MAR-SR 309-14.03
MAR County · est $0.5M
Bid dateThursday, September 29—
MAR County · est $0.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 28 more items below.
| Item | Quantity | R1D L Smith Concrete LLC | R2Park Enterprise Construction CO INC | R3Shelly & Sands INC | R4Complete General Construction Company | R5Smith Paving & Excavating INC | % of bid |
|---|---|---|---|---|---|---|---|
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 220 CY | $495 | $265 | $310 | $310 | $468 | 26% |
| 609E72001 CONCRETE MEDIAN, AS PER PLAN | 819 SY | $109 | $122 | $125 | $125 | $99.00 | 21% |
| 452E19200 NON-REINFORCED CONCRETE PAVEMENT, MISC.: 7" FAST S | 301 SY | $100 | $93.50 | $95.00 | $105 | $65.00 | 7% |
| 625E10490 LIGHT POLE, CONVENTIONAL, AT12B40 | 6 EACH | $5,000 | $4,100 | $2,875 | $2,875 | $3,450 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $25,000 | $25,000 | $27,500 | $113,000 | $95,000 | 6% |
| Item | Quantity | R1D L Smith Concrete LLC | R2Park Enterprise Construction CO INC | R3Shelly & Sands INC | R4Complete General Construction Company | R5Smith Paving & Excavating INC |
|---|---|---|---|---|---|---|
| 623E40000 MONUMENT ASSEMBLY REMOVED AND RESET | 2 EACH | $650 | $885 | $5,000 | $1,000 | $1,100 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 4 CY | $450 | $476 | $450 | $450 | $400 |
| 304E20001 AGGREGATE BASE, AS PER PLAN | 51 CY | $55.00 | $79.75 | $200 | $75.00 | $74.00 |
| 407E20000 NON-TRACKING TACK COAT |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 7,346 SY |
| $2.75 |
| $7.00 |
| $3.50 |
| $3.50 |
| $2.25 |
| 5% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $7,500 | $25,000 | $6,000 | $6,000 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $15,000 | $10,000 | $10,000 | $20,000 | $95,000 | 4% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,800 | $12,500 | $30,000 | $5,000 | $9,750 | 3% |
| 614E12420 DETOUR SIGNING | 1 LS | $9,500 | $15,000 | $35,000 | $44,000 | $8,500 | 2% |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 6 EACH | $1,500 | $2,300 | $1,800 | $2,000 | $1,865 | 2% |
| 202E23000 PAVEMENT REMOVED | 358 SY | $25.00 | $14.75 | $30.00 | $22.00 | $31.00 | 2% |
| 609E31000 COMBINATION CURB AND GUTTER, TYPE 9 | 195 FT | $45.00 | $46.75 | $85.00 | $75.00 | $40.00 | 2% |
| 442E20170 ASPHALT CONCRETE INTERMEDIATE COURSE, 12.5 MM, TYP | 17 CY | $490 | $341 | $260 | $260 | $450 | 2% |
| 625E25400 CONDUIT, 2", 725.04 | 547 FT | $15.00 | $27.75 | $18.50 | $18.50 | $23.00 | 2% |
| 625E23000 NO. 4 AWG 600 VOLT DISTRIBUTION CABLE | 1,863 FT | $4.00 | $4.30 | $3.75 | $3.75 | $3.60 | 2% |
| 625E29002 TRENCH, 24" DEEP | 547 FT | $10.00 | $15.00 | $9.00 | $9.00 | $12.50 | 1% |
| 644E00100 EDGE LINE, 4" | 0.81 MILE | $6,500 | $8,400 | $5,300 | $6,500 | $6,500 | 1% |
| 832E30000 EROSION CONTROL | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 10 EACH | $500 | $384 | $450 | $450 | $320 | 1% |
| 453 GAL |
| $2.75 |
| $5.50 |
| $3.50 |
| $3.50 |
| $2.50 |
| 625E00450 CONNECTION, FUSED PULL APART | 20 EACH | $175 | $133 | $110 | $110 | $110 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 10 EACH | $150 | $133 | $110 | $110 | $110 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 3 EACH | $120 | $133 | $150 | $150 | $110 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 936 FT | $3.00 | $2.50 | $2.25 | $2.25 | $2.00 |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04, 3" | 74 FT | $50.00 | $69.75 | $100 | $100 | $58.00 |
| 625E30700 PULL BOX, 725.08, 18" | 2 EACH | $850 | $1,100 | $1,200 | $1,200 | $930 |
| 625E32000 GROUND ROD | 6 EACH | $350 | $343 | $350 | $350 | $285 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 547 FT | $1.00 | $2.60 | $2.00 | $2.00 | $2.10 |
| 625E75506 LUMINAIRE REMOVED | 4 EACH | $150 | $81.75 | $50.00 | $50.00 | $68.00 |
| 621E00100 RPM, 1-WAY WHITE | 64 EACH | $63.00 | $75.00 | $125 | $60.00 | $63.00 |
| 621E00100 RPM, 2-WAY YELLOW/YELLOW | 14 EACH | $64.50 | $75.00 | $125 | $80.00 | $64.50 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 50 EACH | $1.00 | $12.00 | $50.00 | $8.43 | $50.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 379 FT | $9.50 | $11.25 | $12.75 | $9.50 | $9.50 |
| 630E08600 SIGN POST REFLECTOR | 8 EACH | $25.00 | $30.00 | $46.00 | $25.00 | $25.00 |
| 630E80100 SIGN, FLAT SHEET | 178.9 SF | $15.00 | $18.00 | $20.00 | $15.00 | $15.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 25 EACH | $25.00 | $30.00 | $25.00 | $25.00 | $25.00 |
| 630E85201 REMOVAL OF GROUND MOUNTED SIGN AND DELIVERY, AS PE | 2 EACH | $50.00 | $60.25 | $118 | $50.00 | $50.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 42 EACH | $25.00 | $30.00 | $25.00 | $25.00 | $25.00 |
| 644E00300 CENTER LINE | 0.2 MILE | $7,500 | $9,600 | $11,000 | $7,500 | $7,500 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 244 FT | $15.00 | $19.50 | $8.85 | $15.00 | $15.00 |
| 644E01520 DOTTED LINE, 12" | 139 FT | $8.00 | $10.25 | $3.00 | $8.00 | $8.00 |
| 644E20800 YIELD LINE | 60 FT | $20.00 | $25.75 | $13.00 | $20.00 | $20.00 |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 415 FT | $4.00 | $14.25 | $3.00 | $11.00 | $11.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $75.00 | $83.50 | $81.00 | $81.00 | $95.00 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 442E10000 ASPHALT CONCRETE SURFACE COURSE, 12.5 MM, TYPE A ( | 220 CY | $495 | $109k | 23% |
| 609E72001 CONCRETE MEDIAN, AS PER PLAN | 819 SY | $109 | $89k | 19% |
| 452E19200 NON-REINFORCED CONCRETE PAVEMENT, MISC.: 7" FAST S | 301 SY | $100 | $30k | 6% |
| 625E10490 LIGHT POLE, CONVENTIONAL, AT12B40 | 6 EACH | $5,000 | $30k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $25,000 | $25k | 5% |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE, 1.5" | 7,346 SY | $2.75 | $20k | 4% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $15,000 | $15k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $15,000 | $15k | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $10,800 | $11k | 2% |
| 614E12420 DETOUR SIGNING | 1 LS | $9,500 | $10k | 2% |