CUY-SR 91-07.73
CUY County · est $1.0M
Bid dateThursday, March 22—
CUY County · est $1.0M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 6.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 30 more items below.
| Item | Quantity | R1Chagrin Valley Paving INC | R2Ronyak Paving INC | R3Burton Scot Contractors LLC | R4Barbicas Construction Company INC | R5Karvo Companies INC | R6Shelly Company | R7Kokosing Construction Company INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 2,093 CY | $143 | $142 | $144 | $160 | $156 | $145 | $152 | 36% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (1401 CY | $120 | $125 | $135 | $150 | $130 | $130 | $132 | 20% |
| Item | Quantity | R1Chagrin Valley Paving INC | R2Ronyak Paving INC | R3Burton Scot Contractors LLC | R4Barbicas Construction Company INC | R5Karvo Companies INC | R6Shelly Company | R7Kokosing Construction Company INC |
|---|---|---|---|---|---|---|---|---|
| 209E72051 PREPARING SUBGRADE FOR SHOULDER PAVING, AS PER PLA | 4.56 MILE | $500 | $350 | $950 | $500 | $1,550 | $1,100 | $1,525 |
| 623E39501 MONUMENT BOX ADJUSTED TO GRADE, AS PER PLAN | 7 EACH | $600 | $500 | $450 | $350 | $575 | $600 | $500 |
| 623E39600 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 810 CY |
| $150 |
| $154 |
| $190 |
| $165 |
| $195 |
| $210 |
| $260 |
| 15% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $70,000 | $38,200 | $40,000 | $34,500 | $70,000 | $115,000 | $81,050 | 8% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 21 EACH | $850 | $600 | $700 | $650 | $875 | $800 | $600 | 2% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 1 | 9,667 SY | $1.80 | $2.75 | $2.00 | $2.40 | $2.65 | $2.45 | $3.05 | 2% |
| 624E10000 MOBILIZATION | 1 LS | $17,000 | $29,500 | $20,000 | $10,000 | $25,000 | $40,000 | $20,000 | 2% |
| 407E20000 NON-TRACKING TACK COAT | 7,562 GAL | $2.00 | $2.20 | $2.00 | $3.65 | $2.75 | $2.85 | $2.35 | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 297 CY | $45.00 | $52.50 | $40.00 | $60.00 | $58.00 | $65.00 | $75.00 | 2% |
| 646E10010 EDGE LINE, 6" | 4.78 MILE | $2,450 | $2,450 | $2,450 | $2,944 | $2,944 | $2,450 | $2,450 | 1% |
| 441E50101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), AS | 55 CY | $210 | $410 | $250 | $250 | $240 | $200 | $350 | 1% |
| 251E01000 PARTIAL DEPTH PAVEMENT REPAIR (441) | 200 SY | $50.00 | $61.00 | $45.00 | $30.00 | $54.00 | $170 | $75.00 | 1% |
| 441E50400 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448) | — | $210 | $550 | $250 | $250 | $225 | $250 | $350 | 1% |
| 646E10200 CENTER LINE | 2.74 MILE | $3,400 | $3,400 | $3,400 | $3,550 | $3,550 | $3,400 | $3,400 | 1% |
| 875E10000 LONGITUDINAL JOINT ADHESIVE | 7,054 LB | $1.00 | $0.95 | $1.00 | $1.00 | $1.30 | $1.15 | $0.80 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $7,000 | $7,200 | $8,950 | $6,500 | $5,300 | $3,000 | $4,500 | 1% |
| 621E00100 RPM | 274 EACH | $24.14 | $25.80 | $25.80 | $25.80 | $24.14 | $24.14 | $24.14 | 1% |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 4,000 LB | $1.50 | $1.25 | $1.25 | $1.25 | $1.00 | $1.50 | $1.25 | 1% |
| 632E26501 DETECTOR LOOP, AS PER PLAN | 5 EACH | $1,100 | $1,100 | $1,100 | $1,275 | $1,200 | $1,100 | $1,300 | 1% |
| 630E97800 SIGNING, MISC.: ADDITIONAL SIGNS, GROUND MOUNTED, | 300 SF | $17.50 | $17.50 | $20.00 | $17.50 | $17.50 | $17.50 | $17.50 | 1% |
| 2 EACH |
| $650 |
| $650 |
| $1,000 |
| $400 |
| $650 |
| $650 |
| $650 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E98634 CATCH BASIN RECONSTRUCTED TO GRADE | 5 EACH | $950 | $1,150 | $1,100 | $850 | $975 | $950 | $1,150 |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 5 EACH | $850 | $575 | $625 | $500 | $800 | $800 | $575 |
