WAY-SR 83-14.64
WAY County · est $0.8M
Bid dateThursday, April 5—
WAY County · est $0.8M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 26 more items below.
| Item | Quantity | R1Karvo Companies INC | R2Chagrin Valley Paving INC | R3Barbicas Construction Company INC | R4Kokosing Construction Company INC | R5Melway Paving CO INC | % of bid |
|---|---|---|---|---|---|---|---|
| 442E20201 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 1,933 CY | $121 | $120 | $135 | $135 | $150 | 33% |
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 1,380 CY | $143 | $140 | $140 | $171 | $168 | 28% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (3" DEPTH) | 39,722 SY | $1.60 | $2.30 | $2.00 | $1.30 | $1.96 | 9% |
| Item | Quantity | R1Karvo Companies INC | R2Chagrin Valley Paving INC | R3Barbicas Construction Company INC | R4Kokosing Construction Company INC | R5Melway Paving CO INC |
|---|---|---|---|---|---|---|
| 202E32501 CURB AND GUTTER REMOVED, AS PER PLAN | 100 FT | $38.00 | $10.00 | $8.00 | $15.00 | $10.05 |
| 209E60500 LINEAR GRADING | 0.58 MILE | $2,000 | $750 | $1,000 | $1,500 | $2,200 |
| 209E72051 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 0.58 MILE | $2,000 | $750 | $1,000 | $100 | $1,300 |
| 623E39500 MONUMENT BOX ADJUSTED TO GRADE |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $54,000 | $50,000 | $40,000 | $66,375 | $53,000 | 8% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 100 CY | $245 | $190 | $150 | $350 | $350 | 3% |
| 253E02000 PAVEMENT REPAIR | 100 CY | $245 | $190 | $150 | $350 | $350 | 3% |
| 255E10160 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 90 SY | $220 | $200 | $165 | $220 | $200 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $18,000 | $26,000 | $40,000 | $20,000 | $15,000 | 3% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 120 HOUR | $65.00 | $65.00 | $60.00 | $70.00 | $80.00 | 1% |
| 407E20000 NON-TRACKING TACK COAT (0.08 GAL/SY) | 3,180 GAL | $2.35 | $2.00 | $3.69 | $2.50 | $4.25 | 1% |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 8 SNMT | $900 | $900 | $1,100 | $900 | $800 | 1% |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $1,750 | $500 | $600 | $2,200 | $1,500 | 1% |
| AA2 644E01300 LANE ARROW (ALTERNATE 2) | 80 EACH | $80.00 | $80.00 | $75.00 | $85.00 | $80.00 | 1% |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 9 EACH | $700 | $750 | $350 | $600 | $825 | 1% |
| 617E10100 COMPACTED AGGREGATE | 76 CY | $80.00 | $70.00 | $60.00 | $110 | $85.00 | 1% |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 2,001 FT | $2.85 | $2.85 | $1.00 | $2.85 | $3.00 | 1% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 100 FT | $52.00 | $65.00 | $38.00 | $47.00 | $33.00 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 5.1 MILE | $995 | $995 | $1,820 | $995 | $1,000 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $6,000 | $10,000 | $3,400 | $4,900 | 1% |
| AA2 644E00400 CHANNELIZING LINE, 8" (ALTERNATE 2) | 3,982 FT | $1.25 | $1.25 | $1.15 | $1.50 | $1.30 | 1% |
| 4 EACH |
| $425 |
| $750 |
| $450 |
| $395 |
| $950 |
| 254E01600 PATCHING PLANED SURFACE | 397 SY | $0.40 | $5.00 | $2.10 | $1.25 | $16.00 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 360 FT | $3.00 | $3.00 | $2.50 | $4.50 | $2.10 |
| 407E20000 NON-TRACKING TACK COAT (0.05 GAL/SY) | 1,989 GAL | $2.35 | $2.00 | $3.69 | $2.50 | $4.25 |
| 408E10001 PRIME COAT, AS PER PLAN (0.04 GAL/SY) | 544 GAL | $4.00 | $2.00 | $5.00 | $2.85 | $3.50 |
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 16 CY | $143 | $140 | $140 | $171 | $168 |
| 617E20000 SHOULDER PREPARATION | 681 SY | $1.55 | $1.00 | $1.00 | $0.25 | $1.35 |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 3 EACH | $1,150 | $1,000 | $600 | $900 | $1,000 |
| 621E00100 RPM | 20 EACH | $105 | $105 | $45.00 | $45.00 | $120 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 20 EACH | $1.75 | $1.00 | $20.00 | $15.00 | $6.00 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 1.77 MILE | $650 | $650 | $1,015 | $650 | $660 |
| 642E00204 LANE LINE, 6", TYPE 1 | 0.89 MILE | $425 | $425 | $900 | $425 | $430 |
| 642E00300 CENTER LINE, TYPE 1 | 1.7 MILE | $875 | $875 | $1,155 | $875 | $880 |
| AA2 644E00500 STOP LINE (ALTERNATE 2) | 373 FT | $5.75 | $5.75 | $4.65 | $6.25 | $5.80 |
| AA2 644E00600 CROSSWALK LINE (ALTERNATE 2) | 1,668 FT | $2.65 | $2.65 | $2.40 | $2.75 | $2.70 |
| AA2 644E00700 TRANSVERSE/DIAGONAL LINE (ALTERNATE 2) | 568 FT | $4.50 | $4.50 | $4.50 | $5.00 | $4.60 |
| AA2 644E00900 ISLAND MARKING (ALTERNATE 2) | 53 SF | $4.50 | $4.50 | $2.50 | $5.00 | $4.60 |
| AA2 644E01100 SCHOOL SYMBOL MARKING, 72" (ALTERNATE 2) | 1 EACH | $100 | $100 | $500 | $110 | $100 |
| 614E12460 WORK ZONE MARKING SIGN | 8 EACH | $85.00 | $85.00 | $70.00 | $85.00 | $90.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 25 CY | $175 | $200 | $200 | $100 | $250 |
| 614E20550 WORK ZONE LANE LINE, CLASS III, 4", 642 PAINT | 2.67 MILE | $475 | $475 | $1,555 | $475 | $500 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 11,946 FT | $0.30 | $0.30 | $0.55 | $0.30 | $0.30 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $1,100 | $1,500 | $1,000 | $2,500 | $8,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E20201 ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE | 1,933 CY | $121 | $234k | 31% |
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 1,380 CY | $143 | $197k | 26% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (3" DEPTH) | 39,722 SY | $1.6 | $64k | 8% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $54,000 | $54k | 7% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 100 CY | $245 | $25k | 3% |
| 253E02000 PAVEMENT REPAIR | 100 CY | $245 | $25k | 3% |
| 255E10160 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 90 SY | $220 | $20k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $18,000 | $18k | 2% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 120 HOUR | $65 | $8k | 1% |
| 407E20000 NON-TRACKING TACK COAT (0.08 GAL/SY) | 3,180 GAL | $2.35 | $7k | 1% |