ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 85 more items below.
| Item | Quantity | R1Anthony Allega Cement Contractor | R2INC Karvo Companies INC | R3Perk Company INC | R4Great Lakes Construction CO | R5Ruhlin Company | R6Fabrizi Trucking & Paving CO INC | % of bid |
|---|---|---|---|---|---|---|---|---|
| 452E14120 11" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 9,497 SY | $83.53 | $92.00 | $100 | $132 | $152 | $128 | 38% |
| 452E14022 10.5" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1 | 2,125 SY | $105 | $88.50 | $111 | $127 | $138 | $136 | 11% |
| 304E20000 AGGREGATE BASE | 2,209 CY | $71.99 | $76.00 |
| Item | Quantity | R1Anthony Allega Cement Contractor | R2INC Karvo Companies INC | R3Perk Company INC | R4Great Lakes Construction CO | R5Ruhlin Company | R6Fabrizi Trucking & Paving CO INC |
|---|---|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 362 SF | $2.30 | $1.50 | $4.65 | $3.50 | $1.75 | $2.00 |
| 202E30800 TRAFFIC ISLAND REMOVED | 176 SY | $11.83 | $10.00 | $37.80 | $17.00 | $48.00 | $18.00 |
| 202E32000 CURB REMOVED | 1,734 FT | $2.40 | $10.00 | $2.75 | $3.50 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $74.00 |
| $90.00 |
| $82.00 |
| $72.00 |
| 8% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 2,189 CY | $64.65 | $68.50 | $62.00 | $70.00 | $70.00 | $68.00 | 7% |
| 202E23000 PAVEMENT REMOVED | 13,399 SY | $8.00 | $17.50 | $20.00 | $22.00 | $21.50 | $40.00 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $249,300 | $90,000 | $175,000 | $174,831 | $298,985 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $75,000 | $38,000 | $160,000 | $55,000 | $45,000 | $83,600 | 4% |
| 204E13000 EXCAVATION OF SUBGRADE | 2,189 CY | $29.06 | $30.25 | $40.00 | $60.00 | $60.00 | $22.00 | 3% |
| 832E30000 EROSION CONTROL | 54,277 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 3% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $51,120 | $20,000 | $15,185 | $4,500 | $55,000 | $46,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $50,000 | $31,785 | $30,000 | $34,000 | $21,250 | $52,300 | 2% |
| 611E05900 15" CONDUIT, TYPE B | 250 FT | $188 | $132 | $105 | $120 | $183 | $215 | 2% |
| 605E13510 6" ROCK CUT UNDERDRAINS WITH GEOTEXTILE FABRIC | 2,349 FT | $15.88 | $14.65 | $27.20 | $42.00 | $44.00 | $24.00 | 2% |
| 611E98300 CATCH BASIN, NO. 5 | 4 EACH | $7,964 | $5,200 | $5,915 | $5,500 | $9,000 | $6,590 | 2% |
| 605E11110 6" SHALLOW PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 2,144 FT | $14.81 | $13.70 | $14.00 | $22.00 | $20.00 | $14.00 | 2% |
| 203E10000 EXCAVATION | 833 CY | $37.37 | $35.00 | $40.00 | $55.00 | $74.00 | $32.00 | 1% |
| 659E00300 TOPSOIL | 455 CY | $61.60 | $45.00 | $60.00 | $55.00 | $55.00 | $75.00 | 1% |
| 209E60201 LINEAR GRADING, AS PER PLAN | 29 STA | $861 | $1,000 | $560 | $755 | $1,050 | $286 | 1% |
| 606E60022 IMPACT ATTENUATOR, TYPE 2 (UNIDIRECTIONAL), 45 MPH | 1 EACH | $24,360 | $21,750 | $21,750 | $21,750 | $21,750 | $21,750 | 1% |
| 614E12420 DETOUR SIGNING | 1 LS | $20,423 | $15,000 | $15,000 | $20,000 | $15,000 | $26,500 | 1% |
