CUY-US 6-03.85
CUY County · est $1.3M
Bid dateThursday, January 27—
CUY County · est $1.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 47 more items below.
| Item | Quantity | R1Ronyak Paving INC | R2Chagrin Valley Paving INC | R3Cross-roads Asphalt Recycling INC | R4Kokosing Construction Company INC | R5Shelly Company | R6Karvo Companies INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 1,040 CY | $200 | $195 | $200 | $240 | $200 | $250 | 18% |
| 441E10201 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (1213 CY | $155 | $135 | $156 | $180 | $135 | $165 | 16% |
| 253E01001 PAVEMENT REPAIR, AS PER PLAN | 700 SY | $130 | $80.00 |
| Item | Quantity | R1Ronyak Paving INC | R2Chagrin Valley Paving INC | R3Cross-roads Asphalt Recycling INC | R4Kokosing Construction Company INC | R5Shelly Company | R6Karvo Companies INC |
|---|---|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $500 | $100 | $500 | $500 | $1,500 | $2,500 |
| 202E23000 PAVEMENT REMOVED | 100 SY | $20.00 | $14.85 | $20.00 | $20.00 | $31.50 | $35.00 |
| 202E30001 WALK REMOVED, AS PER PLAN | 2,553 SF | $3.00 | $1.45 | $3.00 | $3.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $121 |
| $135 |
| $150 |
| $165 |
| 8% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 1,400 SY | $60.00 | $45.00 | $69.50 | $80.00 | $60.00 | $85.00 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $80,000 | $184,000 | $126,350 | $129,291 | $237,500 | $150,000 | 7% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN | — | $3.00 | $6.00 | $4.50 | $3.75 | $3.00 | $4.00 | 6% |
| 624E10000 MOBILIZATION | 1 LS | $66,400 | $125,390 | $40,000 | $40,000 | $40,000 | $105,000 | 6% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 79 EACH | $800 | $545 | $800 | $800 | $820 | $925 | 5% |
| 608E52001 CURB RAMP, AS PER PLAN | 2,579 SF | $20.00 | $12.39 | $20.00 | $20.00 | $15.25 | $13.00 | 4% |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 22,000 LB | $2.00 | $1.00 | $2.10 | $2.00 | $2.00 | $2.00 | 4% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 44 EACH | $850 | $839 | $850 | $850 | $950 | $1,025 | 3% |
| 441E50201 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (120 CY | $300 | $250 | $325 | $415 | $225 | $375 | 3% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 103 CY | $300 | $250 | $375 | $475 | $350 | $325 | 3% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 705 FT | $36.00 | $33.49 | $36.00 | $36.00 | $65.00 | $45.00 | 2% |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 33 EACH | $650 | $335 | $650 | $650 | $600 | $450 | 2% |
| 872E10000 VOID REDUCING ASPHALT MEMBRANE (VRAM) | 9,572 FT | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | 2% |
| 614E18600 PORTABLE CHANGEABLE MESSAGE SIGN | 20 SNMT | $900 | $650 | $900 | $900 | $650 | $900 | 2% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN | — | $6.00 | $6.00 | $9.00 | $2.25 | $10.50 | $10.00 | 1% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 200 HOUR | $70.00 | $75.00 | $55.00 | $70.00 | $65.00 | $75.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $10,601 | $10,000 | $9,000 | $6,000 | $5,000 | $18,000 | 1% |
| $2.45 |
| $5.50 |
| 202E32001 CURB REMOVED, AS PER PLAN | 945 FT | $10.50 | $10.59 | $10.50 | $10.50 | $14.00 | $18.00 |
| 203E10000 EXCAVATION | 20 CY | $45.00 | $32.85 | $45.00 | $45.00 | $30.00 | $35.00 |
| 204E10000 SUBGRADE COMPACTION | 100 SY | $1.00 | $1.45 | $1.00 | $1.00 | $10.00 | $3.00 |
| 204E13000 EXCAVATION OF SUBGRADE | 70 CY | $20.00 | $25.00 | $20.00 | $20.00 | $25.00 | $45.00 |
| 204E30010 GRANULAR MATERIAL, TYPE B | 70 CY | $25.00 | $100 | $25.00 | $25.00 | $50.00 | $65.00 |
| 204E50001 GEOTEXTILE FABRIC, AS PER PLAN | 210 SY | $1.50 | $2.00 | $1.50 | $1.50 | $2.00 | $1.25 |
| 608E10001 4" CONCRETE WALK, AS PER PLAN | 500 SF | $10.00 | $8.39 | $10.00 | $10.00 | $4.50 | $18.00 |
| 608E20000 2" ASPHALT CONCRETE WALK | 500 SF | $3.03 | $1.71 | $4.00 | $15.00 | $2.00 | $4.00 |
| 623E39501 MONUMENT BOX ADJUSTED TO GRADE, AS PER PLAN | 14 EACH | $750 | $479 | $750 | $750 | $1,000 | $600 |
| 623E40900 MONUMENT, MISC.: CUYAHOGA COUNTY CENTERLINE MONUME | 2 EACH | $950 | $895 | $950 | $950 | $1,000 | $1,400 |
