| Item | Quantity | R1Specialized Construction INC | R2Geauga Highway CO | R3Ronyak Paving INC | R4Barbicas Construction Company INC | R5Phillips Paving LLC | R6Karvo Companies INC | R7Shelly Company | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 628 CY | $245 | $247 | $255 | $321 | $260 | $300 | $285 | 23% |
| 441E50201 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (509 CY | $235 | $213 | $220 | $282 | $250 | $275 | $265 | 18% |
| 254E01001 |
| Item | Quantity | R1Specialized Construction INC | R2Geauga Highway CO | R3Ronyak Paving INC | R4Barbicas Construction Company INC | R5Phillips Paving LLC | R6Karvo Companies INC | R7Shelly Company |
|---|---|---|---|---|---|---|---|---|
| 202E23000 PAVEMENT REMOVED | 50 SY | $22.00 | $30.00 | $35.00 | $40.00 | $135 | $25.00 | $50.00 |
| 202E30000 WALK REMOVED | 891 SF | $1.75 | $3.00 | $4.00 | $3.50 | $12.00 | $5.00 | $15.00 |
| 202E32000 CURB REMOVED | 195 FT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 17,889 SY |
| $3.00 |
| $4.93 |
| $2.25 |
| $4.90 |
| $3.00 |
| $3.00 |
| $4.25 |
| 8% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 39 EACH | $1,000 | $1,100 | $1,000 | $1,300 | $1,250 | $1,300 | $1,100 | 6% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 17,889 SY | $2.00 | $0.80 | $1.00 | $2.25 | $2.00 | $1.00 | $2.25 | 5% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 900 SY | $35.00 | $65.00 | $95.00 | $38.00 | $70.00 | $45.00 | $75.00 | 5% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 25 EACH | $1,100 | $1,150 | $1,150 | $1,600 | $1,250 | $1,600 | $1,600 | 4% |
| 254E01600 PATCHING PLANED SURFACE | 2,500 SY | $10.00 | $0.50 | $1.00 | $3.30 | $5.00 | $1.00 | $1.00 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $8,500 | $88,105 | $60,000 | $95,000 | $125,000 | $50,000 | 4% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 24 SNMT | $900 | $900 | $900 | $900 | $900 | $1,225 | $900 | 3% |
| 422E25000 EMULSION, CHIP SEAL | 7,162 GAL | $2.90 | $3.00 | $3.00 | $2.90 | $2.00 | $6.00 | $2.90 | 3% |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 24 EACH | $750 | $650 | $600 | $800 | $1,000 | $1,500 | $1,000 | 3% |
| 609E10001 ASPHALT CONCRETE CURB, TYPE 1, AS PER PLAN | 1,009 FT | $16.00 | $12.00 | $20.00 | $18.00 | $16.00 | $25.00 | $20.00 | 2% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $15,000 | $38,000 | $72,700 | $60,000 | $119,000 | $100,000 | $195,000 | 2% |
| 608E52000 CURB RAMP | 681 SF | $21.00 | $21.00 | $45.00 | $30.00 | $20.00 | $33.00 | $30.00 | 2% |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 12 MNTH | $1,000 | $900 | $2,000 | $1,600 | $2,500 | $3,000 | $3,000 | 2% |
| 872E10000 VOID REDUCING ASPHALT MEMBRANE (VRAM) | 5,939 FT | $2.00 | $2.90 | $2.00 | $4.00 | $4.00 | $4.00 | $4.00 | 2% |
| 644E00300 CENTER LINE | 1.1 MILE | $7,500 | $7,250 | $7,250 | $7,250 | $7,500 | $8,895 | $7,250 | 1% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 80 HOUR | $95.00 | $100 | $125 | $80.00 | $125 | $125 | $120 | 1% |
| 623E39501 MONUMENT ASSEMBLY ADJUSTED TO GRADE, AS PER PLAN | 9 EACH | $775 | $500 | $1,175 | $900 | $1,000 | $1,000 | $1,500 | 1% |
| $11.00 |
| $12.50 |
| $10.00 |
| $9.00 |
| $17.00 |
| $11.00 |
| $18.00 |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 203 SF | $19.00 | $13.00 | $18.00 | $22.00 | $20.00 | $12.50 | $32.00 |
| 623E39601 MONUMENT ASSEMBLY RECONSTRUCTED TO GRADE, AS PER P | 5 EACH | $875 | $750 | $1,275 | $1,100 | $2,000 | $1,100 | $1,600 |
| 659E00300 TOPSOIL | 5 CY | $100 | $100 | $150 | $100 | $500 | $250 | $350 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 40 SY | $20.00 | $10.00 | $5.00 | $10.00 | $25.00 | $30.00 | $45.00 |
