BRO-US 68-44.16
BRO County · est $2.7M
Bid dateThursday, January 25—
BRO County · est $2.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 71 more items below.
| Item | Quantity | R1D G M INC | R2John R Jurgensen Company | R3George J Igel & CO INC | R4Sunesis Construction CO | R5Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|---|
| 515E15100 DRAPED STRAND PRESTRESSED CONCRETE BRIDGE I-BEAM M | 5 EACH | $100,000 | $79,663 | $87,000 | $103,120 | $77,000 | 23% |
| 511E34446 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK | 215 CY | $1,160 | $1,151 | $1,020 | $1,258 | $950 | 12% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $155,000 | $101,237 | $326,250 | $122,882 | $130,000 | 7% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $125,000 | $30,367 | $180,000 | $54,459 | $80,000 | 6% |
| 517E70100 RAILING (THREE STEEL TUBE BRIDGE RAILING) | 253 FT | $475 | $459 | $470 | $462 | $500 | 6% |
| Item | Quantity | R1D G M INC | R2John R Jurgensen Company | R3George J Igel & CO INC | R4Sunesis Construction CO | R5Complete General Construction Company |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $20,000 | $12,422 | $15,000 | $8,530 | $15,000 |
| 202E23000 PAVEMENT REMOVED | 1,567 SY | $12.00 | $9.48 | $9.00 | $12.00 | $15.00 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 32 FT | $25.00 | $38.72 | $36.00 | $11.00 | $50.00 |
| 202E38000 GUARDRAIL REMOVED | 750 FT | $1.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 164 CY |
| $700 |
| $1,425 |
| $975 |
| $765 |
| $700 |
| 5% |
| 624E10000 MOBILIZATION | 1 LS | $112,000 | $100,000 | $100,000 | $114,919 | $100,000 | 5% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 85,099 LB | $1.25 | $1.19 | $1.25 | $1.00 | $2.00 | 5% |
| 524E94804 DRILLED SHAFTS, 42" DIAMETER, INTO BEDROCK | 180 FT | $505 | $476 | $370 | $456 | $800 | 4% |
| 526E30010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 267 SY | $290 | $533 | $375 | $416 | $330 | 4% |
| 511E46012 CLASS QC1 CONCRETE WITH QC/QA, RETAINING/WINGWALL | 96 CY | $750 | $699 | $280 | $1,241 | $1,200 | 3% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 306 CY | $230 | $260 | $255 | $222 | $220 | 3% |
| 511E46512 CLASS QC1 CONCRETE WITH QC/QA, FOOTING | 89 CY | $700 | $638 | $700 | $758 | $850 | 3% |
| 203E20000 EMBANKMENT | 2,955 CY | $20.00 | $23.03 | $15.50 | $16.00 | $11.00 | 3% |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 194 CY | $260 | $310 | $290 | $252 | $250 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $40,000 | $16,042 | $15,000 | $0.01 | $25,000 | 2% |
| 516E44100 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 10 EACH | $3,750 | $3,193 | $3,715 | $3,307 | $2,500 | 2% |
| 524E94902 DRILLED SHAFTS, 48" DIAMETER, ABOVE BEDROCK | 106 FT | $300 | $606 | $335 | $830 | $450 | 1% |
| 601E32004 ROCK CHANNEL PROTECTION, TYPE A WITH GEOTEXTILE FA | 322 CY | $87.50 | $108 | $121 | $154 | $125 | 1% |
| 304E20000 AGGREGATE BASE | 375 CY | $75.00 | $82.14 | $85.00 | $81.00 | $103 | 1% |
| $11.88 |
| $6.00 |
| $6.00 |
| $1.80 |
| 203E10000 EXCAVATION | 1,845 CY | $15.00 | $15.23 | $29.00 | $25.00 | $10.00 |
| 204E10000 SUBGRADE COMPACTION | 2,245 SY | $3.00 | $3.02 | $5.00 | $4.00 | $5.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 369 CY | $15.00 | $23.61 | $10.00 | $33.00 | $35.00 |
| 204E20000 EMBANKMENT | 369 CY | $20.00 | $28.12 | $7.00 | $16.00 | $80.00 |
| 204E45000 PROOF ROLLING | 2 HOUR | $75.00 | $212 | $112 | $382 | $200 |