| $4.50 |
| $4.00 |
| 202E35100 PIPE REMOVED, 24" DIAMETER AND UNDER | 350 FT | $5.42 | $18.00 | $15.00 | $31.00 | $20.00 | $8.00 |
| 202E35200 PIPE REMOVED, OVER 24" DIAMETER | 16 FT | $39.30 | $39.00 | $82.00 | $140 | $109 | $15.00 |
| 202E38000 GUARDRAIL REMOVED | 465.7 FT | $5.60 | $5.00 | $6.00 | $5.00 | $5.00 | $5.00 |
| 202E42206 ANCHOR ASSEMBLY REMOVED | 2 EACH | $280 | $250 | $835 | $250 | $250 | $250 |
| 202E47800 IMPACT ATTENUATOR REMOVED | 1 EACH | $532 | $475 | $835 | $475 | $475 | $475 |
| 202E58100 CATCH BASIN REMOVED | 8 EACH | $861 | $900 | $755 | $1,350 | $1,400 | $385 |
| 202E70110 SPECIAL - PIPE CLEANOUT, 24" AND UNDER | 1,332 FT | $14.00 | $6.75 | $29.50 | $22.00 | $24.00 | $42.00 |
| 202E70120 SPECIAL - PIPE CLEANOUT, 27" TO 48" | 345 FT | $28.00 | $42.50 | $25.50 | $30.00 | $39.00 | $65.00 |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 111 FT | $56.00 | $42.50 | $40.00 | $37.00 | $73.00 | $130 |
| 203E20000 EMBANKMENT | 572 CY | $23.31 | $40.00 | $35.50 | $16.00 | $74.00 | $14.00 |
| 204E10000 SUBGRADE COMPACTION | 13,377 SY | $0.31 | $0.95 | $1.25 | $2.00 | $2.00 | $3.30 |
| 204E45000 PROOF ROLLING | 7 HOUR | $267 | $400 | $300 | $350 | $750 | $115 |
| 209E15001 RESHAPING UNDER GUARDRAIL, AS PER PLAN | 5 STA | $833 | $110 | $2,450 | $110 | $650 | $225 |
| 606E15050 GUARDRAIL, TYPE MGS | 437.5 FT | $23.52 | $21.00 | $21.00 | $21.00 | $21.00 | $21.00 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E, MASH 2016 | 1 EACH | $3,192 | $2,850 | $2,850 | $2,850 | $2,850 | $2,850 |
| 606E26550 ANCHOR ASSEMBLY, MGS TYPE T | 2 EACH | $1,176 | $1,050 | $1,050 | $1,050 | $1,050 | $2,100 |
| 608E13000 6" CONCRETE WALK | 163 SF | $18.32 | $9.55 | $18.85 | $20.00 | $30.00 | $11.00 |
| 608E52000 CURB RAMP, TYPE B3 | 144 SF | $19.34 | $9.55 | $37.50 | $22.00 | $37.00 | $32.00 |
| 608E53020 DETECTABLE WARNING | 20 SF | $20.36 | $35.00 | $40.50 | $80.00 | $78.00 | $41.00 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $448 | $400 | $500 | $400 | $400 | $225 |
| 659E00510 SEEDING AND MULCHING, CLASS 2 | 4,155 SY | $1.04 | $0.93 | $2.60 | $0.93 | $0.93 | $7.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 205 SY | $2.24 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 659E15000 INTER-SEEDING | 205 SY | $2.24 | $0.01 | $2.00 | $0.10 | $0.60 | $2.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.66 TON | $1,680 | $1,500 | $1,000 | $1,500 | $1,500 | $850 |
| 659E31000 LIME | 0.85 ACRE | $1,680 | $0.01 | $1,000 | $0.11 | $135 | $1,050 |
| 659E35000 WATER | 23 MGAL | $112 | $0.01 | $50.00 | $0.10 | $5.00 | $10.00 |
| 670E00700 DITCH EROSION PROTECTION | 297 SY | $3.92 | $3.50 | $4.50 | $3.50 | $3.50 | $4.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,660 | $2,700 | $4,500 | $4,000 | $5,500 | $2,600 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $13,709 | $8,500 | $2,450 | $10,500 | $10,200 | $14,000 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $10,881 | $10,150 | $9,715 | $11,000 | $9,713 | $7,500 |