| 623E40900 MONUMENT, MISC.: CUYAHOGA COUNTY MONUMENT BOX | 2 EACH | $950 | $895 | $950 | $950 | $1,000 | $1,400 |
| 623E40900 MONUMENT, MISC.: MONUMENT REFERENCING | 10 EACH | $327 | $250 | $550 | $250 | $250 | $233 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $50.00 | $345 | $30.00 | $50.00 | $100 | $25.00 |
| 659E00300 TOPSOIL | 33 CY | $78.50 | $81.75 | $170 | $78.50 | $160 | $150 |
| 659E10001 SEEDING AND MULCHING, AS PER PLAN | 300 SY | $4.00 | $6.39 | $15.00 | $4.00 | $5.00 | $1.50 |
| 659E20000 COMMERCIAL FERTILIZER | 0.04 TON | $17.00 | $6,865 | $1,500 | $17.00 | $2,500 | $1,000 |
| 659E31000 LIME | 0.06 ACRE | $615 | $4,475 | $1,000 | $615 | $1,666 | $25.00 |
| 659E35000 WATER | 2 MGAL | $1.00 | $165 | $200 | $1.00 | $100 | $1.00 |
| 832E30001 EROSION CONTROL, AS PER PLAN | 7,500 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 605E13410 6" UNCLASSIFIED PIPE UNDERDRAINS WITH GEOTEXTILE F | 100 FT | $8.00 | $17.99 | $8.00 | $8.00 | $15.00 | $17.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 490 FT | $8.00 | $20.85 | $8.00 | $8.00 | $25.00 | $22.00 |
| 611E98635 CATCH BASIN RECONSTRUCTED TO GRADE, AS PER PLAN | 2 EACH | $1,200 | $1,859 | $1,200 | $1,200 | $1,250 | $1,400 |
| 611E99661 MANHOLE RECONSTRUCTED TO GRADE, AS PER PLAN | 2 EACH | $1,100 | $1,869 | $1,100 | $1,100 | $1,200 | $1,200 |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 20 CY | $80.00 | $90.65 | $80.00 | $80.00 | $50.00 | $65.00 |
| 407E13900 TACK COAT, 702.13 | 2,739 GAL | $2.50 | $2.00 | $5.50 | $2.55 | $3.50 | $3.04 |
| 407E20000 NON-TRACKING TACK COAT | 2,739 GAL | $2.00 | $2.00 | $5.00 | $2.26 | $2.50 | $2.50 |
| 452E10050 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 80 SY | $75.00 | $51.35 | $75.00 | $75.00 | $60.00 | $85.00 |
| 452E12050 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 20 SY | $85.00 | $59.25 | $85.00 | $85.00 | $66.00 | $100 |
| 609E16000 CURB, TYPE 2-B | 240 FT | $24.00 | $12.45 | $24.00 | $24.00 | $65.00 | $32.00 |
| 638E10901 SERVICE BOX ADJUSTED TO GRADE, AS PER PLAN | 5 EACH | $100 | $215 | $100 | $100 | $300 | $500 |
| 638E98000 WATER WORK, MISC.:WATER MANHOLE ADJUSTED TO GRADE | 2 EACH | $800 | $489 | $800 | $800 | $1,500 | $1,000 |
| 644E00500 STOP LINE | 237 FT | $6.25 | $6.00 | $6.25 | $6.25 | $6.00 | $6.25 |
| 644E00620 CROSSWALK LINE, 12" | 1,274 FT | $3.25 | $3.00 | $3.25 | $3.25 | $3.00 | $3.25 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 1,153 FT | $4.85 | $5.50 | $4.85 | $4.85 | $5.50 | $4.85 |
| 644E00900 ISLAND MARKING | 246 SF | $4.85 | $3.00 | $4.85 | $4.85 | $3.00 | $4.85 |
| 644E01300 LANE ARROW | 7 EACH | $65.00 | $125 | $65.00 | $65.00 | $125 | $65.00 |
| 644E01410 WORD ON PAVEMENT, 96" | 5 EACH | $300 | $175 | $300 | $300 | $175 | $300 |
| 644E20800 YIELD LINE | 53 FT | $20.00 | $12.00 | $20.00 | $20.00 | $12.00 | $20.00 |
| 646E10200 CENTER LINE | 1.64 MILE | $5,000 | $4,800 | $5,000 | $5,000 | $4,800 | $5,000 |
| 646E10300 CHANNELIZING LINE, 8" | 452 FT | $2.00 | $1.95 | $2.00 | $2.00 | $1.95 | $2.00 |
| 690E98400 SPECIAL - MISC: INVENTORY EXISTING PAVEMENT MARKIN | 1 LS | $850 | $2,500 | $850 | $850 | $2,500 | $850 |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 4 EACH | $1,350 | $1,350 | $1,750 | $1,100 | $1,350 | $1,100 |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 5 MNTH | $1,500 | $1,750 | $1,750 | $2,000 | $2,500 | $2,000 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $3,888 | $2,500 | $4,500 | $2,000 | $5,000 | $2,880 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 1,040 CY | $200 | $208k | 16% |
| 441E10201 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (1213 CY | $155 | $188k | 14% |
| 253E01001 PAVEMENT REPAIR, AS PER PLAN | 700 SY | $130 | $91k | 7% |
| 251E01001 PARTIAL DEPTH PAVEMENT REPAIR (441), AS PER PLAN | 1,400 SY | $60 | $84k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $80,000 | $80k | 6% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN | — | $3 | $75k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $66,400 | $66k | 5% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 79 EACH | $800 | $63k | 5% |
| 608E52001 CURB RAMP, AS PER PLAN | 2,579 SF | $20 | $52k | 4% |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 22,000 LB | $2 | $44k | 3% |