| 606E15050 GUARDRAIL, TYPE MGS | 612.5 FT | $20.00 | $19.00 | $19.00 | $19.00 | $18.40 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP 350/MASH 2016) | 3 EACH | $2,300 | $2,250 | $2,595 | $2,266 | $2,520 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,100 | $1,000 | $1,000 | $1,007 | $1,345 |
| 606E34600 MGS BRIDGE TERMINAL ASSEMBLY, TYPE TST-2 | 4 EACH | $2,200 | $2,150 | $2,150 | $2,165 | $2,285 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 8 SY | $150 | $140 | $155 | $202 | $150 |
| 601E32104 ROCK CHANNEL PROTECTION, TYPE B WITH GEOTEXTILE FA | 42 CY | $95.00 | $251 | $153 | $163 | $125 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 2 CY | $200 | $431 | $720 | $154 | $375 |
| 659E00300 TOPSOIL | 958 CY | $15.00 | $31.73 | $11.00 | $31.00 | $25.00 |
| 659E10000 SEEDING AND MULCHING | 6,855 SY | $1.35 | $0.81 | $2.50 | $2.00 | $0.80 |
| 659E14000 REPAIR SEEDING AND MULCHING | 343 SY | $0.05 | $1.00 | $0.80 | $2.00 | $0.80 |
| 659E20000 COMMERCIAL FERTILIZER | 1.02 TON | $1,500 | $1,100 | $1,400 | $1,410 | $1,400 |
| 659E31000 LIME | 1.56 ACRE | $200 | $250 | $150 | $453 | $150 |
| 659E35000 WATER | 41 MGAL | $1.00 | $10.00 | $1.00 | $1.00 | $1.00 |
| 670E00500 SLOPE EROSION PROTECTION | 1,771 SY | $2.50 | $1.80 | $2.50 | $2.00 | $2.50 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,300 | $1,675 | $1,675 | $1,687 | $2,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $8,000 | $3,675 | $3,360 | $9,969 | $6,270 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $10,000 | $8,836 | $8,805 | $10,070 | $11,000 |
| 832E30000 EROSION CONTROL | 25,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 836E10000 SEEDING AND EROSION CONTROL WITH TURF REINFORCING | 662 SY | $7.00 | $3.50 | $1.00 | $6.00 | $6.00 |
| 602E20000 CONCRETE MASONRY | 1 CY | $2,000 | $1,711 | $1,900 | $2,872 | $5,000 |
| 605E31100 AGGREGATE DRAINS | 265 FT | $15.00 | $56.58 | $18.00 | $12.00 | $15.00 |
| 611E01500 6" CONDUIT, TYPE F | 30 FT | $10.00 | $64.07 | $28.50 | $29.00 | $40.00 |
| 611E07900 18" CONDUIT, TYPE D | 42 FT | $80.00 | $88.43 | $100 | $131 | $275 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 4 EACH | $300 | $743 | $460 | $469 | $500 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5" THICK) | 783 SY | $12.00 | $15.00 | $10.00 | $11.00 | $11.00 |
| 407E10000 TACK COAT | 300 GAL | $2.50 | $10.00 | $10.00 | $3.00 | $2.50 |
| 618E39000 RUMBLE STRIPS, TRANSVERSE (ASPHALT CONCRETE) | 2 EACH | $2,500 | $2,300 | $2,160 | $98.00 | $2,000 |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 60 FT | $100 | $97.25 | $98.00 | $98.00 | $8.00 |
| 621E00100 RPM | 10 EACH | $200 | $201 | $205 | $202 | $266 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 10 EACH | $1.00 | $22.59 | $30.00 | $202 | $50.00 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BI-DIRECTIONAL) | 2 EACH | $12.00 | $15.00 | $11.00 | $11.00 | $11.50 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BI-DIRECTIONAL) | 12 EACH | $12.00 | $11.00 | $11.00 | $11.00 | $12.50 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 46 FT | $25.00 | $21.00 | $21.00 | $21.00 | $19.00 |
| 630E80100 SIGN, FLAT SHEET | 23 SF | $20.00 | $16.00 | $16.00 | $16.00 | $22.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 3 EACH | $20.00 | $15.00 | $15.00 | $15.00 | $10.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 4 EACH | $20.00 | $20.00 | $20.00 | $20.00 | $15.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.34 MILE | $5,000 | $4,308 | $4,310 | $4,338 | $4,205 |
