CLI-/GRE-CHIP FY2022
CLI County · est $1.0M
Bid dateThursday, August 25—
CLI County · est $1.0M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 10 more items below.
| Item | Quantity | R1Shelly Company | R2Allied Construction, LLC | R3Miller-mason Paving CO | R4Strawser Construction INC | % of bid |
|---|---|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 92,460 GAL | $3.05 | $4.00 | $4.00 | $3.70 | 27% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 231,150 SY | $0.84 | $1.00 | $0.45 | $1.10 | 18% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $104,500 | $30,000 | $85,000 | $90,766 | 10% |
| 886E11000 FOG SEAL | 34,673 GAL | $2.95 | $2.72 | $3.00 | $3.54 | 10% |
| 642E30030 REMOVAL OF PAVEMENT MARKING | 45.84 MILE | $1,520 | $1,520 | $2,500 | $1,600 | 7% |
| 253E02000 PAVEMENT REPAIR | 100 CY | $640 | $400 | $500 | $925 |
| Item | Quantity | R1Shelly Company | R2Allied Construction, LLC | R3Miller-mason Paving CO | R4Strawser Construction INC |
|---|---|---|---|---|---|
| 617E25000 WATER | 2 MGAL | $1.00 | $1.00 | $100 | $1.00 |
| 642E00500 STOP LINE, TYPE 1 | 74 FT | $11.20 | $11.20 | $11.20 | $11.25 |
| 642E01000 RAILROAD SYMBOL MARKING, TYPE 1 | 2 EACH | $350 | $350 | $350 | $355 |
| 642E01300 LANE ARROW, TYPE 1 | 3 EACH | $100 | $100 | $100 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 6% |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 91.68 MILE | $585 | $585 | $585 | $600 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $50,000 | $25,675 | $89,769 | 4% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 45.84 MILE | $750 | $750 | $750 | $800 | 3% |
| 621E00100 RPM | 1,081 EACH | $29.50 | $35.00 | $35.00 | $35.00 | 3% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 30.56 MILE | $830 | $830 | $830 | $840 | 2% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 1,081 EACH | $19.00 | $30.00 | $15.00 | $25.00 | 2% |
| 642E00300 CENTER LINE, TYPE 1 | 15.28 MILE | $760 | $760 | $760 | $800 | 1% |
| 617E10100 COMPACTED AGGREGATE | 58 CY | $165 | $105 | $200 | $190 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $5,000 | $12,000 | $5,000 | $6,500 | 0% |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $5,000 | $20,000 | $5,000 | $2,000 | 0% |
| 614E25200 WORK ZONE TRANSVERSE/DIAGONAL LINE, CLASS I, 642 P | 870 FT | $3.25 | $3.25 | $3.25 | $3.25 | 0% |
| 614E32200 WORK ZONE RAILROAD SYMBOL MARKING, CLASS I, 642 PA | 6 EACH | $350 | $350 | $350 | $350 | 0% |
| 642E00700 TRANSVERSE/DIAGONAL LINE, TYPE 1 | 290 FT | $6.70 | $6.70 | $6.70 | $6.75 | 0% |
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 370 FT | $2.45 | $2.45 | $2.45 | $2.50 | 0% |
| $105 |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 734 FT | $1.00 | $1.00 | $1.00 | $1.00 |
| 642E30020 REMOVAL OF PAVEMENT MARKING | 5 EACH | $150 | $150 | $150 | $155 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 8 HOUR | $80.00 | $200 | $300 | $85.00 |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 1,110 FT | $0.65 | $0.65 | $65.00 | $0.65 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 222 FT | $3.50 | $3.50 | $3.50 | $3.50 |
| 614E30200 WORK ZONE ARROW, CLASS I, 642 PAINT | 9 EACH | $100 | $100 | $100 | $100 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 422E25000 EMULSION, CHIP SEAL | 92,460 GAL | $3.05 | $282k | 26% |
| 422E11000 AGGREGATE, SINGLE CHIP SEAL, TYPE A | 231,150 SY | $0.84 | $194k | 18% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $104,500 | $105k | 10% |
| 886E11000 FOG SEAL | 34,673 GAL | $2.95 | $102k | 10% |
| 642E30030 REMOVAL OF PAVEMENT MARKING | 45.84 MILE | $1,520 | $70k | 7% |
| 253E02000 PAVEMENT REPAIR | 100 CY | $640 | $64k | 6% |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 91.68 MILE | $585 | $54k | 5% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 4% |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 45.84 MILE | $750 | $34k | 3% |
| 621E00100 RPM | 1,081 EACH | $29.5 | $32k | 3% |