MRW-CR 15-05.01
MRW County · est $1.1M
Bid dateThursday, February 1—
MRW County · est $1.1M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 8.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 12 more items below.
| Item | Quantity | R1V O Menuez & Son INC | R2Shelly & Sands INC | R3R & I Construction INC | R4Righter Company INC | R5Eagle Bridge CO | R6Rietschlin Construction INC | R7Buds INC | R8Crawford Construction Company INC | R9Miller Bros Const INC | R10Ruhlin Company | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 530E99020 SPECIAL - SUPERSTRUCTURE | 1 LS | $347,286 | $310,800 | $348,500 | $250,000 | $292,000 | $306,092 | $235,000 | $275,000 | $324,000 | $295,000 | 35% |
| 400E99000 |
| Item | Quantity | R1V O Menuez & Son INC | R2Shelly & Sands INC | R3R & I Construction INC | R4Righter Company INC | R5Eagle Bridge CO | R6Rietschlin Construction INC | R7Buds INC | R8Crawford Construction Company INC | R9Miller Bros Const INC | R10Ruhlin Company |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 202E98200 REMOVAL MISC.:DECORATIVE RETAINING WALL REMOVED AN | 25 FT | $125 | $61.00 | $100 | $100 | $90.00 | $265 | $100 | $310 | $60.00 | $100 |
| 623E38500 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $111,218 |
| $86,000 |
| $125,000 |
| $135,000 |
| $40,000 |
| $122,841 |
| $109,000 |
| $115,000 |
| $85,000 |
| $107,500 |
| 11% |
| 203E99000 SPECIAL - EARTHWORK | 1 LS | $104,150 | $134,000 | $111,000 | $85,000 | $125,000 | $125,661 | $111,000 | $90,290 | $90,000 | $165,000 | 10% |
| 530E99010 SPECIAL - SUBSTRUCTURE | 1 LS | $92,640 | $134,000 | $125,000 | $165,300 | $115,000 | $167,717 | $235,000 | $220,000 | $158,000 | $141,800 | 9% |
| 202E99000 SPECIAL - STRUCTURE REMOVED | 1 LS | $66,000 | $40,280 | $60,000 | $65,000 | $85,000 | $52,000 | $45,000 | $41,500 | $60,000 | $90,000 | 7% |
| 300E99000 SPECIAL - BASES | 1 LS | $64,351 | $31,200 | $35,000 | $35,000 | $80,000 | $26,397 | $100,000 | $79,500 | $80,000 | $70,000 | 6% |
| 201E99000 SPECIAL - CLEARING AND GRUBBING | 1 LS | $32,328 | $16,000 | $20,000 | $35,000 | $25,000 | $31,700 | $16,000 | $33,000 | $60,000 | $25,000 | 3% |
| 107E99000 SPECIAL - UTILITY COORDINATION | 1 LS | $22,000 | $520 | $6,500 | $5,000 | $10,000 | $8,200 | $3,000 | $8,000 | $3,000 | $2,000 | 2% |
| 690E20050 SPECIAL - FINAL DESIGN | 1 LS | $20,100 | $23,000 | $34,000 | $13,000 | $32,500 | $11,700 | $22,000 | $20,000 | $30,000 | $51,000 | 2% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $20,000 | $40,000 | $45,000 | $40,000 | $40,000 | $32,000 | $25,000 | $28,000 | $40,000 | $40,000 | 2% |
| 606E99000 SPECIAL - GUARDRAIL | 1 LS | $19,708 | $46,000 | $15,000 | $20,000 | $40,000 | $21,555 | $45,000 | $20,925 | $20,500 | $20,000 | 2% |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $16,800 | $7,000 | $5,000 | $10,000 | $9,000 | $10,500 | $5,000 | $19,400 | $4,500 | $15,000 | 2% |
| 832E99100 SPECIAL - CONSTRUCTION EROSION CONTROL | 15,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 690E20040 SPECIAL - PRELIMINARY DESIGN | 1 LS | $13,800 | $26,000 | $15,000 | $35,000 | $25,000 | $27,100 | $45,000 | $42,000 | $50,000 | $31,000 | 1% |
