LOR-US 6-12.36
LOR County · est $1.3M
Bid dateThursday, April 14—
LOR County · est $1.3M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 7.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 29 more items below.
| Item | Quantity | R1Karvo Companies INC | R2Ronyak Paving INC | R3Kokosing Construction Company INC | R4Barbicas Construction Company INC | R5Chagrin Valley Paving INC | % of bid |
|---|---|---|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 3,399 CY | $183 | $188 | $210 | $225 | $175 | 54% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE-1.25 | 81,476 SY | $1.33 | $1.50 | $1.85 | $2.75 | $5.00 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $64,269 | $80,000 | $85,268 | $40,000 | $150,000 | 6% |
| 624E10000 |
| Item | Quantity | R1Karvo Companies INC | R2Ronyak Paving INC | R3Kokosing Construction Company INC | R4Barbicas Construction Company INC | R5Chagrin Valley Paving INC |
|---|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 2,111 SF | $2.00 | $2.00 | $2.00 | $1.00 | $2.00 |
| 202E32000 CURB REMOVED | 16 FT | $11.00 | $11.00 | $11.00 | $11.00 | $11.00 |
| 202E32500 CURB AND GUTTER REMOVED | 10 FT | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $50,000 |
| $54,950 |
| $40,000 |
| $80,000 |
| $95,000 |
| 4% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 150 CY | $320 | $510 | $405 | $220 | $500 | 4% |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 43 EACH | $700 | $700 | $700 | $400 | $700 | 3% |
| 608E52000 CURB RAMP | 1,414 SF | $20.00 | $20.00 | $20.00 | $25.00 | $20.00 | 2% |
| 253E02000 PAVEMENT REPAIR | 85 CY | $320 | $525 | $435 | $220 | $750 | 2% |
| 617E10100 COMPACTED AGGREGATE | 368 CY | $73.00 | $96.00 | $30.00 | $80.00 | $80.00 | 2% |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 20 EACH | $950 | $950 | $950 | $600 | $950 | 2% |
| 611E99654 MANHOLE ADJUSTED TO GRADE | 19 EACH | $925 | $925 | $925 | $600 | $925 | 2% |
| 407E20000 NON-TRACKING TACK COAT @ 0.08 GAL/SY | 6,518 GAL | $2.50 | $3.00 | $2.00 | $2.80 | $2.00 | 1% |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 26.48 MILE | $600 | $600 | $600 | $600 | $600 | 1% |
| 644E01630 BIKE LANE SYMBOL MARKING | 62 EACH | $250 | $250 | $250 | $250 | $250 | 1% |
| 408E10001 PRIME COAT, AS PER PLAN | 3,429 GAL | $4.50 | $3.00 | $3.55 | $5.00 | $2.00 | 1% |
| 209E60500 LINEAR GRADING | 7.02 MILE | $1,835 | $1,800 | $1,000 | $700 | $750 | 1% |
| 644E00620 CROSSWALK LINE, 12" | 3,078 FT | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 | 1% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 13.24 MILE | $690 | $690 | $690 | $690 | $690 | 1% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 120 HOUR | $75.00 | $85.00 | $75.00 | $85.00 | $125 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,000 | $9,822 | $5,500 | $15,000 | $10,000 | 1% |
| 203E20001 EMBANKMENT, AS PER PLAN | 6 CY | $115 | $115 | $115 | $115 | $115 |
| 209E80000 GRADING MAILBOX APPROACHES | 10 EACH | $75.00 | $381 | $10.00 | $100 | $100 |
| 608E10000 4" CONCRETE WALK | 471 SF | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 10 FT | $50.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 609E26000 CURB, TYPE 6 | 87 FT | $40.00 | $40.00 | $40.00 | $50.00 | $40.00 |
| 623E39500 MONUMENT BOX ADJUSTED TO GRADE | 3 EACH | $725 | $725 | $725 | $725 | $725 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 1 EACH | $835 | $125 | $785 | $222 | $450 |
| 690E50200 SPECIAL - MAILBOX SUPPORT SYSTEM, DOUBLE | 1 EACH | $975 | $150 | $975 | $322 | $650 |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 254E01600 PATCHING PLANED SURFACE | 4,074 SY | $0.50 | $1.00 | $1.25 | $1.85 | $3.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 8 EACH | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 630E86010 REMOVAL OF GROUND MOUNTED POST SUPPORT AND REERECT | 3 EACH | $75.00 | $75.00 | $75.00 | $75.00 | $75.00 |
| 642E00300 CENTER LINE, TYPE 1 | 4 MILE | $975 | $975 | $975 | $975 | $975 |
| 644E00400 CHANNELIZING LINE, 8" | 215 FT | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 644E00500 STOP LINE | 468 FT | $6.15 | $6.15 | $6.15 | $6.15 | $6.15 |
| 644E00630 CROSSWALK LINE, 24" | 430 FT | $6.50 | $6.50 | $6.50 | $6.50 | $6.50 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 252 FT | $6.00 | $6.00 | $6.00 | $6.00 | $6.00 |
| 644E00900 ISLAND MARKING | 45 SF | $6.00 | $6.00 | $6.00 | $6.00 | $6.00 |
| 644E01300 LANE ARROW | 14 EACH | $90.00 | $90.00 | $90.00 | $90.00 | $90.00 |
| 644E01500 DOTTED LINE, 4" | 419 FT | $1.25 | $1.25 | $1.25 | $1.25 | $1.25 |
| 646E10400 STOP LINE | 24 FT | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 646E10510 CROSSWALK LINE, 12" | 128 FT | $20.00 | $20.00 | $20.00 | $20.00 | $20.00 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 8 MILE | $975 | $975 | $975 | $975 | $975 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 430 FT | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 619E16010 FIELD OFFICE, TYPE B | 4 MNTH | $2,000 | $1,650 | $2,000 | $200 | $1,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,100 | $4,179 | $1,500 | $600 | $4,179 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E00201 ASPHALT CONCRETE SURFACE COURSE, 9.5 MM, TYPE A (4 | 3,399 CY | $183 | $622k | 51% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE-1.25 | 81,476 SY | $1.33 | $108k | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $64,269 | $64k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $50,000 | $50k | 4% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 150 CY | $320 | $48k | 4% |
| 638E10800 VALVE BOX ADJUSTED TO GRADE | 43 EACH | $700 | $30k | 2% |
| 608E52000 CURB RAMP | 1,414 SF | $20 | $28k | 2% |
| 253E02000 PAVEMENT REPAIR | 85 CY | $320 | $27k | 2% |
| 617E10100 COMPACTED AGGREGATE | 368 CY | $73 | $27k | 2% |
| 611E98630 CATCH BASIN ADJUSTED TO GRADE | 20 EACH | $950 | $19k | 2% |