WOO-MR 746-00.05 Pemberville Brdg
WOO County · est $2.0M
Bid dateThursday, September 25—
WOO County · est $2.0M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 55 more items below.
| Item | Quantity | R1E S Wagner Company | R2Vernon Nagel INC | R3Miller Bros Const INC | R4R G Zachrich Construction INC | R5R & I Construction INC | R6D2 Excavating LLC | R7Great Lakes Demolition Company | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 515E12051 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 14 EACH | $14,270 | $17,100 | $15,870 | $17,600 | $15,900 | $19,500 | $19,340 | 16% |
| 515E12051 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 7 EACH | $16,146 | $20,500 | $21,397 | $17,600 | $15,900 | $20,000 | $20,340 | 9% |
| Item | Quantity | R1E S Wagner Company | R2Vernon Nagel INC | R3Miller Bros Const INC | R4R G Zachrich Construction INC | R5R & I Construction INC | R6D2 Excavating LLC | R7Great Lakes Demolition Company |
|---|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $10,000 | $10,000 | $4,500 | $10,000 | $27,000 | $10,000 | $22,500 |
| 202E23000 PAVEMENT REMOVED | 309 SY | $10.25 | $16.00 | $8.00 | $10.00 | $8.00 | $15.00 | $20.00 |
| 202E30000 WALK REMOVED |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $109,500 |
| $76,000 |
| $106,891 |
| $36,000 |
| $50,000 |
| $200,000 |
| $107,000 |
| 9% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $107,645 | $147,000 | $120,549 | $120,000 | $215,000 | $100,000 | $150,000 | 8% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 98 CY | $1,038 | $1,000 | $908 | $1,159 | $1,000 | $1,000 | $1,450 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $75,772 | $78,000 | $79,810 | $30,000 | $85,000 | $25,000 | $125,500 | 6% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 81 CY | $777 | $650 | $776 | $830 | $1,000 | $1,250 | $925 | 5% |
| 524E94704 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK | 54 FT | $1,082 | $1,425 | $1,417 | $1,399 | $2,000 | $800 | $1,600 | 5% |
| 524E94604 DRILLED SHAFTS, 30" DIAMETER, INTO BEDROCK | 56 FT | $1,028 | $1,260 | $1,331 | $1,332 | $1,900 | $800 | $1,500 | 4% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 33,561 LB | $1.61 | $1.50 | $1.74 | $1.50 | $2.00 | $2.00 | $1.80 | 4% |
| 524E94803 DRILLED SHAFTS, 42" DIAMETER, ABOVE BEDROCK, AS PE | 42 FT | $1,217 | $800 | $803 | $1,157 | $803 | $700 | $450 | 4% |
| 517E75120 RAILING (CONCRETE PARAPET WITH TWIN STEEL TUBE RAI | 162 FT | $306 | $315 | $301 | $300 | $151 | $165 | $151 | 4% |
| 517E75121 RAILING (CONCRETE PARAPET WITH TWIN STEEL TUBE RAI | 162 FT | $277 | $315 | $301 | $300 | $151 | $165 | $151 | 4% |
| 511E41010 CLASS QC1 CONCRETE, PIER ABOVE FOOTINGS | 24 CY | $1,664 | $1,300 | $1,773 | $2,000 | $1,500 | $1,200 | $1,350 | 3% |
| 516E44101 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 56 EACH | $586 | $750 | $660 | $655 | $600 | $700 | $650 | 3% |
| 524E94702 DRILLED SHAFTS, 36" DIAMETER, ABOVE BEDROCK | 40 FT | $799 | $500 | $496 | $815 | $496 | $700 | $350 | 2% |
| 526E10001 REINFORCED CONCRETE APPROACH SLABS (T=12"), AS PER | 89 SY | $338 | $275 | $381 | $482 | $300 | $325 | $275 | 2% |
| 601E34100 ROCK CHANNEL PROTECTION, TYPE B WITHOUT FILTER | 217 CY | $96.00 | $100 | $78.61 | $170 | $100 | $200 | $140 | 2% |
| 832E30000 EROSION CONTROL | 20,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 511E51510 CLASS QC2 CONCRETE, SIDEWALK | 26 CY | $702 | $550 | $492 | $715 | $1,000 | $50.00 | $650 | 1% |