| 623E99000 SPECIAL - CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $11,880 | $16,000 | $4,000 | $15,000 | $8,500 | $4,860 | $7,000 | $4,500 | $10,000 | $9,500 | 1% |
| 103E99010 SPECIAL - PREMIUM FOR CONTRACT PERFORMANCE BOND AN | 1 LS | $11,675 | $6,800 | $10,000 | $16,500 | $12,500 | $9,500 | $13,000 | $9,200 | $12,000 | $8,500 | 1% |
| 611E97800 SPECIAL - DRAINAGE | 1 LS | $10,182 | $23,500 | $10,000 | $15,000 | $13,500 | $15,736 | $2,000 | $19,000 | $15,000 | $13,500 | 1% |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $8,376 | $1,200 | $1,500 | $2,000 | $7,500 | $2,500 | $5,000 | $1,200 | $1,500 | $1,500 | 1% |
| 614E99000 SPECIAL - MAINTAINING TRAFFIC | 1 LS | $8,140 | $4,800 | $7,000 | $15,000 | $15,000 | $7,020 | $5,000 | $5,000 | $7,500 | $25,000 | 1% |
| 619E16000 FIELD OFFICE, TYPE A | 6 MNTH | $1,150 | $2,600 | $300 | $750 | $1,500 | $1,400 | $750 | $2,200 | $1,500 | $3,000 | 1% |
| 2 EACH |
| $845 |
| $1,750 |
| $500 |
| $750 |
| $1,500 |
| $775 |
| $1,500 |
| $1,600 |
| $1,000 |
| $750 |
| 659E99000 SPECIAL - PERMANENT EROSION CONTROL | 1 LS | $6,523 | $22,000 | $27,000 | $45,000 | $35,000 | $42,840 | $25,000 | $24,025 | $30,000 | $36,000 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $2,450 | $10,300 | $17,000 | $5,000 | $9,500 | $10,500 | $2,000 | $15,500 | $9,000 | $11,500 |
| 630E99000 SPECIAL - SIGNS AND SUPPORTS | 1 LS | $1,953 | $4,300 | $200 | $2,000 | $2,000 | $1,766 | $1,000 | $1,300 | $2,000 | $2,000 |
| 640E99000 SPECIAL - PAVEMENT MARKING | 1 LS | $2,300 | $1,700 | $2,000 | $2,000 | $2,500 | $2,950 | $5,000 | $2,400 | $2,000 | $2,500 |
| 512E99000 SPECIAL - SEALING OF CONCRETE | 1 LS | $1,979 | $3,600 | $3,000 | $3,000 | $6,000 | $2,754 | $4,000 | $3,600 | $3,000 | $1,500 |
| 690E20010 SPECIAL - AS-BUILT CONSTRUCTION PLANS | 1 LS | $2,600 | $3,200 | $2,000 | $5,000 | $1,500 | $985 | $3,000 | $3,000 | $3,000 | $4,500 |
| 690E20020 SPECIAL - FIELD SURVEYS | 1 LS | $1,100 | $770 | $1,500 | $3,645 | $1.00 | $3,800 | $16,000 | $12,000 | $15,000 | $5,500 |
| 690E20080 SPECIAL - SUBSURFACE INVESTIGATIONS | 1 LS | $600 | $100 | $500 | $10,000 | $220 | $540 | $3,000 | $3,000 | $3,000 | $6,000 |
| 100E99010 SPECIAL - PROFESSIONAL LIABILITY INSURANCE | 1 LS | $1.00 | $105 | $1.00 | $1,000 | $1,500 | $540 | $3,000 | $3,000 | $3,000 | $1.00 |
| 108E99100 SPECIAL - CPM PROGRESS SCHEDULE FOR SHORT DURATION | 1 LS | $3,135 | $1,700 | $2,000 | $2,000 | $1,500 | $2,700 | $5,000 | $4,000 | $500 | $2,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 530E99020 SPECIAL - SUPERSTRUCTURE | 1 LS | $347,286 | $347k | 34% |
| 400E99000 SPECIAL - FLEXIBLE PAVEMENT | 1 LS | $111,218 | $111k | 11% |
| 203E99000 SPECIAL - EARTHWORK | 1 LS | $104,150 | $104k | 10% |
| 530E99010 SPECIAL - SUBSTRUCTURE | 1 LS | $92,640 | $93k | 9% |
| 202E99000 SPECIAL - STRUCTURE REMOVED | 1 LS | $66,000 | $66k | 6% |
| 300E99000 SPECIAL - BASES | 1 LS | $64,351 | $64k | 6% |
| 201E99000 SPECIAL - CLEARING AND GRUBBING | 1 LS | $32,328 | $32k | 3% |
| 107E99000 SPECIAL - UTILITY COORDINATION | 1 LS | $22,000 | $22k | 2% |
| 690E20050 SPECIAL - FINAL DESIGN | 1 LS | $20,100 | $20k | 2% |
| 624E99000 SPECIAL - MOBILIZATION | 1 LS | $20,000 | $20k | 2% |