CUY-SR 3-02.72
CUY County · est $1.6M
Bid dateThursday, December 16—
CUY County · est $1.6M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 33 more items below.
| Item | Quantity | R1Chagrin Valley Paving INC | R2Ronyak Paving INC | R3Shelly Company | R4Kokosing Construction Company INC | R5Karvo Companies INC | % of bid |
|---|---|---|---|---|---|---|---|
| 255E10161 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 2,400 SY | $150 | $125 | $110 | $110 | $185 | 23% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 1,687 CY | $180 | $195 | $200 | $240 | $205 | 19% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (1352 CY | $160 | $165 | $170 | $215 | $180 | 14% |
| Item | Quantity | R1Chagrin Valley Paving INC | R2Ronyak Paving INC | R3Shelly Company | R4Kokosing Construction Company INC | R5Karvo Companies INC |
|---|---|---|---|---|---|---|
| 204E50000 GEOTEXTILE FABRIC, 712.09, TYPE D | 240 SY | $3.00 | $1.00 | $4.00 | $2.00 | $1.50 |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 800 SF | $9.00 | $12.00 | $10.00 | $10.00 | $6.00 |
| 623E38501 MONUMENT ASSEMBLY, AS PER PLAN | 1 EACH | $550 | $1,000 | $950 | $950 | $1,200 |
| 623E39500 MONUMENT BOX ADJUSTED TO GRADE | 14 EACH | $400 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $150,000 |
| $120,000 |
| $300,000 |
| $204,227 |
| $174,193 |
| 10% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, T | 48,171 SY | $2.00 | $2.00 | $1.95 | $2.75 | $2.25 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $90,000 | $94,100 | $40,000 | $100,000 | $120,000 | 6% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 1,000 SY | $52.00 | $65.00 | $31.50 | $66.00 | $100 | 3% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 72 EACH | $700 | $400 | $878 | $800 | $1,300 | 3% |
| 301E46001 ASPHALT CONCRETE BASE, PG64-22, AS PER PLAN | 150 CY | $250 | $195 | $250 | $550 | $675 | 2% |
| 608E52001 CURB RAMP, AS PER PLAN | 1,533 SF | $22.00 | $38.00 | $17.00 | $17.00 | $30.00 | 2% |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 18,000 LB | $1.50 | $4.00 | $1.50 | $1.85 | $1.75 | 2% |
| 609E26001 CURB, TYPE 6, AS PER PLAN | 550 FT | $45.00 | $42.00 | $45.00 | $47.50 | $50.00 | 2% |
| 872E10000 VOID REDUCING ASPHALT MEMBRANE (VRAM) | 13,993 FT | $1.70 | $2.00 | $1.70 | $1.70 | $1.70 | 2% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 50 CY | $350 | $375 | $500 | $240 | $270 | 1% |
| 832E30001 EROSION CONTROL, AS PER PLAN | 15,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 15 EACH | $1,000 | $1,317 | $1,000 | $1,000 | $1,100 | 1% |
| 407E20000 NON-TRACKING TACK COAT | 7,356 GAL | $2.00 | $2.00 | $2.85 | $2.10 | $2.25 | 1% |
| 644E00300 CENTER LINE | 3.2 MILE | $4,250 | $4,250 | $4,250 | $4,250 | $4,250 | 1% |
| 254E01601 PATCHING PLANED SURFACE, AS PER PLAN | 2,400 SY | $5.00 | $1.00 | $0.75 | $1.25 | $1.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $11,000 | $13,893 | $10,000 | $7,700 | $15,000 | 1% |
| $850 |
| $650 |
| $600 |
| $900 |
| 616E20000 CALCIUM CHLORIDE | 5 TON | $100 | $10.00 | $75.00 | $110 | $25.00 |
| 605E05201 4" UNCLASSIFIED PIPE UNDERDRAINS, AS PER PLAN | 200 FT | $13.00 | $5.00 | $12.00 | $12.00 | $10.00 |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN, DUAL / | 1 EACH | $1,400 | $1,000 | $1,550 | $1,450 | $1,600 |
| 611E98635 CATCH BASIN RECONSTRUCTED TO GRADE, AS PER PLAN | 2 EACH | $1,000 | $2,000 | $1,300 | $1,200 | $1,450 |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 6 EACH | $700 | $900 | $825 | $750 | $1,200 |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN, UTILITY MA | 10 EACH | $700 | $900 | $900 | $900 | $1,400 |
| 611E99661 MANHOLE RECONSTRUCTED TO GRADE, AS PER PLAN | 1 EACH | $1,000 | $950 | $1,300 | $1,300 | $1,600 |
| 203E98000 ROADWAY, MISC.:, UNDERCUTTING SUBGRADE AND SUBBASE | 40 CY | $65.00 | $75.00 | $30.00 | $60.00 | $95.00 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, T=1.50" | 1,067 SY | $5.00 | $10.00 | $15.00 | $2.75 | $7.50 |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 12 EACH | $400 | $800 | $625 | $600 | $800 |
| 638E10901 SERVICE BOX ADJUSTED TO GRADE, AS PER PLAN | 3 EACH | $400 | $100 | $100 | $100 | $825 |
| 644E00100 EDGE LINE, 4" | 0.04 MILE | $12,500 | $12,500 | $12,500 | $12,500 | $12,500 |
| 644E00400 CHANNELIZING LINE, 8" | 1,455 FT | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 644E00500 STOP LINE | 373 FT | $6.00 | $6.00 | $6.00 | $6.00 | $6.00 |
| 644E00600 CROSSWALK LINE | 1,630 FT | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 |
| 644E00600 CROSSWALK LINE, LADDER STYLE | 292 FT | $6.00 | $6.00 | $6.00 | $6.00 | $6.00 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 712 FT | $6.00 | $6.00 | $6.00 | $6.00 | $6.00 |
| 644E00900 ISLAND MARKING | 214 SF | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 644E01300 LANE ARROW | 28 EACH | $88.00 | $88.00 | $88.00 | $88.00 | $88.00 |
| 644E01410 WORD ON PAVEMENT, 96" | 8 EACH | $350 | $350 | $350 | $350 | $350 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 6.4 MILE | $100 | $1,000 | $1,000 | $700 | $1,000 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 3.2 MILE | $885 | $885 | $885 | $500 | $885 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 750 FT | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 375 FT | $3.50 | $3.50 | $3.50 | $3.50 | $3.50 |
| 614E27200 WORK ZONE CROSSWALK LINE, CLASS I, 642 PAINT | 3,300 FT | $2.35 | $2.35 | $2.35 | $2.35 | $2.35 |
| 614E27620 WORK ZONE CROSSWALK LINE, CLASS III, 642 PAINT | 1,650 FT | $2.35 | $2.35 | $2.35 | $2.35 | $2.35 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 60 HOUR | $100 | $75.00 | $70.00 | $80.00 | $75.00 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $2,000 | $1,500 | $1,500 | $2,100 | $2,000 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $100 | $8,133 | $1,500 | $1,000 | $5,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 255E10161 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 2,400 SY | $150 | $360k | 22% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 1,687 CY | $180 | $304k | 18% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (1352 CY | $160 | $216k | 13% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $150,000 | $150k | 9% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, T | 48,171 SY | $2 | $96k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $90,000 | $90k | 5% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 1,000 SY | $52 | $52k | 3% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 72 EACH | $700 | $50k | 3% |
| 301E46001 ASPHALT CONCRETE BASE, PG64-22, AS PER PLAN | 150 CY | $250 | $38k | 2% |
| 608E52001 CURB RAMP, AS PER PLAN | 1,533 SF | $22 | $34k | 2% |