| 642E00300 CENTER LINE, TYPE 1 | 0.17 MILE | $7,000 | $6,460 | $6,460 | $6,505 | $4,530 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 16 HOUR | $50.00 | $87.98 | $100 | $70.00 | $90.00 |
| 614E12420 DETOUR SIGNING | 1 LS | $6,500 | $5,965 | $6,000 | $6,006 | $9,000 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 10 CY | $180 | $188 | $306 | $151 | $400 |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 6 SNMT | $1,200 | $1,050 | $1,050 | $1,057 | $957 |
| 616E10000 WATER | 2 MGAL | $1.00 | $51.92 | $61.00 | $21.00 | $75.00 |
| 202E23500 WEARING COURSE REMOVED | 363 SY | $8.00 | $9.03 | $7.50 | $8.00 | $30.00 |
| 503E21100 UNCLASSIFIED EXCAVATION | 76 CY | $25.00 | $78.13 | $125 | $1,813 | $2,200 |
| 511E33500 SEMI-INTEGRAL DIAPHRAGM GUIDE | 2 EACH | $1,700 | $6,169 | $3,700 | $3,110 | $8,000 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 579 SY | $37.00 | $23.50 | $28.50 | $34.00 | $23.50 |
| 515E20000 INTERMEDIATE DIAPHRAGMS | 12 EACH | $1,750 | $2,057 | $4,250 | $4,590 | $6,500 |
| 516E13600 1" PREFORMED EXPANSION JOINT FILLER | 3 SF | $30.00 | $16.21 | $45.00 | $9.00 | $35.00 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 68 SF | $20.00 | $9.78 | $15.00 | $5.00 | $15.00 |
| 516E14020 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 107 FT | $45.00 | $39.76 | $35.00 | $57.00 | $42.50 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 191 CY | $90.00 | $136 | $155 | $114 | $150 |
| 518E22300 SPECIAL - STEEL DRIP STRIP | 290 FT | $17.50 | $14.50 | $15.00 | $29.00 | $14.50 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 153 FT | $20.00 | $9.13 | $12.00 | $7.00 | $10.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 82 FT | $20.00 | $63.41 | $16.00 | $14.00 | $15.00 |
| 526E90010 TYPE A INSTALLATION | 82 FT | $220 | $322 | $220 | $174 | $275 |
| 894E10000 THERMAL INTEGRITY PROFILING (TIP) TEST | 2 EACH | $7,500 | $7,533 | $8,200 | $7,049 | $15,000 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $25,000 | $34,288 | $8,500 | $3,656 | $9,000 |
| 619E16010 FIELD OFFICE, TYPE B | 7 MNTH | $1,250 | $1,943 | $2,800 | $1,421 | $2,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,000 | $9,567 | $18,000 | $17,471 | $5,000 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $2,000 | $5,104 | $2,900 | $806 | $10,000 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $2,000 | $5,104 | $4,000 | $806 | $5,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E15100 DRAPED STRAND PRESTRESSED CONCRETE BRIDGE I-BEAM M | 5 EACH | $100,000 | $500k | 20% |
| 511E34446 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK | 215 CY | $1,160 | $249k | 10% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $155,000 | $155k | 6% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $125,000 | $125k | 5% |
| 517E70100 RAILING (THREE STEEL TUBE BRIDGE RAILING) | 253 FT | $475 | $120k | 5% |
| 511E44112 CLASS QC1 CONCRETE WITH QC/QA, ABUTMENT NOT INCLUD | 164 CY | $700 | $115k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $112,000 | $112k | 4% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 85,099 LB | $1.25 | $106k | 4% |
| 524E94804 DRILLED SHAFTS, 42" DIAMETER, INTO BEDROCK | 180 FT | $505 | $91k | 4% |
| 526E30010 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 267 SY | $290 | $77k | 3% |