JEF-SR 7-04.00 Truck Parking Area
JEF County · est $0.7M
Bid dateThursday, May 12—
JEF County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 19 more items below.
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Litman Excavating INC | R4Eclipse CO LLC | R5Alan Stone CO INC | % of bid |
|---|---|---|---|---|---|---|---|
| 451E14010 9" REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 2,880 SY | $72.00 | $89.00 | $95.50 | $100 | $110 | 37% |
| 304E20000 AGGREGATE BASE | 1,963 CY | $80.00 | $75.00 | $81.00 | $84.78 | $100 | 28% |
| 255E10011 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 200 SY | $220 | $165 | $184 | $130 | $350 | 8% |
| 203E10000 EXCAVATION | 1,947 CY | $14.50 | $23.50 | $27.50 | $30.00 | $25.00 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $15,000 | $15,000 | $10,000 | $26,173 | $25,000 | 3% |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION |
| Item | Quantity | R1Ohio-west Virginia Excavating CO | R2Shelly & Sands INC | R3Litman Excavating INC | R4Eclipse CO LLC | R5Alan Stone CO INC |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $2,500 | $1,500 | $1,000 | $3,500 | $5,000 |
| 202E23000 PAVEMENT REMOVED | 245 SY | $17.00 | $6.00 | $27.00 | $21.02 | $10.00 |
| 204E45000 PROOF ROLLING | 2 HOUR | $140 | $250 | $134 | $260 | $220 |
| 611E98690 CATCH BASIN, MISC.:CAPPED AND SEALED | 2 EACH | $1,000 | $1,450 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 8 EACH |
| $1,600 |
| $1,050 |
| $1,063 |
| $1,200 |
| $1,200 |
| 2% |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 362 SF | $32.00 | $28.00 | $29.25 | $35.00 | $33.50 | 2% |
| 630E07500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X22 | 160 FT | $62.00 | $75.00 | $78.00 | $62.50 | $90.50 | 2% |
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 34 CY | $255 | $644 | $523 | $550 | $600 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $7,500 | $10,000 | $7,000 | $11,000 | $25,000 | 1% |
| 642E01200 PARKING LOT STALL MARKING, TYPE 1 | 1,608 FT | $4.50 | $5.00 | $4.50 | $1.12 | $5.00 | 1% |
| 204E10000 SUBGRADE COMPACTION | 2,894 SY | $2.50 | $2.00 | $1.50 | $1.25 | $3.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,000 | $3,600 | $6,900 | $12,000 | $10,000 | 1% |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 8 EACH | $850 | $805 | $853 | $440 | $985 | 1% |
| 618E40100 RUMBLE STRIPS, SHOULDER (ASPHALT CONCRETE) | 1,846 FT | $3.50 | $2.50 | $4.25 | $3.25 | $6.50 | 1% |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 2,047 FT | $3.00 | $1.50 | $1.25 | $1.06 | $2.00 | 1% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (2") | 823 SY | $6.50 | $17.00 | $14.75 | $13.37 | $22.50 | 1% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 1,073 FT | $4.50 | $3.00 | $3.50 | $3.02 | $5.00 | 1% |
| 202E70110 SPECIAL - PIPE CLEANOUT, 24" AND UNDER | 140 FT | $30.00 | $25.00 | $19.50 | $26.40 | $50.00 | 1% |
| $388 |
| $1,800 |
| $2,000 |
| 407E10000 TACK COAT | 70 GAL | $10.00 | $2.50 | $3.00 | $3.34 | $4.00 |
| 621E00100 RPM | 50 EACH | $65.00 | $65.00 | $69.00 | $62.50 | $79.50 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 87 FT | $22.00 | $21.50 | $16.50 | $14.00 | $19.00 |
| 630E06500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W6X9 | 41 FT | $27.00 | $38.00 | $39.50 | $41.00 | $50.00 |
| 630E80100 SIGN, FLAT SHEET | 46 SF | $22.00 | $20.00 | $20.25 | $26.50 | $23.50 |
| 630E85400 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND DISPOSAL | 1 EACH | $275 | $280 | $253 | $150 | $292 |
| 630E86102 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 2 EACH | $600 | $350 | $325 | $260 | $375 |
| 642E00104 EDGE LINE, 6", TYPE 1 | 0.97 MILE | $2,000 | $1,900 | $2,010 | $1,855 | $2,300 |
| 642E00404 CHANNELIZING LINE, 12", TYPE 1 | 1,293 FT | $1.20 | $1.15 | $1.25 | $1.24 | $1.50 |
| 642E00700 TRANSVERSE/DIAGONAL LINE, TYPE 1 | 142 FT | $6.50 | $6.50 | $6.50 | $6.18 | $7.50 |
| 642E00720 CHEVRON MARKING, TYPE 1 | 87 FT | $11.00 | $12.00 | $11.00 | $6.80 | $12.50 |
| 642E01510 DOTTED LINE, 6", TYPE 1 | 1,400 FT | $0.50 | $0.50 | $0.50 | $1.00 | $0.60 |
| 616E10000 WATER | 6 MGAL | $10.00 | $50.00 | $10.00 | $24.88 | $1.00 |
| 619E16000 FIELD OFFICE, TYPE A | 3 MNTH | $1,400 | $1,400 | $1,100 | $683 | $500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,000 | $4,000 | $5,500 | $8,000 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 451E14010 9" REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 2,880 SY | $72 | $207k | 35% |
| 304E20000 AGGREGATE BASE | 1,963 CY | $80 | $157k | 26% |
| 255E10011 FULL DEPTH PAVEMENT REMOVAL AND RIGID REPLACEMENT, | 200 SY | $220 | $44k | 7% |
| 203E10000 EXCAVATION | 1,947 CY | $14.5 | $28k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $15,000 | $15k | 3% |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 8 EACH | $1,600 | $13k | 2% |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 362 SF | $32 | $12k | 2% |
| 630E07500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X22 | 160 FT | $62 | $10k | 2% |
| 442E22100 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 34 CY | $255 | $9k | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $7,500 | $8k | 1% |