HUR-SR 303-02.42
HUR County · est $0.2M
Bid dateThursday, October 23—
HUR County · est $0.2M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 29 more items below.
| Item | Quantity | R1Great Lakes Demolition Company | R2Crawford Construction Company INC | R3Bcc Ohio INC | R4Adena Corporation | R5Buckeye Excavating & Construction | R6INC Eclipse CO LLC | R7Stanley Miller Construction Company | R8Madex Construction CO | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 427 SY | $70.00 | $103 | $75.96 | $58.95 | $61.00 | $72.39 | $60.00 | $86.84 | 16% |
| 624E10000 MOBILIZATION | 1 LS | $24,500 | $12,000 | $8,124 | $14,766 | $14,000 |
| Item | Quantity | R1Great Lakes Demolition Company | R2Crawford Construction Company INC | R3Bcc Ohio INC | R4Adena Corporation | R5Buckeye Excavating & Construction | R6INC Eclipse CO LLC | R7Stanley Miller Construction Company | R8Madex Construction CO |
|---|---|---|---|---|---|---|---|---|---|
| 202E20010 HEADWALL REMOVED | 2 EACH | $250 | $360 | $774 | $300 | $1,500 | $1,365 | $300 | $1,288 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 67 FT | $25.00 | $44.00 | $30.81 | $39.31 | $48.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $29,542 |
| $17,000 |
| $29,910 |
| 13% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 76 CY | $300 | $298 | $368 | $302 | $283 | $275 | $300 | $347 | 12% |
| 442E22001 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 39 CY | $375 | $437 | $525 | $435 | $412 | $391 | $390 | $463 | 8% |
| 611E10400 24" CONDUIT, TYPE B | 75 FT | $160 | $164 | $249 | $345 | $455 | $219 | $220 | $326 | 6% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,500 | $2,900 | $20,768 | $22,133 | $13,200 | $16,500 | $13,250 | $18,906 | 5% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 3 EACH | $2,700 | $2,740 | $2,693 | $3,523 | $2,700 | $2,822 | $3,017 | $3,474 | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $6,500 | $1,725 | $1,452 | $10,019 | $3,500 | $5,748 | $7,000 | $11,523 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $6,500 | $3,800 | $4,541 | $9,780 | $7,000 | $2,216 | $7,000 | $8,684 | 4% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 44 CY | $140 | $190 | $158 | $140 | $172 | $217 | $165 | $232 | 3% |
| 304E20000 AGGREGATE BASE | 86 CY | $70.00 | $100 | $138 | $92.54 | $80.00 | $80.69 | $121 | $139 | 3% |
| 202E23000 PAVEMENT REMOVED | 289 SY | $20.00 | $15.00 | $14.86 | $20.00 | $11.00 | $20.26 | $21.00 | $17.86 | 3% |
| 203E20000 EMBANKMENT | 219 CY | $25.00 | $20.00 | $35.09 | $26.71 | $49.00 | $58.85 | $100 | $52.11 | 3% |
| 614E12420 DETOUR SIGNING | 1 LS | $4,500 | $3,900 | $4,794 | $4,282 | $4,000 | $14,351 | $9,000 | $9,263 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,500 | $4,000 | $2,760 | $5,123 | $6,000 | $4,636 | $14,000 | $7,368 | 2% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (VARIES 0" TO 3 | 146 SY | $30.00 | $33.00 | $21.00 | $45.11 | $58.00 | $45.31 | $50.00 | $46.32 | 2% |
| 611E99574 MANHOLE, NO. 3 | 1 EACH | $4,250 | $5,150 | $11,040 | $6,881 | $8,000 | $4,572 | $6,667 | $8,684 | 2% |
| 606E15050 GUARDRAIL, TYPE MGS | 150 FT | $25.00 | $27.00 | $24.57 | $28.29 | $24.00 | $25.74 | $27.00 | $34.74 | 2% |
| 659E00300 TOPSOIL | 101 CY | $35.00 | $42.60 | $71.70 | $40.53 | $30.00 | $68.03 | $50.00 | $76.32 | 2% |
| 659E10000 SEEDING AND MULCHING | 912 SY | $3.50 | $4.30 | $4.15 | $3.68 | $6.00 | $4.35 | $4.60 | $4.63 | 2% |
| $83.28 |
| $45.00 |
| $61.47 |
| 203E10000 EXCAVATION | 31 CY | $20.00 | $70.00 | $129 | $11.78 | $42.00 | $65.73 | $75.00 | $40.53 |