| 674 SF |
| $2.25 |
| $5.00 |
| $2.14 |
| $3.50 |
| $3.00 |
| $15.00 |
| $3.00 |
| 202E30701 CONCRETE BARRIER REMOVED, AS PER PLAN | 40 FT | $17.50 | $15.00 | $21.55 | $56.00 | $10.00 | $10.00 | $30.00 |
| 202E98200 REMOVAL MISC.:METAL RAILING | 47 FT | $5.70 | $10.00 | $8.82 | $12.00 | $15.00 | $10.00 | $30.00 |
| 203E10000 EXCAVATION | 51 CY | $55.00 | $20.00 | $31.20 | $25.00 | $20.00 | $25.00 | $25.00 |
| 203E20000 EMBANKMENT | 22 CY | $105 | $20.00 | $50.36 | $25.00 | $20.00 | $25.00 | $20.00 |
| 606E15050 GUARDRAIL, TYPE MGS | 25 FT | $23.00 | $23.00 | $23.00 | $23.00 | $23.00 | $25.00 | $23.00 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,450 | $1,450 | $1,450 | $1,450 | $1,450 | $1,500 | $1,450 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 1 EACH | $2,350 | $2,350 | $2,350 | $2,350 | $2,350 | $2,500 | $2,350 |
| 606E35003 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1, AS PER PLAN | 1 EACH | $2,350 | $2,350 | $2,350 | $2,350 | $2,350 | $2,500 | $2,350 |
| 607E98000 FENCE, MISC.:TEMPORARY ORANGE PLASTIC CONSTRUCTION | 500 FT | $5.85 | $2.19 | $5.19 | $15.00 | $10.00 | $5.00 | $10.00 |
| 607E98000 FENCE, MISC.:WOOD FENCE | 32 FT | $72.00 | $170 | $170 | $170 | $170 | $250 | $170 |
| 608E10000 4" CONCRETE WALK | 510 SF | $11.00 | $11.00 | $14.13 | $18.00 | $15.00 | $16.00 | $8.00 |
| 601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA | 12 CY | $145 | $170 | $222 | $150 | $100 | $170 | $125 |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 189 CY | $67.00 | $30.00 | $18.53 | $50.00 | $50.00 | $65.00 | $65.00 |
| 659E10000 SEEDING AND MULCHING | 1,699 SY | $1.80 | $1.80 | $1.80 | $1.80 | $3.50 | $7.25 | $3.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 85 SY | $1.80 | $1.80 | $1.80 | $1.80 | $0.50 | $1.00 | $1.00 |
| 659E15000 INTER-SEEDING | 85 SY | $1.00 | $1.00 | $1.00 | $1.00 | $0.10 | $1.00 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.25 TON | $850 | $850 | $850 | $850 | $538 | $1,000 | $1,000 |
| 659E35000 WATER | 9 MGAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 1 CY | $2,200 | $1,200 | $1,900 | $2,200 | $1,500 | $1,200 | $1,850 |
| 605E13410 6" UNCLASSIFIED PIPE UNDERDRAINS WITH GEOTEXTILE F | 102 FT | $24.00 | $15.00 | $26.22 | $23.00 | $12.00 | $25.00 | $12.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 40 FT | $29.00 | $18.00 | $51.57 | $30.00 | $12.00 | $25.00 | $15.00 |
| 611E04400 12" CONDUIT, TYPE B | 42 FT | $130 | $75.00 | $75.69 | $112 | $35.00 | $50.00 | $55.00 |
| 611E04600 12" CONDUIT, TYPE C | 114 FT | $115 | $65.00 | $62.15 | $95.00 | $35.00 | $50.00 | $40.00 |
| 611E98180 CATCH BASIN, NO. 3A | 4 EACH | $3,000 | $2,600 | $3,264 | $3,850 | $3,000 | $2,800 | $2,850 |
| 611E99574 MANHOLE, NO. 3 | 2 EACH | $3,800 | $3,200 | $6,108 | $7,000 | $3,500 | $9,000 | $4,250 |
| 204E10000 SUBGRADE COMPACTION | 257 SY | $4.75 | $1.00 | $2.72 | $4.00 | $2.00 | $3.00 | $3.00 |
| 251E01010 PARTIAL DEPTH PAVEMENT REPAIR (441) | 13 CY | $465 | $465 | $465 | $465 | $465 | $470 | $550 |
| 253E02000 PAVEMENT REPAIR | 6 CY | $575 | $575 | $575 | $575 | $575 | $600 | $675 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 3" | 57 SY | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 | $55.00 | $35.00 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 26 CY | $380 | $380 | $380 | $380 | $380 | $395 | $450 |