| 605E13410 6" UNCLASSIFIED PIPE UNDERDRAINS WITH GEOTEXTILE F | 259 FT | $20.72 | $15.00 | $17.85 | $22.00 | $26.00 | $28.00 |
| 605E14020 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC | 1,321 FT | $13.84 | $14.30 | $17.85 | $25.00 | $13.50 | $15.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 251 FT | $29.56 | $21.00 | $17.85 | $22.00 | $42.00 | $18.00 |
| 611E03300 10" CONDUIT, TYPE C | 8 FT | $519 | $102 | $110 | $150 | $278 | $100 |
| 611E04400 12" CONDUIT, TYPE B | 20 FT | $613 | $131 | $122 | $150 | $387 | $190 |
| 611E04600 12" CONDUIT, TYPE C | 42 FT | $207 | $122 | $115 | $145 | $114 | $180 |
| 611E06100 15" CONDUIT, TYPE C | 8 FT | $529 | $155 | $120 | $170 | $257 | $200 |
| 611E07600 18" CONDUIT, TYPE C | 16 FT | $521 | $112 | $120 | $110 | $129 | $250 |
| 611E10600 24" CONDUIT, TYPE C | 8 FT | $601 | $153 | $205 | $195 | $313 | $900 |
| 611E21100 48" CONDUIT, TYPE C | 8 FT | $886 | $466 | $425 | $1,350 | $1,445 | $1,170 |
| 611E53004 38" X 60" CONDUIT, TYPE C, 706.04 | 8 FT | $1,016 | $714 | $715 | $1,600 | $3,190 | $1,315 |
| 611E98180 CATCH BASIN, NO. 3A | 1 EACH | $9,451 | $3,400 | $4,940 | $3,900 | $7,540 | $4,595 |
| 611E98344 CATCH BASIN, NO. 5A | 1 EACH | $15,783 | $10,000 | $17,800 | $22,000 | $14,500 | $22,045 |
| 611E98370 CATCH BASIN, NO. 6 | 1 EACH | $7,187 | $3,700 | $7,030 | $3,900 | $12,250 | $6,750 |
| 611E98644 CATCH BASIN GRATE | 1 EACH | $1,693 | $550 | $1,180 | $850 | $1,650 | $950 |
| 611E98690 CATCH BASIN, MISC.: CITY OF CLEVELAND CB-1 CATCH B | 1 EACH | $5,598 | $5,500 | $6,295 | $5,300 | $8,750 | $4,735 |
| 611E98711 INLET, NO. 2-6, AS PER PLAN | 4 EACH | $4,024 | $4,800 | $5,360 | $8,500 | $13,000 | $7,865 |
| 255E20000 FULL DEPTH PAVEMENT SAWING | 1,201 FT | $3.36 | $3.50 | $1.80 | $2.00 | $1.80 | $4.00 |
| 441E70801 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 449 (21 CY | $662 | $420 | $850 | $750 | $907 | $825 |
| 451E10010 6" REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 5 SY | $564 | $230 | $1,095 | $565 | $865 | $160 |
| 609E14000 CURB, TYPE 2-A | 1,728 FT | $7.24 | $2.75 | $7.65 | $7.00 | $8.50 | $6.00 |
| 609E54000 6" CONCRETE TRAFFIC ISLAND | 176 SY | $82.46 | $68.50 | $82.50 | $63.00 | $21.00 | $119 |
| 621E00100 RPM | 193 EACH | $89.45 | $83.76 | $65.00 | $80.00 | $86.60 | $125 |
| 626E00110 BARRIER REFLECTOR, TYPE 2, ONE-WAY | 6 EACH | $12.32 | $11.00 | $11.00 | $11.00 | $11.00 | $15.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 651.5 FT | $13.44 | $12.50 | $12.00 | $7.50 | $12.50 | $16.50 |
| 630E08004 ONE WAY SUPPORT, NO. 3 POST | 88.2 FT | $15.68 | $15.00 | $14.00 | $12.15 | $15.00 | $16.50 |
| 630E08600 SIGN POST REFLECTOR | 44 EACH | $61.60 | $35.00 | $55.00 | $22.00 | $35.00 | $61.00 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 2 EACH | $140 | $100 | $125 | $76.00 | $100 | $116 |
| 630E80100 SIGN, FLAT SHEET | 379.5 SF | $15.68 | $25.00 | $14.00 | $13.80 | $25.00 | $20.00 |