| 832E30000 EROSION CONTROL | 6,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E05201 4" UNCLASSIFIED PIPE UNDERDRAINS, AS PER PLAN | 50 FT | $10.00 | $25.00 | $20.00 | $20.00 | $50.00 | $35.00 | $20.00 |
| 611E98635 CATCH BASIN RECONSTRUCTED TO GRADE, AS PER PLAN | 2 EACH | $1,500 | $1,800 | $1,950 | $2,100 | $2,500 | $1,800 | $2,000 |
| 611E99661 MANHOLE RECONSTRUCTED TO GRADE, AS PER PLAN | 3 EACH | $1,325 | $1,600 | $1,625 | $1,700 | $2,000 | $1,400 | $1,400 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 1,000 LB | $5.00 | $2.00 | $5.00 | $3.00 | $5.00 | $2.75 | $6.00 |
| 407E20000 NON-TRACKING TACK COAT | 1,085 GAL | $3.40 | $3.00 | $2.00 | $3.10 | $2.00 | $2.30 | $3.00 |
| 452E10050 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 50 SY | $75.00 | $130 | $145 | $150 | $135 | $135 | $130 |
| 609E26000 CURB, TYPE 6 | 114 FT | $45.00 | $60.00 | $70.00 | $45.00 | $40.00 | $75.00 | $60.00 |
| 644E00500 STOP LINE | 75 FT | $10.00 | $7.50 | $7.50 | $7.50 | $10.00 | $6.00 | $7.50 |
| 644E00620 CROSSWALK LINE, 12" | 533 FT | $5.00 | $6.25 | $6.25 | $6.25 | $5.00 | $5.50 | $6.25 |
| 644E01200 PARKING LOT STALL MARKING | 260 FT | $4.00 | $3.50 | $3.50 | $3.50 | $4.00 | $4.20 | $3.50 |
| 644E01514 DOTTED LINE, 8" | 133 FT | $5.00 | $2.50 | $2.50 | $2.50 | $5.00 | $3.40 | $2.50 |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 2 EACH | $1,800 | $1,550 | $1,550 | $1,400 | $1,800 | $1,550 | $1,550 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 3.3 MILE | $1,800 | $1,250 | $1,250 | $1,250 | $1,800 | $2,260 | $1,250 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 1.1 MILE | $1,700 | $1,250 | $1,250 | $1,250 | $1,700 | $1,835 | $1,250 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 225 FT | $5.00 | $4.00 | $4.00 | $4.00 | $5.00 | $3.50 | $4.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 75 FT | $5.00 | $4.00 | $4.00 | $4.00 | $5.00 | $3.25 | $4.00 |
| 614E24204 WORK ZONE DOTTED LINE, CLASS I, 8", 642 PAINT | 133 FT | $3.00 | $0.75 | $0.75 | $0.75 | $3.00 | $1.00 | $0.75 |
| 614E27050 WORK ZONE CROSSWALK LINE, CLASS I, 12", 642 PAINT | 533 FT | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 614E98100 WORK ZONE PAVEMENT MARKING, MISC.:PARKING LOT STAL | 260 FT | $2.00 | $1.75 | $1.75 | $1.75 | $2.00 | $2.50 | $1.75 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $6,000 | $8,000 | $6,500 | $10,000 | $20,000 | $10,000 | $5,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,500 | $2,000 | $2,080 | $2,500 | $2,500 | $2,500 | $10,000 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $5,000 | $750 | $2,850 | $2,850 | $2,850 | $3,000 | $3,000 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $5,000 | $750 | $2,850 | $2,850 | $2,850 | $3,000 | $3,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 628 CY | $245 | $154k | 21% |
| 441E50201 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (509 CY | $235 | $120k | 16% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, T | 17,889 SY | $3 | $54k | 7% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 39 EACH | $1,000 | $39k | 5% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 17,889 SY | $2 | $36k | 5% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 900 SY | $35 | $32k | 4% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 25 EACH | $1,100 | $28k | 4% |
| 254E01600 PATCHING PLANED SURFACE | 2,500 SY | $10 | $25k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $25,000 | $25k | 3% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 24 SNMT | $900 | $22k | 3% |