COL-SR 518-0.00/4.80
COL County · est $1.0M
Bid dateThursday, September 27—
COL County · est $1.0M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 6%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 6 more items below.
| Item | Quantity | R1Superior Paving & Materials INC | R2Shelly Company | R3Barbicas Construction Company INC | R4R T Vernal Paving & Excavating INC | R5Shelly & Sands INC | R6Nls Paving, INC | R7Central-allied Enterprises INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 424E12001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B, AS P | 2,973 CY | $172 | $173 | $193 | $176 | $189 | $210 | $186 | 56% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 350 CY | $225 | $175 | $160 | $255 | $220 | $210 | $345 | 9% |
| Item | Quantity | R1Superior Paving & Materials INC | R2Shelly Company | R3Barbicas Construction Company INC | R4R T Vernal Paving & Excavating INC | R5Shelly & Sands INC | R6Nls Paving, INC | R7Central-allied Enterprises INC |
|---|---|---|---|---|---|---|---|---|
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E31100 AGGREGATE DRAINS | 450 FT | $6.00 | $4.00 | $16.00 | $15.00 | $11.25 | $8.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 253E02000 PAVEMENT REPAIR |
| 225 CY |
| $230 |
| $205 |
| $160 |
| $255 |
| $285 |
| $210 |
| $375 |
| 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $41,000 | $115,000 | $23,000 | $35,000 | $36,000 | $58,000 | $100,000 | 4% |
| 646E10010 EDGE LINE, 6" | 12.74 MILE | $2,490 | $2,490 | $2,795 | $2,490 | $2,490 | $2,490 | $2,795 | 3% |
| 407E20000 NON-TRACKING TACK COAT | 8,809 GAL | $3.25 | $3.00 | $3.50 | $4.50 | $2.85 | $3.25 | $2.85 | 3% |
| 408E10001 PRIME COAT, AS PER PLAN | 5,868 GAL | $4.00 | $3.50 | $4.30 | $5.25 | $3.00 | $3.25 | $2.65 | 3% |
| 617E10100 COMPACTED AGGREGATE | 408 CY | $50.00 | $82.50 | $85.00 | $60.00 | $63.00 | $75.00 | $20.00 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $40,000 | $40,000 | $20,000 | $40,000 | $100,000 | 2% |
| 646E10200 CENTER LINE | 6.37 MILE | $2,800 | $2,800 | $2,890 | $2,800 | $2,800 | $2,800 | $2,890 | 2% |
| 621E00100 RPM | 843 EACH | $20.50 | $20.50 | $22.45 | $30.00 | $23.00 | $21.75 | $25.00 | 2% |
| 441E50401 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448) | — | $225 | $450 | $223 | $200 | $354 | $250 | $400 | 2% |
| 202E23500 WEARING COURSE REMOVED | 2,178 SY | $5.00 | $8.00 | $3.50 | $10.00 | $9.45 | $8.00 | $5.00 | 1% |
| 209E60500 LINEAR GRADING | 12.5 MILE | $750 | $295 | $850 | $1,500 | $1,500 | $800 | $100 | 1% |
| 209E72051 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 12.5 MILE | $680 | $295 | $850 | $1,000 | $1,600 | $1,200 | $100 | 1% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 6.41 MILE | $1,100 | $850 | $1,165 | $990 | $850 | $995 | $1,165 | 1% |
| 618E43000 CENTER LINE, RUMBLE STRIPE (ASPHALT CONCRETE) | 6.34 MILE | $986 | $1,000 | $2,500 | $1,100 | $1,000 | $1,000 | $1,500 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,200 | $4,000 | $10,000 | $5,000 | $2,500 | $4,500 | $15,000 | 1% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 843 EACH | $6.00 | $6.45 | $7.25 | $5.00 | $10.00 | $12.00 | $5.00 | 1% |
| 614E21500 WORK ZONE CENTER LINE, CLASS II, 642 PAINT | 6.41 MILE | $561 | $400 | $965 | $400 | $400 | $585 | $965 | 0% |
| $5.00 |
| 646E10400 STOP LINE | 28 FT | $19.00 | $19.00 | $15.00 | $19.00 | $12.00 | $19.00 | $15.00 |
| 646E20504 DOTTED LINE, 6" | 115 FT | $7.60 | $7.60 | $5.00 | $7.60 | $7.60 | $7.60 | $5.00 |
| 614E12460 WORK ZONE MARKING SIGN | 50 EACH | $65.00 | $65.00 | $60.00 | $65.00 | $125 | $100 | $65.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 28 FT | $10.00 | $3.00 | $2.40 | $16.75 | $3.00 | $16.75 | $2.40 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 424E12001 FINE GRADED POLYMER ASPHALT CONCRETE, TYPE B, AS P | 2,973 CY | $172 | $511k | 55% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 350 CY | $225 | $79k | 9% |
| 253E02000 PAVEMENT REPAIR | 225 CY | $230 | $52k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $41,000 | $41k | 4% |
| 646E10010 EDGE LINE, 6" | 12.74 MILE | $2,490 | $32k | 3% |
| 407E20000 NON-TRACKING TACK COAT | 8,809 GAL | $3.25 | $29k | 3% |
| 408E10001 PRIME COAT, AS PER PLAN | 5,868 GAL | $4 | $23k | 3% |
| 617E10100 COMPACTED AGGREGATE | 408 CY | $50 | $20k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20k | 2% |
| 646E10200 CENTER LINE | 6.37 MILE | $2,800 | $18k | 2% |