MER-SR 29-07.80
MER County · est $1.6M
Bid dateThursday, January 11—
MER County · est $1.6M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 44 more items below.
| Item | Quantity | R1Brumbaugh Construction INC | R2Eagle Bridge CO | R3Miller Bros Const INC | R4R G Zachrich Construction INC | R5Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|---|
| 511E33312 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 278 CY | $1,100 | $1,150 | $1,150 | $1,230 | $1,000 | 26% |
| 509E26000 GALVANIZED STEEL REINFORCEMENT | 90,833 LB | $1.50 | $1.75 | $1.90 | $1.90 | $2.00 | 12% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 359 CY | $255 | $204 | $250 | $250 | $204 | 8% |
| 507E98000 PILING, MISC.: PREBORED HOLES ABOVE BEDROCK | 183 FT | $500 | $325 | $300 | $380 | $400 | 8% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 85 CY | $800 | $750 | $950 | $720 | $1,300 | 6% |
| 202E11002 |
| Item | Quantity | R1Brumbaugh Construction INC | R2Eagle Bridge CO | R3Miller Bros Const INC | R4R G Zachrich Construction INC | R5Complete General Construction Company |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,000 | $250 | $8,000 | $1,500 | $15,000 |
| 202E38001 GUARDRAIL REMOVED, AS PER PLAN | 615 FT | $5.00 | $3.50 | $7.50 | $7.50 | $2.00 |
| 203E10000 EXCAVATION | 959 CY | $15.00 | $20.00 | $30.00 | $15.00 | $10.00 |
| 203E20000 EMBANKMENT | 910 CY |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $60,000 |
| $60,000 |
| $200,000 |
| $120,000 |
| $120,000 |
| 5% |
| 624E10000 MOBILIZATION | 1 LS | $56,648 | $40,000 | $40,000 | $75,000 | $40,000 | 5% |
| 526E15001 REINFORCED CONCRETE APPROACH SLABS (T=13"), AS PER | 178 SY | $300 | $155 | $200 | $235 | $210 | 5% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 206 FT | $255 | $250 | $250 | $250 | $270 | 5% |
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 120 CY | $320 | $365 | $120 | $310 | $365 | 3% |
| 507E98000 PILING, MISC.: PREBORED HOLES INTO ROCK | 104 FT | $300 | $550 | $600 | $1,088 | $600 | 3% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 30,120 LB | $0.90 | $1.25 | $1.70 | $1.40 | $1.75 | 2% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $25,000 | $30,000 | $10,000 | $80,000 | $70,000 | 2% |
| 202E23000 PAVEMENT REMOVED | 1,164 SY | $20.00 | $15.00 | $12.00 | $4.25 | $16.50 | 2% |
| 503E21301 UNCLASSIFIED EXCAVATION, AS PER PLAN | 1 LS | $20,000 | $45,500 | $45,000 | $55,000 | $65,000 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $20,000 | $12,500 | $20,000 | $22,000 | $17,000 | 2% |
| 507E00201 STEEL PILES HP12X53, FURNISHED, AS PER PLAN | 320 FT | $60.00 | $50.00 | $70.00 | $60.00 | $75.00 | 2% |
| 304E20000 AGGREGATE BASE | 254 CY | $60.00 | $82.00 | $90.00 | $65.00 | $95.00 | 1% |
| 507E00101 STEEL PILES HP10X42, FURNISHED, AS PER PLAN | 300 FT | $50.00 | $40.00 | $60.00 | $52.00 | $55.00 | 1% |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 166 CY | $90.00 | $65.00 | $140 | $100 | $100 | 1% |
| $15.00 |
| $20.00 |
| $30.00 |
| $12.00 |
| $15.00 |
| 204E10000 SUBGRADE COMPACTION | 1,508 SY | $1.50 | $4.50 | $1.75 | $2.00 | $6.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 450 FT | $18.00 | $18.00 | $18.00 | $18.00 | $18.25 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, NCHRP 350 OR MASH 201 | 4 EACH | $2,700 | $2,450 | $2,450 | $2,450 | $2,480 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 4 EACH | $2,300 | $2,200 | $2,200 | $2,200 | $2,320 |
| 659E00300 TOPSOIL | 144 CY | $40.00 | $10.00 | $40.00 | $40.00 | $25.00 |
| 659E10000 SEEDING AND MULCHING | 1,291 SY | $2.00 | $3.00 | $2.50 | $2.50 | $3.20 |
| 659E20000 COMMERCIAL FERTILIZER | 0.18 TON | $700 | $1,250 | $800 | $800 | $700 |
| 659E31000 LIME | 0.27 ACRE | $5.00 | $5.00 | $36.00 | $35.00 | $10.00 |