| 611E99660 MANHOLE RECONSTRUCTED TO GRADE | 2 EACH | $950 | $1,100 | $950 | $800 | $950 | $900 | $1,100 |
| 254E01011 PAVEMENT PLANING, PORTLAND CEMENT CONCRETE, AS PER | 331 SY | $10.00 | $28.00 | $9.00 | $3.25 | $7.00 | $3.50 | $53.00 |
| 304E20000 AGGREGATE BASE | 50 CY | $30.00 | $27.50 | $45.00 | $45.00 | $35.00 | $35.00 | $45.00 |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 5 EACH | $600 | $450 | $280 | $100 | $545 | $600 | $450 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 150 EACH | $1.00 | $10.00 | $10.00 | $5.00 | $2.00 | $4.00 | $23.00 |
| 646E10400 STOP LINE | 156 FT | $12.00 | $12.00 | $12.00 | $11.00 | $11.00 | $12.00 | $12.00 |
| 646E20300 LANE ARROW | 1 EACH | $155 | $155 | $155 | $170 | $170 | $155 | $155 |
| 646E20504 DOTTED LINE, 6" | 25 FT | $4.00 | $4.00 | $4.00 | $8.00 | $8.00 | $4.00 | $4.00 |
| 646E20600 BIKE LANE SYMBOL MARKING | 1 EACH | $205 | $205 | $205 | $200 | $200 | $205 | $205 |
| 690E98400 SPECIAL - INVENTORY EXISTING PAVEMENT MARKINGS | 1 LS | $500 | $500 | $500 | $625 | $625 | $500 | $500 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $75.00 | $45.00 | $59.00 | $65.00 | $65.00 | $65.00 | $60.00 |
| 614E12460 WORK ZONE MARKING SIGN | 20 EACH | $88.00 | $88.00 | $20.00 | $60.00 | $88.00 | $88.00 | $88.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 25 CY | $50.00 | $150 | $180 | $125 | $210 | $125 | $100 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 4 SNMT | $915 | $915 | $1,050 | $915 | $915 | $915 | $915 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 3.09 MILE | $800 | $800 | $800 | $1,050 | $1,050 | $800 | $800 |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 2.74 MILE | $750 | $750 | $750 | $850 | $850 | $750 | $750 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 4.78 MILE | $550 | $550 | $550 | $725 | $725 | $550 | $550 |
| 614E22360 WORK ZONE EDGE LINE, CLASS III, 6", 642 PAINT | 4.78 MILE | $525 | $525 | $525 | $575 | $575 | $525 | $525 |
| 614E24201 WORK ZONE DOTTED LINE, CLASS I, 642 PAINT, AS PER | 25 FT | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 614E24610 WORK ZONE DOTTED LINE, CLASS III, 642 PAINT | 25 FT | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 231 FT | $3.00 | $3.00 | $3.00 | $3.25 | $3.25 | $3.00 | $3.00 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 156 FT | $3.00 | $3.00 | $3.00 | $3.25 | $3.25 | $3.00 | $3.00 |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 6 MNTH | $500 | $1,500 | $1,000 | $600 | $1,750 | $2,350 | $1,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $500 | $1,000 | $1,870 | $500 | $1,200 | $3,150 | $1,800 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 441E10101 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), AS | 2,093 CY | $143 | $299k | 34% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (1401 CY | $120 | $168k | 19% |
| 253E02000 PAVEMENT REPAIR | 810 CY | $150 | $122k | 14% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $70,000 | $70k | 8% |
| 611E98631 CATCH BASIN ADJUSTED TO GRADE, AS PER PLAN | 21 EACH | $850 | $18k | 2% |
| 254E01001 PAVEMENT PLANING, ASPHALT CONCRETE, AS PER PLAN, 1 | 9,667 SY | $1.8 | $17k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $17,000 | $17k | 2% |
| 407E20000 NON-TRACKING TACK COAT | 7,562 GAL | $2 | $15k | 2% |
| 617E10101 COMPACTED AGGREGATE, AS PER PLAN | 297 CY | $45 | $13k | 2% |
| 646E10010 EDGE LINE, 6" | 4.78 MILE | $2,450 | $12k | 1% |