D07-CHIP-FY25 (B)
D07 County · est $1.1M
Bid dateThursday, December 19—
D07 County · est $1.1M
Bid form · ODOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 104,845 GAL | $2.9 | $304k |
ODOT bid tab line items with each bidder’s unit price. Top 18items by winning bid’s extended amount.
| Item | Quantity | R1Shelly Company | R2Sc Construction & Materials LLC | R3Henry W Bergman INC | R4Ward Construction CO | R5Strawser Construction INC | % of bid |
|---|---|---|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 104,845 GAL | $2.90 | $3.25 | $3.50 | $4.10 | $3.00 | 30% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 262,113 SY | $0.87 | $1.00 | $0.75 | $0.92 | $1.23 | 22% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $87,130 | $20,000 | $75,000 | $52,000 | $48,727 | 8% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 1,000 SY | $85.50 | $65.00 | $75.00 | $70.00 | $130 | 8% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 63.8 MILE | $880 | $914 | $970 | $880 | $950 | 5% |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 63.8 MILE |
| $805 |
| $810 |
| $890 |
| $805 |
| $875 |
| 5% |
| 621E00100 RPM | 1,145 EACH | $40.00 | $40.00 | $44.00 | $40.00 | $39.00 | 4% |
| 642E30030 REMOVAL OF PAVEMENT MARKING, EDGE LINE, 6", TYPE 1 | 31.9 MILE | $1,015 | $1,000 | $1,150 | $1,015 | $1,100 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $35,000 | $50,000 | $40,000 | $111,325 | 3% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 31.9 MILE | $805 | $800 | $890 | $805 | $875 | 2% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1,145 EACH | $22.00 | $30.00 | $27.00 | $15.00 | $35.00 | 2% |
| 642E00300 CENTER LINE, TYPE 1 | 31.9 MILE | $750 | $800 | $820 | $750 | $825 | 2% |
| 642E30030 REMOVAL OF PAVEMENT MARKING, CENTER LINE, 6", TYPE | 15.95 MILE | $1,015 | $1,015 | $1,150 | $1,015 | $1,100 | 2% |
| 614E12460 WORK ZONE MARKING SIGN | 112 EACH | $100 | $100 | $110 | $100 | $105 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $8,500 | $15,000 | $8,000 | $8,000 | 0% |
| 642E00500 STOP LINE, TYPE 1 | 124 FT | $9.00 | $6.00 | $10.00 | $9.00 | $10.00 | 0% |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 124 FT | $3.50 | $3.50 | $3.85 | $3.50 | $3.75 | 0% |
| 642E30000 REMOVAL OF PAVEMENT MARKING, STOP LINE, TYPE 1 | 62 FT | $5.75 | $6.00 | $6.00 | $5.75 | $6.25 | 0% |
| 30% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 262,113 SY | $0.87 | $228k | 22% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $87,130 | $87k | 8% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 1,000 SY | $85.5 | $86k | 8% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 63.8 MILE | $880 | $56k | 5% |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 63.8 MILE | $805 | $51k | 5% |
| 621E00100 RPM | 1,145 EACH | $40 | $46k | 4% |
| 642E30030 REMOVAL OF PAVEMENT MARKING, EDGE LINE, 6", TYPE 1 | 31.9 MILE | $1,015 | $32k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $30k | 3% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 31.9 MILE | $805 | $26k | 2% |