| 659E35000 WATER | 8 MGAL | $5.00 | $10.00 | $1.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 2 CY | $80.00 | $150 | $100 | $130 | $250 |
| 605E31100 AGGREGATE DRAINS | 177 FT | $8.00 | $12.00 | $18.00 | $20.00 | $15.00 |
| 611E00900 6" CONDUIT, TYPE B | 50 FT | $6.00 | $6.00 | $10.00 | $20.00 | $6.00 |
| 611E01400 6" CONDUIT, TYPE E | 50 FT | $6.00 | $5.00 | $10.00 | $8.00 | $6.00 |
| 611E01500 6" CONDUIT, TYPE F | 50 FT | $6.00 | $5.00 | $10.00 | $8.00 | $6.00 |
| 611E02600 8" CONDUIT, TYPE F | 50 FT | $8.00 | $7.00 | $12.00 | $10.00 | $8.00 |
| 611E05200 12" CONDUIT, TYPE F | 50 FT | $12.00 | $28.00 | $15.00 | $12.00 | $12.00 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 61 FT | $15.00 | $8.00 | $6.00 | $16.00 | $15.00 |
| 407E10000 TACK COAT | 233 GAL | $1.00 | $3.00 | $1.00 | $1.00 | $3.00 |
| 617E10100 COMPACTED AGGREGATE | 33 CY | $55.00 | $82.00 | $85.00 | $140 | $1,000 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 6 EACH | $50.00 | $15.00 | $12.00 | $12.00 | $50.00 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 BI-DIRECTIONAL | 22 EACH | $14.00 | $11.00 | $11.00 | $11.00 | $12.50 |
| 630E80101 SIGN, FLAT SHEET, AS PER PLAN | 1.3 SF | $100 | $95.97 | $95.97 | $150 | $300 |
| 646E10010 EDGE LINE, 6" | 0.17 MILE | $25,000 | $23,640 | $23,640 | $24,000 | $38,400 |
| 646E10200 CENTER LINE | 0.09 MILE | $20,000 | $19,130 | $19,130 | $48,000 | $24,325 |
| 614E12420 DETOUR SIGNING | 1 LS | $10,000 | $8,000 | $7,250 | $8,000 | $19,000 |
| 202E22900 APPROACH SLAB REMOVED | 134 SY | $60.00 | $40.00 | $50.00 | $50.00 | $85.00 |
| 202E23500 WEARING COURSE REMOVED | 399 SY | $9.00 | $8.00 | $5.00 | $3.25 | $15.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 115 SY | $40.00 | $35.00 | $38.00 | $32.00 | $35.00 |
| 516E13200 1/2" PREFORMED EXPANSION JOINT FILLER | 85 SF | $4.00 | $6.00 | $7.00 | $8.00 | $25.00 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 119 SF | $6.00 | $7.00 | $8.00 | $10.00 | $17.00 |
| 516E14014 INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 137 FT | $30.00 | $32.00 | $36.00 | $37.00 | $40.00 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 75 CY | $70.00 | $105 | $125 | $120 | $150 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 235 FT | $12.00 | $16.00 | $19.00 | $18.00 | $14.50 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 143 FT | $12.00 | $11.00 | $10.00 | $20.00 | $10.00 |
| 518E40011 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 60 FT | $12.00 | $16.00 | $22.00 | $20.00 | $15.00 |
| 526E90020 TYPE B INSTALLATION | 58 SY | $75.00 | $55.00 | $85.00 | $60.00 | $150 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1,500 | $5,500 | $3,000 | $6,000 | $12,000 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $1,000 | $2,250 | $2,400 | $1,500 | $2,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,000 | $10,000 | $18,000 | $15,000 | $5,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 511E33312 CLASS QC2 CONCRETE WITH QC/QA, SUPERSTRUCTURE | 278 CY | $1,100 | $306k | 23% |
| 509E26000 GALVANIZED STEEL REINFORCEMENT | 90,833 LB | $1.5 | $136k | 10% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 359 CY | $255 | $92k | 7% |
| 507E98000 PILING, MISC.: PREBORED HOLES ABOVE BEDROCK | 183 FT | $500 | $92k | 7% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 85 CY | $800 | $68k | 5% |
| 202E11002 STRUCTURE REMOVED, OVER 20 FOOT SPAN | 1 LS | $60,000 | $60k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $56,648 | $57k | 4% |
| 526E15001 REINFORCED CONCRETE APPROACH SLABS (T=13"), AS PER | 178 SY | $300 | $53k | 4% |
| 517E70000 RAILING (TWIN STEEL TUBE) | 206 FT | $255 | $53k | 4% |
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 120 CY | $320 | $38k | 3% |