| 204E10000 SUBGRADE COMPACTION | 323 SY | $3.00 | $2.00 | $3.87 | $2.26 | $1.50 | $2.58 | $5.00 | $3.47 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 1 EACH | $1,500 | $1,500 | $1,449 | $2,136 | $1,450 | $1,518 | $1,623 | $2,316 |
| 623E38500 MONUMENT ASSEMBLY, TYPE C | 1 EACH | $1,650 | $2,670 | $2,251 | $2,732 | $2,000 | $1,804 | $2,750 | $1,158 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $1,000 | $845 | $840 | $1,108 | $800 | $499 | $2,750 | $2,895 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $1,000 | $845 | $840 | $1,108 | $800 | $499 | $2,750 | $2,895 |
| 601E11000 RIPRAP, TYPE D | 8 SY | $125 | $344 | $833 | $409 | $500 | $445 | $675 | $826 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 2 CY | $500 | $250 | $779 | $338 | $211 | $266 | $400 | $463 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $200 | $25.00 | $76.20 | $100 | $225 | $142 | $500 | $69.47 |
| 659E14000 REPAIR SEEDING AND MULCHING | 46 SY | $1.00 | $0.90 | $0.95 | $1.00 | $10.00 | $0.99 | $1.00 | $2.32 |
| 659E15000 INTER-SEEDING | 46 SY | $1.00 | $0.10 | $0.11 | $1.00 | $10.00 | $0.11 | $1.00 | $2.32 |
| 659E20000 COMMERCIAL FERTILIZER | 0.12 TON | $1,000 | $625 | $656 | $1,220 | $500 | $688 | $800 | $1,158 |
| 659E31000 LIME | 0.19 ACRE | $100 | $50.00 | $52.53 | $308 | $400 | $55.00 | $150 | $868 |
| 659E35000 WATER | 5.04 MGAL | $1.00 | $1.25 | $1.31 | $1.00 | $50.00 | $1.38 | $1.00 | $1.00 |
| 670E00520 SLOPE EROSION PROTECTION MAT, TYPE B | 46 SY | $15.00 | $4.80 | $5.04 | $3.76 | $6.00 | $5.28 | $21.00 | $5.79 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 48 FT | $15.00 | $20.00 | $8.43 | $7.46 | $20.00 | $10.49 | $26.00 | $78.78 |
| 611E10600 24" CONDUIT, TYPE C | 20 FT | $85.00 | $90.00 | $186 | $118 | $450 | $168 | $200 | $405 |
| 407E10000 TACK COAT | 50 GAL | $4.00 | $2.41 | $1.81 | $17.25 | $2.25 | $2.48 | $6.00 | $3.47 |
| 621E00100 RPM | 3 EACH | $1,000 | $834 | $924 | $586 | $800 | $858 | $1,000 | $1,158 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 3 EACH | $100 | $60.00 | $20.64 | $30.45 | $100 | $55.00 | $100 | $70.53 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL | 6 EACH | $15.00 | $16.00 | $15.75 | $15.22 | $16.00 | $16.50 | $1,500 | $28.95 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.09 MILE | $7,000 | $24,000 | $5,367 | $9,057 | $6,300 | $5,500 | $15,000 | $11,579 |
| 642E00300 CENTER LINE, TYPE 1 | 0.04 MILE | $13,000 | $67,000 | $5,250 | $18,622 | $12,600 | $5,500 | $25,000 | $24,316 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 2 SNMT | $1,200 | $1,872 | $924 | $1,263 | $1,050 | $1,418 | $800 | $937 |
| 602E20000 CONCRETE MASONRY | 1 CY | $2,850 | $2,620 | $3,570 | $2,406 | $4,500 | $4,453 | $3,200 | $2,316 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,000 | $3,470 | $3,099 | $5,686 | $2,700 | $3,836 | $7,500 | $11,071 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 427 SY | $70 | $30k | 14% |
| 624E10000 MOBILIZATION | 1 LS | $24,500 | $25k | 11% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 76 CY | $300 | $23k | 11% |
| 442E22001 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 39 CY | $375 | $15k | 7% |
| 611E10400 24" CONDUIT, TYPE B | 75 FT | $160 | $12k | 6% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,500 | $9k | 4% |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E | 3 EACH | $2,700 | $8k | 4% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $6,500 | $7k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $6,500 | $7k | 3% |
| 601E32000 ROCK CHANNEL PROTECTION, TYPE A WITH FILTER | 44 CY | $140 | $6k | 3% |