $40.00 | $20.00 | $10.00 | $25.00 |
| 209E60501 LINEAR GRADING, AS PER PLAN | 3.87 MILE | $850 | $2,000 | $600 | $4,000 |
| 606E13000 GUARDRAIL, TYPE 5 | 25 FT | $120 | $175 | $120 | $128 |
| 608E10000 4" CONCRETE WALK | 293 SF | $10.25 | $10.25 | $18.00 | $25.00 |
| 623E39601 MONUMENT ASSEMBLY RECONSTRUCTED TO GRADE, AS PER P | 1 EACH | $1,250 | $1,000 | $1,375 | $1,200 |
| 659E10000 SEEDING AND MULCHING | 260 SY | $8.00 | $8.00 | $7.95 | $4.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.04 TON | $50.00 | $50.00 | $675 | $1,500 |
| 659E31000 LIME | 0.06 ACRE | $50.00 | $50.00 | $50.00 | $4.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 260 SY | $6.50 | $6.50 | $12.80 | $7.00 |
| 611E98634 CATCH BASIN RECONSTRUCTED TO GRADE | 4 EACH | $1,250 | $1,250 | $2,400 | $2,200 |
| 611E99151 INLET ADJUSTED TO GRADE, AS PER PLAN | 9 EACH | $1,075 | $1,075 | $3,000 | $1,500 |
| 611E99154 INLET RECONSTRUCTED TO GRADE | 2 EACH | $1,350 | $1,350 | $4,000 | $1,600 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 1,500 LB | $3.00 | $3.00 | $4.00 | $3.00 |
| 611E99900 DRAINAGE STRUCTURE, MISC.:CLEANOUT | 13 EACH | $750 | $750 | $300 | $50.00 |
| 255E10161 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 11 SY | $216 | $216 | $475 | $385 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 1,331 FT | $3.00 | $3.00 | $6.00 | $5.00 |
| 304E20000 AGGREGATE BASE | 5 CY | $80.00 | $80.00 | $115 | $75.00 |
| 609E26000 CURB, TYPE 6 | 112 FT | $53.00 | $53.00 | $60.00 | $85.00 |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 13 EACH | $725 | $725 | $750 | $1,150 |
| 646E10100 LANE LINE, 4" | 4.33 MILE | $1,250 | $1,250 | $1,250 | $2,600 |
| 646E10200 CENTER LINE | 1.54 MILE | $4,250 | $4,250 | $4,250 | $4,780 |
| 646E10300 CHANNELIZING LINE, 8" | 2,230 FT | $1.65 | $1.65 | $1.65 | $1.70 |
| 646E10400 STOP LINE | 524 FT | $15.00 | $15.00 | $15.00 | $12.00 |
| 646E10510 CROSSWALK LINE, 12" | 704 FT | $9.00 | $9.00 | $9.00 | $6.00 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 153 FT | $15.00 | $15.00 | $15.00 | $11.00 |
| 646E10620 CHEVRON MARKING | 65 FT | $15.00 | $15.00 | $15.00 | $12.00 |
| 646E10800 ISLAND MARKING | 160 SF | $7.50 | $7.50 | $7.50 | $8.00 |
| 646E20300 LANE ARROW | 31 EACH | $200 | $200 | $200 | $162 |
| 646E20502 DOTTED LINE, 4" | 1,561 FT | $1.25 | $1.25 | $1.25 | $3.30 |
| 690E98400 SPECIAL - INVENTORY EXISTING PAVEMENT MARKINGS | 1 LS | $500 | $500 | $2,500 | $1,000 |
| 614E12460 WORK ZONE MARKING SIGN | 16 EACH | $85.00 | $85.00 | $85.00 | $90.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 50 CY | $135 | $125 | $250 | $300 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 12 SNMT | $800 | $900 | $800 | $800 |
| 614E20100 WORK ZONE LANE LINE, CLASS I, 4", 642 PAINT | 0.3 MILE | $650 | $650 | $650 | $3,900 |
| 614E20550 WORK ZONE LANE LINE, CLASS III, 4", 642 PAINT | 4.33 MILE | $650 | $650 | $650 | $650 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 1.1 MILE | $1,250 | $1,250 | $1,250 | $1,400 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 1.54 MILE | $1,250 | $1,250 | $1,250 | $1,150 |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 0.33 MILE | $900 | $900 | $900 | $4,800 |
| 614E22350 WORK ZONE EDGE LINE, CLASS III, 4", 642 PAINT | 7.45 MILE | $900 | $900 | $900 | $590 |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 1,317 FT | $0.55 | $0.55 | $0.55 | $1.00 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 2,230 FT | $0.55 | $0.55 | $0.55 | $0.70 |
| 614E24610 WORK ZONE DOTTED LINE, CLASS III, 4", 642 PAINT | 1,561 FT | $0.55 | $0.55 | $0.55 | $0.70 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 203 FT | $3.00 | $3.00 | $3.00 | $3.30 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 524 FT | $3.00 | $3.00 | $3.00 | $3.20 |
| 614E27050 WORK ZONE CROSSWALK LINE, CLASS I, 12", 642 PAINT | 579 FT | $2.75 | $2.75 | $2.75 | $1.65 |
| 614E27250 WORK ZONE CROSSWALK LINE, CLASS III, 12", 642 PAIN | 704 FT | $2.75 | $2.75 | $2.75 | $1.50 |
| 614E30200 WORK ZONE ARROW, CLASS I, 642 PAINT | 24 EACH | $45.00 | $45.00 | $45.00 | $50.00 |
| 614E30650 WORK ZONE ARROW, CLASS III, 642 PAINT | 31 EACH | $45.00 | $45.00 | $45.00 | $46.00 |
| 630E97800 SIGNING, MISC.:ADDITIONAL SIGNS, GROUND MOUNTED, A | 300 SF | $22.50 | $22.50 | $22.50 | $22.50 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,000 | $10,000 | $18,235 | $25,000 |
| 108E30000 CPM PROGRESS SCHEDULE SHORT DURATION PROJECTS | 1 LS | $5,000 | $1,000 | $2,500 | $4,700 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $8,000 | $6,000 | $10,500 | $5,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 3,800 CY | $198 | $752k | 33% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (2748 CY | $185 | $508k | 22% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $220,000 | $220k | 10% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN | — | $1.75 | $173k | 8% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 4% |
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 319 CY | $210 | $67k | 3% |
| 407E20000 NON-TRACKING TACK COAT | 14,832 GAL | $3 | $44k | 2% |
| 255E10161 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 100 SY | $340 | $34k | 2% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 26 EACH | $975 | $25k | 1% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 15 EACH | $1,350 | $20k | 1% |