| 304E20000 AGGREGATE BASE | 43 CY | $40.00 | $70.00 | $59.54 | $115 | $70.00 | $70.00 | $65.00 |
| 407E10000 TACK COAT | 33 GAL | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $2.00 | $4.00 |
| 441E70000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG | 24 CY | $425 | $425 | $425 | $425 | $425 | $450 | $580 |
| 609E24511 CURB, TYPE 4-C, AS PER PLAN | 88 FT | $56.45 | $35.00 | $41.50 | $55.00 | $50.00 | $95.00 | $65.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 4 EACH | $22.00 | $50.00 | $50.00 | $50.00 | $25.00 | $50.00 | $50.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 2 EACH | $22.00 | $50.00 | $50.00 | $50.00 | $25.00 | $50.00 | $50.00 |
| 616E10000 WATER | 1 MGAL | $45.00 | $10.00 | $64.38 | $50.00 | $1.00 | $1,000 | $1.00 |
| 503E21101 UNCLASSIFIED EXCAVATION, AS PER PLAN | 200 CY | $77.00 | $100 | $83.28 | $150 | $70.00 | $200 | $45.00 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 556 SY | $28.50 | $26.00 | $22.72 | $35.00 | $35.00 | $30.00 | $50.00 |
| 516E10010 ARMORLESS PREFORMED JOINT SEAL | 53 FT | $57.00 | $35.00 | $54.32 | $160 | $50.00 | $20.00 | $56.00 |
| 516E13900 2" PREFORMED EXPANSION JOINT FILLER | 26 SF | $6.30 | $8.00 | $12.79 | $13.50 | $8.00 | $20.00 | $40.00 |
| 516E14020 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 80 FT | $34.30 | $50.00 | $30.23 | $42.00 | $30.00 | $56.00 | $30.00 |
| 516E44101 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 28 EACH | $577 | $750 | $651 | $725 | $600 | $660 | $700 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 60 CY | $115 | $100 | $119 | $130 | $100 | $200 | $70.00 |
| 518E40000 6" PERFORATED CORRUGATED PLASTIC PIPE | 97 FT | $8.00 | $10.00 | $6.60 | $15.00 | $12.00 | $20.00 | $12.00 |
| 518E40010 6" NON-PERFORATED CORRUGATED PLASTIC PIPE, INCLUDI | 48 FT | $11.50 | $10.00 | $11.90 | $15.00 | $12.00 | $20.00 | $12.00 |
| 526E90030 TYPE C INSTALLATION | 53 FT | $210 | $175 | $206 | $315 | $250 | $250 | $380 |
| 625E33000 STRUCTURE GROUNDING SYSTEM | 1 EACH | $11,130 | $10,963 | $10,963 | $9,750 | $2,600 | $10,000 | $4,500 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,200 | $15,000 | $7,842 | $24,000 | $24,000 | $20,000 | $16,500 |
| 108E30000 CPM PROGRESS SCHEDULE SHORT DURATION PROJECTS | 1 LS | $1.00 | $2,500 | $5,750 | $5,000 | $3,400 | $4,000 | $4,500 |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $3,500 | $5,500 | $1,500 | $8,000 | $6,000 | $10,000 | $6,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10.00 | $12,000 | $16,800 | $20,820 | $10,000 | $10,000 | $12,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 515E12051 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 14 EACH | $14,270 | $200k | 13% |
| 515E12051 PRESTRESSED CONCRETE COMPOSITE BOX BEAM BRIDGE MEM | 7 EACH | $16,146 | $113k | 7% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $109,500 | $110k | 7% |
| 202E11203 PORTIONS OF STRUCTURE REMOVED, OVER 20 FOOT SPAN, | 1 LS | $107,645 | $108k | 7% |
| 511E31610 CLASS QC2 CONCRETE, SUPERSTRUCTURE | 98 CY | $1,038 | $102k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $75,772 | $76k | 5% |
| 511E43510 CLASS QC1 CONCRETE, ABUTMENT INCLUDING FOOTING | 81 CY | $777 | $63k | 4% |
| 524E94704 DRILLED SHAFTS, 36" DIAMETER, INTO BEDROCK | 54 FT | $1,082 | $58k | 4% |
| 524E94604 DRILLED SHAFTS, 30" DIAMETER, INTO BEDROCK | 56 FT | $1,028 | $58k | 4% |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 33,561 LB | $1.61 | $54k | 4% |