COL-SR-SR 9/VAR-14.72/VAR
COL County · est $0.9M
Bid dateThursday, November 14—
COL County · est $0.9M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 20 more items below.
| Item | Quantity | R1Shelly & Sands INC | R2Kirila Contractors INC | R3Shelly Company | R4Karvo Companies INC | R5Barbicas Construction Company INC | % of bid |
|---|---|---|---|---|---|---|---|
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 1,103.2 CY | $222 | $230 | $240 | $250 | $250 | 32% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (873.6 CY | $228 | $205 | $230 | $243 | $250 | 26% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $66,947 | $63,800 | $92,000 | $48,000 | $40,000 | 9% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 2 1/4") | 31,605 SY | $1.85 | $3.00 | $3.05 | $2.55 | $3.00 | 8% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 15 EACH | $1,750 | $1,760 | $1,750 | $1,750 | $1,600 | 3% |
| 624E10000 MOBILIZATION |
| Item | Quantity | R1Shelly & Sands INC | R2Kirila Contractors INC | R3Shelly Company | R4Karvo Companies INC | R5Barbicas Construction Company INC |
|---|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 240 SF | $15.00 | $15.00 | $9.00 | $17.00 | $7.00 |
| 202E32500 CURB AND GUTTER REMOVED | 98 FT | $25.00 | $25.00 | $17.00 | $10.50 | $10.00 |
| 607E98000 FENCE, MISC.: TEMP. ORANGE PLASTIC CONSTRUCTION FE | 150 FT | $12.00 | $12.00 | $7.00 | $1.00 | $5.00 |
| 608E10000 4" CONCRETE WALK | 240 SF | $15.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $20,000 |
| $26,182 |
| $20,000 |
| $60,000 |
| $55,000 |
| 3% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $3,250 | $2,200 | $2,250 | $3,250 | $850 | 3% |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $650 | $704 | $400 | $650 | $561 | 2% |
| 646E10520 CROSSWALK LINE, 24" | 1,351 FT | $11.00 | $11.00 | $11.00 | $11.00 | $25.00 | 2% |
| 407E20000 NON-TRACKING TACK COAT | 4,828.7 GAL | $3.05 | $3.05 | $3.00 | $2.75 | $3.20 | 2% |
| 646E10510 CROSSWALK LINE, 12" | 2,521 FT | $5.55 | $5.55 | $5.55 | $5.55 | $15.00 | 2% |
| 608E52000 CURB RAMP | 240 SF | $44.17 | $44.50 | $22.00 | $24.25 | $42.00 | 1% |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 6 EACH | $1,450 | $1,175 | $1,450 | $1,450 | $950 | 1% |
| 611E98634 CATCH BASIN RECONSTRUCTED TO GRADE | 3 EACH | $2,750 | $2,055 | $2,750 | $2,750 | $1,500 | 1% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 4 EACH | $2,000 | $1,500 | $2,000 | $2,000 | $1,000 | 1% |
| 646E10200 CENTER LINE | 1.31 MILE | $5,460 | $5,460 | $5,460 | $5,460 | $6,250 | 1% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN (T | 635.5 SY | $10.00 | $6.00 | $11.00 | $19.00 | $8.00 | 1% |
| 611E99661 MANHOLE RECONSTRUCTED TO GRADE, AS PER PLAN | 2 EACH | $2,500 | $1,960 | $2,500 | $2,500 | $2,000 | 1% |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 824 FT | $6.00 | $6.00 | $6.00 | $6.00 | $5.50 | 1% |
| 646E20300 LANE ARROW | 27 EACH | $177 | $177 | $177 | $177 | $225 | 1% |
| $15.00 |
| $14.00 |
| $16.00 |
| $10.00 |
| 609E26000 CURB, TYPE 6 | 98 FT | $45.00 | $45.00 | $30.00 | $62.00 | $45.00 |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 2 EACH | $1,550 | $1,650 | $1,550 | $1,550 | $1,600 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 500 LB | $5.00 | $4.00 | $5.00 | $5.00 | $2.50 |
| 646E10000 EDGE LINE, 4" | 0.52 MILE | $4,329 | $4,329 | $4,329 | $4,329 | $5,750 |
| 646E10100 LANE LINE, 4" | 0.27 MILE | $3,480 | $3,480 | $3,480 | $3,480 | $4,750 |
| 646E10300 CHANNELIZING LINE, 8" | 621 FT | $1.67 | $1.67 | $1.67 | $1.67 | $3.75 |
| 646E10400 STOP LINE | 272 FT | $13.50 | $13.50 | $13.50 | $13.50 | $20.00 |
| 646E10900 HANDICAP SYMBOL MARKING | 2 EACH | $133 | $133 | $133 | $133 | $250 |
| 646E20200 PARKING LOT STALL MARKING | 1,101 FT | $4.00 | $4.00 | $4.00 | $4.00 | $5.50 |
| 614E12460 WORK ZONE MARKING SIGN | 16 EACH | $200 | $100 | $75.00 | $135 | $75.00 |
| 614E21000 WORK ZONE CENTER LINE, CLASS I | 3.24 MILE | $1,200 | $1,725 | $1,200 | $1,300 | $1,500 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 1.62 MILE | $1,500 | $1,350 | $1,500 | $1,100 | $1,500 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 274 FT | $4.00 | $8.00 | $4.00 | $3.35 | $5.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,000 | $4,800 | $5,000 | $4,000 | $20,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,000 | $5,100 | $5,000 | $1,500 | $250 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 1,103.2 CY | $222 | $245k | 30% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (873.6 CY | $228 | $199k | 25% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $66,947 | $67k | 8% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (T = 2 1/4") | 31,605 SY | $1.85 | $58k | 7% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 15 EACH | $1,750 | $26k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 2% |
| 619E16010 FIELD OFFICE, TYPE B | 6 MNTH | $3,250 | $20k | 2% |
| 441E70501 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $650 | $17k | 2% |
| 646E10520 CROSSWALK LINE, 24" | 1,351 FT | $11 | $15k | 2% |
| 407E20000 NON-TRACKING TACK COAT | 4,828.7 GAL | $3.05 | $15k | 2% |