| 630E81010 RAMP REFERENCE MARKER | 1 EACH | $101 | $150 | $90.00 | $58.00 | $150 | $200 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 56 EACH | $22.40 | $15.00 | $20.00 | $22.40 | $15.00 | $18.00 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 1 EACH | $95.20 | $15.00 | $85.00 | $47.00 | $15.00 | $65.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 52 EACH | $33.60 | $15.00 | $30.00 | $24.00 | $15.00 | $22.10 |
| 630E87500 REMOVAL OF POLE MOUNTED SIGN AND DISPOSAL | 2 EACH | $22.40 | $50.00 | $20.00 | $64.00 | $50.00 | $20.00 |
| 646E10010 EDGE LINE, 6" | 1.14 MILE | $5,432 | $5,500 | $4,850 | $5,455 | $5,500 | $5,500 |
| 646E10310 CHANNELIZING LINE, 12" | 3,273 FT | $2.80 | $3.50 | $2.50 | $2.65 | $3.50 | $2.75 |
| 646E10400 STOP LINE | 145 FT | $13.44 | $15.00 | $12.00 | $17.05 | $15.00 | $18.00 |
| 646E10510 CROSSWALK LINE, 12" | 363 FT | $6.72 | $12.50 | $6.00 | $8.10 | $12.50 | $8.50 |
| 646E20300 LANE ARROW | 64 EACH | $174 | $200 | $185 | $225 | $200 | $225 |
| 646E20320 WRONG WAY ARROW | 4 EACH | $207 | $350 | $185 | $500 | $350 | $500 |
| 646E20506 DOTTED LINE, 8" | 143 FT | $5.60 | $2.50 | $5.00 | $2.50 | $2.50 | $2.50 |
| 625E31600 PULL BOX, MISC.:PULL BOX ADJUSTED TO GRADE | 5 EACH | $336 | $385 | $30.00 | $385 | $850 | $450 |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 3 EACH | $1,680 | $1,850 | $1,500 | $1,850 | $1,076 | $1,950 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 100 HOUR | $112 | $100 | $100 | $100 | $102 | $85.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 18 SNMT | $896 | $800 | $1,200 | $735 | $800 | $1,025 |
| 614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I | 0.39 MILE | $15,264 | $32,500 | $15,000 | $12,000 | $32,500 | $34,500 |
| 614E24402 WORK ZONE DOTTED LINE, CLASS I, 6", 740.06, TYPE I | 1,440 FT | $1.70 | $1.00 | $5.00 | $1.30 | $1.00 | $1.55 |
| 616E10000 WATER | 6 MGAL | $102 | $50.00 | $50.00 | $50.00 | $115 | $10.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,082 | $15,000 | $35,000 | $20,000 | $20,000 | $18,500 |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 12 MNTH | $1,445 | $3,000 | $2,230 | $3,750 | $3,125 | $4,850 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $7,258 | $3,240 | $6,500 | $1,000 | $4,500 | $3,200 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $7,258 | $3,000 | $6,500 | $1,000 | $4,500 | $3,800 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 452E14120 11" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 9,497 SY | $83.53 | $793k | 31% |
| 452E14022 10.5" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1 | 2,125 SY | $105.31 | $224k | 9% |
| 304E20000 AGGREGATE BASE | 2,209 CY | $71.99 | $159k | 6% |
| 204E30010 GRANULAR MATERIAL, TYPE B | 2,189 CY | $64.65 | $142k | 5% |
| 202E23000 PAVEMENT REMOVED | 13,399 SY | $8 | $107k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100k | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $75,000 | $75k | 3% |
| 204E13000 EXCAVATION OF SUBGRADE | 2,189 CY | $29.06 | $64k | 2% |
| 832E30000 EROSION CONTROL | 54,277 EACH | $1 | $54k | 2% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $51,120 | $51k | 2% |